Nokia Solutions and Networks WTFA-01 GSM 800 Transciever User Manual dn991456x3x0xen

Nokia Solutions and Networks GSM 800 Transciever dn991456x3x0xen

Installation

Nokia MetroSite EDGE Base StationDN991456 © Nokia Corporation 1 (72)Issue 3 en Nokia Proprietary and ConfidentialInstallation
Installation2 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enThe information in this documentation is subject to change without notice and describes onlythe product defined in the introduction of this documentation. This documentation is intendedfor the use of Nokia's customers only for the purposes of the agreement under which thedocumentation is submitted, and no part of it may be reproduced or transmitted in any form ormeans without the prior written permission of Nokia. The documentation has been prepared tobe used by professional and properly trained personnel, and the customer assumes fullresponsibility when using it. Nokia welcomes customer comments as part of the process ofcontinuous development and improvement of the documentation.The information or statements given in this documentation concerning the suitability, capacity,or performance of the mentioned hardware or software products cannot be considered bindingbut shall be defined in the agreement made between Nokia and the customer. However, Nokiahas made all reasonable efforts to ensure that the instructions contained in the documentationare adequate and free of material errors and omissions. Nokia will, if necessary, explain issueswhich may not be covered by the documentation.Nokia's liability for any errors in the documentation is limited to the documentary correction oferrors. NOKIA WILL NOT BE RESPONSIBLE IN ANY EVENT FOR ERRORS IN THISDOCUMENTATION OR FOR ANY DAMAGES, INCIDENTAL OR CONSEQUENTIAL(INCLUDING MONETARY LOSSES), that might arise from the use of this documentation orthe information in it.This documentation and the product it describes are considered protected by copyrightaccording to the applicable laws.NOKIA logo is a registered trademark of Nokia Corporation.Other product names mentioned in this documentation may be trademarks of their respectivecompanies, and they are mentioned for identification purposes only.Copyright © Nokia  Corporation 2002. All rights reserved.
DN991456 © Nokia Corporation 3 (72)Issue 3 en Nokia Proprietary and ConfidentialHereby, Nokia Corporation, declares that this product is in compliance with theessential requirements and other relevant provisions of Directive: 1999/5/EC.The product is marked with the CE marking and Notified Body number according to theDirective 1999/5/ECFCC FCC §15.21 - Information to user - This product is used as an intentional radiatedequipment and any changes or modifications on the equipment without any approvalby Nokia could void the user's authority to operate the equipment.FCC §15.105 - Information to user - This equipment has been tested and found tocomply with the limits for a Class B digital device, pursuant to part 15 of the FCCRules. These limits are designed to provide reasonable protection against harmfulinterference in a residential installation. This equipment generates, uses and canradiate radio frequency energy and, if not installed and used in accordance with theinstructions, may cause harmful interference to radio communications. However, thereis no guarantee that interference will not occur in a particular installation. If thisequipment does cause harmful interference to radio or television reception, which canbe determined by turning the equipment off and on, the user is encouraged to try tocorrect the interference by one or more of the following measures:• Reorient or relocate the receiving antenna.• Increase the separation between the equipment and receiver.• Connect the equipment into an outlet on a circuit different from that to which thereceiver is connected.• Consult the dealer or an experienced radio/TV technician for help.0523
Installation4 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en4 (20) © Nokia Corporation DN9990375Nokia Proprietary and Confidential Issue 3 en     For the MetroSite EDGE to be used in the USA and continue to meet the FCC certification granted, it must be noted that the following channels are blocked and can not be configured for use.For use in the GSM 1900 band:• Channel 512• Channel 585• Channel 586• Channel 587• Channel 610• Channel 611• Channel 612• Channel 685• Channel 686• Channel 687• Channel 710• Channel 711• Channel 712• Channel 735• Channel 736• Channel 737• Channel 810For use in the GSM 800 band:• Channel 128• Channel 181• Channel 182• Channel 183• Channel 231• Channel 232• Channel 233• Channel 239• Channel 240• Channel 251If these channels are not blocked from use the FCC certification will be invalid.
DN991456 © Nokia Corporation 5 (72)Issue 3 en Nokia Proprietary and ConfidentialContentsContents 5List of tables 6List of figures 71 About this document 112 Working order 133 Preparations for installation 153.1 Checking the delivery 153.2 Checking the site 153.2.1 BTS interfaces and cables 163.3 Installation equipment 164 Unpacking the delivery 194.1 Working order for unpacking 194.2 Contents of the BTS transportation package 214.3 Contents of the pole mounting kit 225 Removing the units 256 Mounting the BTS 296.1 Wall mounting 306.2 Pole mounting 346.2.1 Attaching the cabinet with the small-pole mounting kit 356.2.2 Attaching the cabinet with the large-pole mounting kit 417 Reinstalling the units 498 Cabinet cabling 518.1 Preparations for cabling 518.2 Grounding 538.3 Power supply 558.4 Transmission unit 588.4.1 FC E1/T1 transmission unit 588.4.2 FXC E1 transmission unit 608.4.3 FXC E1/T1 transmission unit 618.4.4 FXC RRI transmission unit 628.5 Interface unit 638.6 Transceiver units (TRXs) 648.7 Completing the cabling 669 Completing the installation 69Index 71
Installation6 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enList of tablesTable 1. Working order for installing the Nokia MetroSite EDGE Base Station 13Table 2. Installation equipment checklist 16Table 3. Pre-installation parts checklist 17Table 4. Checklist for contents of the transportation package for the NokiaMetroSite EDGE Base Station 21Table 5. Checklist for contents of the optional pole mounting kit 22Table 6. Parts required for wall mounting 30Table 7. Parts and pole diameters required for pole installation 34Table 8. Band length for different pole diameters 41
DN991456 © Nokia Corporation 7 (72)Issue 3 en Nokia Proprietary and ConfidentialList of figuresFigure 1. Contents of the Nokia MetroSite EDGE Base Station transportationpackage when unpacked 22Figure 2. Contents of the optional pole mounting kit 23Figure 3. Connecting the antistatic wrist strap before removing any units 25Figure 4. Removing the units 27Figure 5. Mounting rack dimensions and screw holes 29Figure 6. Cardboard template for aligning wall mounting screw holes 31Figure 7. Wall mounting 33Figure 8. Bracket blocks for pole mounting 35Figure 9. Pre-assembling the pole brackets 36Figure 10. Attaching the mounting rack and the pole brackets 38Figure 11. Pole mounting with the small-pole mounting kit 40Figure 12. Pole bracket pre-assembled (large-pole mounting kit) 42Figure 13. Pole bracket pre-assembled (large-pole mounting kit) 43Figure 14. Attaching the mounting rack and the pole brackets 45Figure 15. Pole mounting with large-pole mounting kit 47Figure 16. Displacing the sealing strip and removing the cable entry blockscrews 52Figure 17. Cable routing through the cable entry block 53Figure 18. Grounding connector alternatives 54Figure 19. Power supply unit and power connector alternatives 57Figure 20. Cabling alternatives for the FC E1/T1 transmission unit 59Figure 21. Cabling of the FXC E1 transmission unit 60Figure 22. Cabling of the FXC E1/T1 transmission unit 61Figure 23. Cabling of the FXC RRI transmission unit 62Figure 24. Cabling of the interface unit 63Figure 25. Examples of diversity cabling alternatives 65Figure 26. Routing the cables and closing the cable cover 67Figure 27. Hanging the BTS cover 70
Installation8 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
DN991456 © Nokia Corporation 9 (72)Issue 3 en Nokia Proprietary and ConfidentialSummary of changesVersion 1, 12th November 1999Version 2, 22nd June 2000:• Changed title• Added GSM reference to body text• Added CE marking• Removed RX diversity cable from 2+1 TRX of Figure 24• Edited Figure 26• Removed note from alternative 1 procedure in Chapter 6.3.2• Added BTS safety strap to Figure 1 and to list in Chapter 2.1Version 3, 18th April 2001:• Updated for EDGE• Document restructuredVersion 3.1, July/October 2002:• Modifications to pole mounting kit incorporated (two types of band andlocking device)• Note added about horizontal mounting of WCUA cover
Installation10 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
About this documentDN991456 © Nokia Corporation 11 (72)Issue 3 en Nokia Proprietary and ConfidentialCaution1About this documentThis document describes the installation of the Nokia MetroSiteTM EDGE BaseStation from delivery of the BTS package to the site to BTS commissioning. Readcarefully Nokia MetroSite EDGE Base Station: Warnings and Cautions andNokia MetroSite EDGE Base Station: Requirements for Installation andOperation before starting the installation.The following information can be found in this document:• Working order for installation• Preparations before installation• Tools and parts required• How to safely unpack the delivery• Contents of the BTS delivery• How to remove and reinstall units• How to install the BTS on a wall or a pole• How to cable the BTS• Completing the installation after commissioningInstallation, commissioning and maintenance of the Nokia MetroSite EDGE BaseStation (BTS) may be performed only by trained and authorised personnel.
Installation12 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
Working orderDN991456 © Nokia Corporation 13 (72)Issue 3 en Nokia Proprietary and ConfidentialNote2Working orderThe Nokia MetroSite EDGE Base Station is installed upright on a pole or a wall.Pole mounting requires a pole mounting kit, which is ordered separately whenrequired. The BTS can also be installed horizontally on its back.Horizontal mounting of the Nokia MetroSite EDGE Base Station is only suitablefor certain site conditions and countries. Contact your Nokia dealer for advice.Refer to Table 1for the working order and location of instructions for installingthe Nokia MetroSite EDGE Base Station. Removing the units before mounting isoptional, depending on the number of installation personnel on the site.Table 1. Working order for installing the Nokia MetroSite EDGE BaseStationActivity InstructionsPreparations for installation Chapter 3Unpacking and checking the delivery Chapter 4Removing units to reduce weight whenmounting the cabinet (optional)Chapter 5Mounting the BTS on a pole or wall Chapter 6Reinstalling units Chapter 7Cabling the BTS Chapter 8Completing the installation Chapter 9
Installation14 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
Preparations for installationDN991456 © Nokia Corporation 15 (72)Issue 3 en Nokia Proprietary and ConfidentialNoteCaution3Preparations for installationBefore beginning installation, check the delivery, the site, and the required toolsand extra parts against the relevant checklists.The installation of the Nokia MetroSite EDGE Base Station can be carried out byone person if units are removed before mounting the cabinet. However, it requiresat least two people to lift a BTS with its units installed.Use only trained and authorised personnel for installing and commissioning theNokia MetroSite EDGE Base Station.3.1 Checking the deliveryBefore unpacking any of the packages, check that the delivery is correct. Confirmthat the delivery notes on each package agree with the order note.3.2 Checking the siteThe BTS site has been planned and prepared according to the specifications givenin Nokia MetroSite EDGE Base Station: Requirements for Installation andOperation. Before beginning installation, check the site against thesespecifications using a site preparation checklist.If the site conditions do not conform to the checklist, stop the installation at thisstage and return to the site preparation procedures.
Installation16 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNote3.2.1 BTS interfaces and cablesDepending on the site solution, check that the appropriate interface units andcables are on the site if cabling is to be completed during one installation. Detailsof the required connectors and cables are found in Nokia MetroSite EDGE BaseStation: Requirements for Installation and Operation.Diversity cables are delivered with the BTS in the transportation package.3.3 Installation equipmentMake sure that all the necessary installation equipment is available on the sitebefore beginning installation. Refer to Table 2 for tools and Table 3 for parts.Detailed information on the installation equipment can be found in NokiaMetroSite EDGE Base Station: Requirements for Installation and Operation.Table 2. Installation equipment checklistTool NotesTorque driver with 60 mm shaft and:• T10 Torx bit• 4 mm Allen bitRequired for:• Unit retaining screws• BTS fixing screws, cable entry blockscrews, ground cable fixingTorque socket spanner/wrench with 80mm extension shaft and:• 6 mm Allen bit• 8 mm hexagon socket• 10 mm hexagon socketRequired for:• Bolts in pole brackets, L-beamscrews• Locking device for pole brackets,grounding cable nut• Removing grounding bridges ontransmission unitsTorque key For attaching diversity cablesSide cutting pliers For cutting cable ties and preparinggrounding cable for crimp terminalCrimping tool For attaching crimp connector to cable ingrounding alternative 1
Preparations for installationDN991456 © Nokia Corporation 17 (72)Issue 3 en Nokia Proprietary and ConfidentialTable 3. Pre-installation parts checklistPart NotesBTS transportation package Confirm that the correct package hasbeen deliveredOptional pole mounting kit For pole mounting, ordered from Nokiaif requiredBTS interfaces and cables Depending on the site solutionWall screws and anchor plugs Supplied by installer for wall mounting,refer to Table 6 for screw specificationsFlat crimp terminal Supplied by installer for attachinggrounding cable to grounding point,alternative 1Cable shoe terminal Supplied by installer for attachinggrounding cable to grounding point,alternative 2Plastic cable ties supplied by installer for securing cablerouting out of the BTS
Installation18 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
Unpacking the deliveryDN991456 © Nokia Corporation 19 (72)Issue 3 en Nokia Proprietary and ConfidentialWARNING4Unpacking the deliveryThe Nokia MetroSite EDGE Base Station is delivered in a transportation packagewith all the ordered units pre-installed in the chassis. . The transportation packagealso includes equipment needed in the installation of the base station.A pole mounting kit is required if the BTS will be mounted on a pole. This isordered and delivered separately if needed.Lifting a BTS complete with units requires at least two people. The NokiaMetroSite EDGE Base Station weighs 28 to 40 kg (62 to 88 lb), depending onthe number of TRXs installed.4.1 Working order for unpackingThe procedures for unpacking include careful checking of the condition andcontents of the delivery. If any defects or missing parts are noticed, theinstallation should be stopped and replacement parts ordered.The following procedures should be followed in sequence.Check the contents of the pole mounting kit• If pole mounting is being used, check the completeness of the polemounting kit against the checklist in Table 5.Remove the BTS from the packaging1. Remove the plastic wrapping from the BTS transportation package.
Installation20 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNote2. Lift the BTS out of the package and lay it horizontally. Do not stand theBTS in a vertical position. Lay the BTS onto a clean or covered surface, notdirectly onto the ground.3. Save the packing cardboard from the package! The cardboard can be usedas a template for defining clearances around the BTS and for marking drillhole locations for wall installation.Check the contents of the BTS transportation package1. Check the completeness of the delivery against the general contentschecklist in Table 4.2. Visually inspect the cover of the BTS for any defects.Remove the BTS cover1. Inspect the cover visually for defects before removing it.2. Open the lock on the bottom of the BTS using the key provided. The keywill remain in the lock whenever the lock is in the open position.3. Loosen the cover by sliding it along the chassis to disengage the hookswhich hold it in place. Lift the cover off when the hooks are disengaged.Check the BTS1. Check the completeness of the delivery against the order specifications toconfirm that the delivery contains the correct unit types.2. Visually inspect the interior of the BTS for any defects.The unused connectors on the units are protected with rubber caps. Leave the capon the connector if the connector is not going to be used for cabling.
Unpacking the deliveryDN991456 © Nokia Corporation 21 (72)Issue 3 en Nokia Proprietary and ConfidentialRemove the mounting rack1. Make sure that you have removed the BTS cover and prepared a cleansurface for working on the BTS.2. Turn the BTS over and lay it flat on its front.3. The mounting rack is attached to the back of the BTS for transportation. Itmust be removed before continuing with installation. The mounting rackcan be seen in detail in Figure 7. Loosen the offset screws on the bottomand the top of the mounting rack: on the L-beam and screws B1 and B2. Donot remove the screws completely.4. Remove the wooden spacer blocks and the mounting rack.4.2 Contents of the BTS transportation packageRefer to Table 4 and Figure 1 for the contents of the transportation package forthe Nokia MetroSite EDGE Base Station.Table 4. Checklist for contents of the transportation package for the NokiaMetroSite EDGE Base StationPart NotesBTS chassis with the ordered units pre-installed.Shield units are installed in the slots thatare not populated with functional unitsBTS coverT-shaped mounting rack Provides the fixing base for the BTSTwo Allen screws, M6 x 20 For fixing the BTS to the mounting rackCable cover For cables routed out of the BTSCable cover support Mounting for the cable coverDiversity cablesSafety strap For securing the cover to the chassisFour unit retaining screws Spare partsSpare counterparts for the unit retainingscrewsAttached to the uppermost TRX guidebeam on the top of the BTSKey for BTS lock
Installation22 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFigure 1. Contents of the Nokia MetroSite EDGE Base Station transportationpackage when unpacked4.3 Contents of the pole mounting kitThe pole mounting kit is ordered as an option when required. Refer to Table 5 andFigure 2 for the contents of the pole mounting kit.Nokia MetroSite BTScover and chassiswith the ordered unitsCable cover support4 unit retainingscrews(spare parts)Mounting rackCable coverU-plateWasherSafety strapTable 5. Checklist for contents of the optional pole mounting kitPart NotesTwo front bracket blocks Upper and lower bracket blocks areidentical.Two back bracket blocks Upper and lower bracket blocks areidentical.Four Allen screws, M6 x 20 For fixing the front bracket blocks to themounting rack.Four long bolts, M8 x 120 For fixing the back block to the frontblock (smaller diameter poles).
Unpacking the deliveryDN991456 © Nokia Corporation 23 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 2. Contents of the optional pole mounting kitFour flat washersFour flat, square nuts, 20 x 20 x 4 mm For fixing the back bracket block to thefront bracket block (smaller diameterpoles).Two metal bands 1010 mm (39.8 in.) For fixing the front bracket block to thepole (larger diameter poles).Two locking devices Worm drive clamps with hexagonnut/screw, for tightening the metal bandto the pole (larger diameter poles). Thereare two types of locking device, asdescribed in Section 6.2.2.Table 5. Checklist for contents of the optional pole mounting kit (Continued)Part NotesBack blocksFront  blocksMetal bandsLocking deviceAllen screws(M6x20)M8x120 boltsSquare nuts20x20x4 mmWashersDN0245446
Installation24 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
Removing the unitsDN991456 © Nokia Corporation 25 (72)Issue 3 en Nokia Proprietary and ConfidentialCaution5Removing the unitsUnits can be removed from the chassis in order to make the BTS easier to handleduring installation. The TRXs are the heaviest units, weighing approximately 4.5kg (9.9 lb) each. Do not remove the shield units.Always use the antistatic wrist strap  when removing or installing the units. Formore information on electro-static discharge protection, refer to Nokia MetroSiteEDGE Base Station: Warnings and Cautions. The wrist strap and the connectionpoint are shown in Figure 3.Figure 3. Connecting the antistatic wrist strap before removing any unitsESD studto ESD studWrist strap
Installation26 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNoteCautionRemoving a unit1. Lay the BTS on its back, in the position shown in Figure 4.2. Loosen the upper and lower retaining screws of the unit to be removedusing a torque driver with a T10 Torx bit.Loosen the screws enough to remove the unit, but leave them engaged inthe threads. By doing this, the screws remain in the optimal position forreconnecting.3. Slide the TRX units out of the slots by pulling from the handle on the frontpanel of the TRX.4. Remove the power supply unit, interface unit, and transmission unit bypulling each unit out until it comes to a stop. Then lift the unit upwards andoutwards to remove it. See Figure 4.If the unit does not come out easily, rock it slightly from left to right using thehandle and then pull the unit out. Do not use excessive force!When handling the units, beware of sharp edges!
Removing the unitsDN991456 © Nokia Corporation 27 (72)Issue 3 en Nokia Proprietary and ConfidentialCautionFigure 4. Removing the unitsHandle the units with care. Do not knock the units or place them with theirconnectors facing the ground. Prevent dirt, water, or snow from entering theconnectors.Power supply unitInterface unitTransmission unitTransceiver unitsUnit retainingscrews
Installation28 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
Mounting the BTSDN991456 © Nokia Corporation 29 (72)Issue 3 en Nokia Proprietary and Confidential6Mounting the BTSThe mounting rack is used in both wall and pole installations to provide a fixingbase for the Nokia MetroSite EDGE Base Station. The dimensions of themounting rack are presented in Figure 5. Screw holes R1, R2, R3, R4, R5, and R6are for fixing the mounting rack onto the wall or the pole bracket. Screw holes B1and B2 are used for fixing the BTS to the mounting rack.Figure 5. Mounting rack dimensions and screw holesNOTE: DIMENSIONS mm (inch)713(28.07)194 (7.64)B1 B2R1 R2R3 R4R5 R6
Installation30 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNoteThe Nokia MetroSite EDGE Base Station can be installed in a vertical position orin a horizontal position. For more information on the permitted mountingpositions, refer to Nokia MetroSite EDGE Base Station: Requirements forInstallation and Operation.Horizontal installation is done in the same manner as wall mounting.Horizontal mounting is not recommended for all site conditions. Nokia MetroSiteEDGE BTSs fitted with the WCUA type cover are not suitable for horizontalmounting. Contact your Nokia representative for more information.6.1 Wall mountingThe mounting rack is attached to a suitable wall with screws and the BTS is thenfixed to the mounting rack. Screw hole positions are marked out on the wall usingthe cardboard template which came with the BTS transportation package (seeFigure 6). The required wall screws are provided by the installer, according to thespecifications given in Table 6.Table 6. Parts required for wall mountingPart NotesMounting rack Provided in the BTS transportationpackageCardboard template to show screw holepositions and minimum clearancearound the BTSProvided as part of the BTStransportation packageFour anchor plugs for M6 wall screws To provide a secure fixing for the wallscrewsFour wall screws, M6, stainless steel,minimum tensile strength (Rm) of 600N/mm2Refer to ISO 3506-1 for details
Mounting the BTSDN991456 © Nokia Corporation 31 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 6. Cardboard template for aligning wall mounting screw holes
Installation32 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFixing the mounting rack to the wall1. To define clearances required around the BTS, cut the template out of thepacking cardboard by following the dotted line (see Figure 6).2. Find a wall area which is large enough to cover all parts of the template andplace the cardboard template on the wall at the required height. Use a spiritlevel to check that the template is in a straight position.3. Mark the fixing points on the wall for the upper screw holes of themounting rack (R1 and R2, see Figure 5). For example, use a centre punchthrough the template to mark the fixing points.4. Drill holes R1 and R2 in the wall and clean them out. Insert anchor plugs(or an appropriate counterpart, depending on the material) into the wall.5. Position the mounting rack in the correct location on the wall and attach itwith screws through holes R1 and R2 (see Figure 7). Use a spirit level toset the mounting rack straight (adjustment is possible due to the oval shapeof holes R1 and R2). Tighten the screws when the rack is level.6. Drill screw holes for the lower anchor screws through the holes marked R3and R4 in Figure 7. Insert the anchor plugs (or appropriate counterparts)into the wall.7. Position the rectangle shaped washer over screw holes R3 and R4 andinsert and tighten the screws.
Mounting the BTSDN991456 © Nokia Corporation 33 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 7. Wall mountingB1B2Mounting rackAttaching the BTS andthe mounting rack:The view shows how the offsetscrews and the L-beam on theback of the cabinet areattached to the mounting rack.Offset fixing screws attached to theL-beam (2 pcs)R3R4B2B1R2R1WasherL-beamMounting rack
Installation34 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFixing the BTS to the mounting rack1. Hang the BTS on the upper fixing screws, B1 and B2 in Figure 7. Do nottighten them yet!2. Position the two offset screws which are attached to the L-beam (on theback of the cabinet) into the offset screw slots on the lower part of themounting rack, as shown in the inset illustration in Figure 7.3. Tighten the upper BTS fixing screws (B1 and B2 in Figure 7) using atorque driver and a 4 mm Allen bit with a shaft of at least 60 mm in length.Tighten the screws to 5.5 Nm (4.06 lb ft).4. Tighten the offset screws on the L-beam to 12 Nm (8.85 lb ft) using atorque socket spanner/wrench and a 6 mm Allen bit with an 80 mmextension. See the inset illustration in Figure 7, which shows the rear viewof the cabinet.5. If you have removed any of the units, proceed to Chapter 7. If you have notremoved any units, proceed directly to Chapter 8.6.2 Pole mountingPole mounting includes three work phases:1. Pre-assembling the pole brackets.2. Installing the pole brackets and the mounting rack on the pole.3. Fixing the BTS to the mounting rack.Table 7. Parts and pole diameters required for pole installationPart NotesMounting rack Provided in the BTStransportation packagePole mounting kit, containing:• Small-pole kit: 2 front blocks, 2 back blocks, 4bolts, 4 square nuts, 4 washers, 4 Allen screws• Large-pole kit: 2 front blocks, 2 metal bands, 2locking devices, 4 Allen screwsFor poles of diameter:• Small poles: 60 - 120 mm(2.4 - 4.7 in)• Large poles: 120 - 300 mm(4.7 - 11.8 in)
Mounting the BTSDN991456 © Nokia Corporation 35 (72)Issue 3 en Nokia Proprietary and ConfidentialNoteThere are two pole mounting options available with the pole mounting kit. Thesmall-pole kit uses both front and back bracket blocks, but not the metal bands.The large-pole kit is for larger diameter poles and uses the front bracket blocksand the metal bands. Refer to Table 7 for selecting the correct mounting kit typefor the pole diameter.There are two M6 screw holes at the ends of the upper and lower front blocks(Figure 8) for fixing an optional cable rack.6.2.1 Attaching the cabinet with the small-pole mounting kitThe mounting brackets (both upper and lower) consist of two blocks. The frontblock is attached to the BTS mounting rack, and the back block clamps themounting to the pole.The bracket blocks and their bolt holes are shown in Figure 8.Figure 8. Bracket blocks for pole mountingIf the diameter of the installation pole is 60 to 90 mm (2.4 to 3.5 in), use the innerbolt holes. If the diameter of the installation pole is 90 to 120 mm (3.5 to 4.7 in),use the outer holes. Figure 9 shows the inner bolt holes being used.Front blockBack blockUse outer bolt holesfor     90-120 (3.5-4.7) poleUse inner bolt holesfor     60-90 (2.4-3.5) poleNOTE: DIMENSIONS mm (inch)
Installation36 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enPre-assembling the pole brackets1. Insert the M8 assembly bolts and washers into the bolt holes in the backblocks. See [1] in Figure 9.2. Attach the square nuts on the ends of the bolts. Screw on the nuts justenough to secure them on the ends of the bolts. See [2] in Figure 9.3. Slide one of the bolts with the square nut into the slot at the side of the frontblock. See [3] in Figure 9.4. Screw the bolt in further, enough to prevent the bolt and the square nutfrom sliding out from the front block. See [4] in Figure 9.Figure 9. Pre-assembling the pole brackets1324
Mounting the BTSDN991456 © Nokia Corporation 37 (72)Issue 3 en Nokia Proprietary and ConfidentialNoteFixing the pole brackets and the mounting rack onto a poleBefore taking the mounting rack to the pole, perform the tasks instructed in Steps1 and 2 below.1. To fix the upper pole bracket to the mounting rack, screw the M6 x 20Allen screws through holes R1 and R2 into the upper front block, as shownin Figure 10. Make sure that the front block is the correct way up (the setof three adjacent screw holes on the back of the block should be on theupper edge). Use a torque driver with a 4 mm Allen bit to tighten the screwsto 5.5 Nm (4.06 lb ft).2. To fix the lower pole bracket to the mounting rack, screw the M6 x 20Allen screws through holes R5 and R6 into the lower front block, as shownin Figure 10. Make sure that the three adjacent screw holes are on the upperedge of the block. Use a torque driver with a 4 mm Allen bit to tighten thescrews to 5.5 Nm (4.06 lb ft).3. Bring the mounting rack/pole bracket combination to the pole.4. Position the upper front block of the pole bracket on the pole. Rotate theback block so that you can insert the free bolt and square nut into the freeslot on the other side of the front block.5. Tighten the bolts in even stages to fix the upper pole bracket to the pole.Use a torque socket spanner/wrench with a 6 mm Allen bit to tighten thebolts to 12 Nm (8.85 lb ft).6. Fix the lower bracket to the pole in the same manner as the upper bracket.
Installation38 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFigure 10. Attaching the mounting rack and the pole bracketsFixing the BTS to the mounting rack1. Bring the BTS to the mounting rack and hang it on the upper BTS fixingscrews, B1 and B2 in Figure 11. Do not tighten them yet!B1B2R2R1R6R5NOTE! Make sure thatthe three adjacent screw holesare on the upper edgeof the bracket block.
Mounting the BTSDN991456 © Nokia Corporation 39 (72)Issue 3 en Nokia Proprietary and Confidential2. Position the two offset screws which are attached to the L-beam (on theback of the cabinet) into the offset screw slots in the lower part of themounting rack, as shown in the inset illustration in Figure 7.3. Tighten the upper BTS fixing screws (B1 and B2 in Figure 11) to 5.5 Nm(4.06 lb ft) using a torque driver with a 4 mm Allen bit.4. Tighten the offset screws on the L-beam from the underside. Use a torquesocket spanner/wrench with a 6 mm Allen bit and an 80 mm extension totighten to 12 Nm (8.85 lb ft).5. If you have removed any BTS units, proceed to Chapter 7. If you have notremoved any units proceed directly to Chapter 8.
Installation40 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFigure 11. Pole mounting with the small-pole mounting kitB1B2Mounting rackAttach the BTS to the mounting rackwith offset screws at the BTS back side.
Mounting the BTSDN991456 © Nokia Corporation 41 (72)Issue 3 en Nokia Proprietary and Confidential6.2.2 Attaching the cabinet with the large-pole mounting kitWith the large-pole mounting kit, the front bracket blocks are clamped to the polewith a metal band and locking device.There are two types of band and locking device. One uses grooved metal bands,as described in procedure [A] below. The other type of locking device usessmooth bands and a locking rack, as described in procedure [B] below. Follow theprocedure for the type of locking device and band in your kit.[A] Pre-assembling the pole brackets and bands (grooved band type)1. Assemble the locking device and band by inserting the end of the metalband approximately 25 mm (1 in.) into the locking device. The correct setup of the parts is shown in Figure 12.Bend the surplus end of the metal band underneath the locking device, asshown in [3] [A] in Figure 12.Flatten the bent-over end of the metal band to remove any distortion.The locking device is now assembled.2. Cut the metal band to the appropriate length, according to the polediameter. Refer to Table 8 below.Table 8. Band length for different pole diametersPole diameter(mm)Band length(mm)Pole diameter(in)Band length(in)140 580 5.5 22.8160 630 6.3 24.8180 680 7.1 26.8200 740 7.9 29.1220 790 8.7 31.1240 850 9.5 33.5260 900 10.2 35.4280 950 11.0 37.4300 1010 11.8 39.8
Installation42 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en3. Route the metal band through the holes in the front block, as shown in [4],Figure 12.Leave the other end of the metal band free until you have completed thenext procedure (fixing the front bracket blocks to the mounting rack).Legend:1 Metal band2 Locking device3 Detail of locking device, attached to metal band4 Detail of entry point for metal band into front bracket blockFigure 12. Pole bracket pre-assembled (large-pole mounting kit)1DN02454342AB34
Mounting the BTSDN991456 © Nokia Corporation 43 (72)Issue 3 en Nokia Proprietary and Confidential[B] Pre-assembling the pole brackets and bands (non-grooved bandtype)1. Assemble the locking device by inserting the end of the locking rack intothe worm screw housing and turning the screw to engage the rack. Makesure you have the rack the right way round when doing this. The words‘THIS SIDE UP’ should be visible on the rack when the locking device isclamped around the pole. Refer to Figure 12.2. Cut the metal band to the appropriate length, according to the polediameter. Refer to Table 8 above.3. Route the metal band through the holes in the front block.4. Bend one end of the metal band over to form a hook of about 30 mm (1.2in) in length.5. Insert the hook into the slot at the end of the locking rack.6. Bend the other end of the metal band over to form another hook of about30 mm (1.2 in) in length. Leave it free for now.Figure 13. Pole bracket pre-assembled (large-pole mounting kit)LockingrackMetalbandWorm screwhousingWorm screw
Installation44 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNoteFixing the pole bracket and the mounting rack to a poleBefore taking the mounting rack up the pole, perform the tasks instructed in Steps1 and 2 below.1. Fix the upper pole bracket to the mounting rack by screwing the M6 x 20Allen screws through R1 and R2 into the upper front block, as shown inFigure 14. Make sure that the front block is the correct way up (the set ofthree adjacent screw holes should be on the upper edge of the bracket). Usea torque driver with a 4 mm Allen bit to tighten the screws to 5.5 Nm (4.06lb ft).2. Fix the lower pole bracket to the mounting rack by screwing the M6 x 20Allen screws through R5 and R6 into the lower block, as shown in Figure14. Make sure that the set of three adjacent screw holes is on the upper edgeof the bracket. Use a torque driver with a 4 mm Allen bit to tighten thescrews to 5.5 Nm (4.06 lb ft).3. Take the mounting rack/pole bracket combination to the pole.4. Wrap the metal band of the upper bracket around the pole.5. Insert the free end of the metal band (grooved type) into the slot on theworm screw housing, as shown in [B] of Figure 12. Wind the metal bandinto the locking device by turning the nut with a flat screwdriver or 8 mmhexagon socket and wrench.ORInsert the hook-shaped free end of the band (non-grooved type) into the sloton the worm screw housing. Tighten the worm screw using a flatscrewdriver or 8 mm hexagon socket and wrench.6. When all the slack on the band has been wound in with the locking device,tighten the worm screw to 10 Nm (7.4 lb ft) using a torque socketspanner/wrench and the 8 mm hexagon socket.7. Fix the lower bracket in the same manner as the upper bracket.
Mounting the BTSDN991456 © Nokia Corporation 45 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 14. Attaching the mounting rack and the pole bracketsB1B2R2R1R6R5NOTE! Make sure thatthe three adjacent screw holesare on the upper edge of thebracket block.DN99544792
Installation46 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFixing the BTS to the mounting rack1. Bring the BTS to the mounting rack and hang it on the upper BTS fixingscrews, B1 and B2 in Figure 15. Do not tighten them yet!2. Position the offset screws on the L-beam (on the back of the cabinet) intothe offset screw slots on the lower part of the mounting rack, as shown inthe inset illustration in Figure 7.3. Tighten the upper BTS fixing screws (B1 and B2 in Figure 15) to 5.5 Nm(4.06 lb ft) using a torque driver with a 4 mm Allen bit.4. Tighten the offset screws on the L-beam from the underside. Use a torquesocket spanner/wrench with a 6 mm Allen bit to tighten to 12 Nm (8.85 lbft).5. If you have removed any units, proceed to Chapter 7. If you have notremoved any units proceed directly to Chapter 8.
Mounting the BTSDN991456 © Nokia Corporation 47 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 15. Pole mounting with large-pole mounting kitB1B1Mounting rackAttach the BTS to the mounting rackwith offset screws at the BTS back side.B2B2DN9913502
Installation48 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
Reinstalling the unitsDN991456 © Nokia Corporation 49 (72)Issue 3 en Nokia Proprietary and ConfidentialNoteCautionNote7Reinstalling the unitsIf any units have been removed from the BTS, they can be reinstalled in any order.If you have removed any units from the BTS, be sure to install the groundingcable before reinstalling the units. Refer to the grounding cabling instructions inSection 8.2.Always use the antistatic wrist strap  when removing or installing the units. Formore information on electro-static discharge protection, refer to Nokia MetroSiteEDGE Base Station: Warnings and Cautions. The wrist strap and the connectionpoint are shown in Figure 3.Reinstalling units1. Slide the unit into the appropriate slot (see Figure 4).2. Press the unit carefully against the connectors on the backplane. Do not useexcessive force!3. Fix and tighten the unit retaining screws. Use a torque driver with a T10Torx bit to tighten to 1.5 Nm (1.11 lb ft).Shield unit fixing screws may only be tightened to 1.0 Nm (0.74 lb ft).
Installation50 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enCautionIn order to ensure proper weather shielding, all unit retaining screws must betightened.
Cabinet cablingDN991456 © Nokia Corporation 51 (72)Issue 3 en Nokia Proprietary and ConfidentialNote8Cabinet cablingThis document assumes that you are using the ready-made cables supplied byNokia, or that all cables have been prefabricated before starting the cabling of theBTS. For information on the cable types and connectors refer to Nokia MetroSiteEDGE Base Station: Requirements for Installation and Operation. For the pinconfigurations refer to Nokia MetroSite EDGE Base Station: ProductDescription.The connectors on the units’ front panels are protected with rubber caps. Removethe caps only from those connectors that will be used for BTS cabling.8.1 Preparations for cablingBefore starting the cabling, do the following:1. Displace the sealing strip around the cable entry block. See [A] in Figure16.2. Loosen and remove the two Allen screws that keep the cable entry block inplace. Use a torque driver with a 4 mm Allen bit. For the location of thescrews, see [B] in Figure 16.
Installation52 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNoteFigure 16. Displacing the sealing strip and removing the cable entry blockscrewsWhen the screws are removed, the cable entry block can be split apart atappropriate places for routing the cables through the cable holes. For routing thecables through the block, see Figure 17.ASealing stripAllen screwsM6Allen key 4 mm
Cabinet cablingDN991456 © Nokia Corporation 53 (72)Issue 3 en Nokia Proprietary and ConfidentialWARNINGFigure 17. Cable routing through the cable entry block8.2 GroundingTo guarantee the safety of service personnel and other users of thetelecommunication network, additional protective grounding is alwaysrequired as stated in EN 60950, “Safety of information technologyequipment, including electrical business equipment.” and UL 1950 3rdedition. The additional external ground cable is connected to the groundingconnector.Ensure that the ground connection is secure and non-removable.There are two alternative grounding connectors in the BTS chassis (see Figure18). Depending on the local regulations, choose the appropriate connector forconnecting the grounding cable to the chassis. Note that the grounding cable inalternative 2 must be fitted with a cable shoe.AntennafeedersPower supply cableExtension cables- Grounding cable, 1 pc- Transmission cables, max 8 pcs- External alarms and controls
Installation54 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFigure 18. Grounding connector alternativesConnecting the ground wire to the connector, alternative 11. Loosen the two locking screws and washers from the grounding connectorusing a torque driver with a 4 mm Allen bit.2. Strip the end of the grounding cable using side-cutting pliers and attach aflat crimp terminal to it. Fix the terminal to the cable with a crimping tool.3. Insert the crimp terminal between the cabinet and the washer. Tighten thescrews.Alternative 1Alternative 2
Cabinet cablingDN991456 © Nokia Corporation 55 (72)Issue 3 en Nokia Proprietary and ConfidentialWARNINGWARNING4. Make sure that the grounding cable is correctly positioned and that thescrews are securely tightened.Connecting the ground wire to the connector, alternative 21. Strip the end of the grounding cable using side-cutting pliers and attach acable shoe to the cable with a crimping tool.2. Loosen and remove the locknut from the grounding stud.3. Place the cable shoe over the grounding stud.4. Replace the locknut on the stud and tighten with an 8 mm hexagon socket.5. Make sure that the grounding cable is correctly positioned and that the nutis securely tightened.8.3 Power supplyMAINS VOLTAGE! Follow your national legislation when working with thepower supply. The Nokia MetroSite EDGE Base Station must bepermanently wired to a disconnect device (such as a circuit breaker), inaccordance with current local and national wiring standards.The following warning applies to the AC power supply. The protectiveground wire can only be used for protective conductor installations. Usingthe protective ground conductor for other purpose is dangerous to life.Ensure that the ground connection is established before the power outlet isconnected to the BTS.The mains power supply must be switched OFF before starting installationof the power supply cable!
Installation56 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNoteConnecting the power supply cable to the power supply unit1. Make sure that the site’s mains power supply is switched OFF and that theswitch on the power supply unit is in the stand-by position.2. Open the connector shield by loosening the retaining screws with a torquedriver and a T10 Torx bit (see Figure 19).3. Open up the rubber sealing piece and route the power supply cable throughit. Close the sealing piece.DC power can be fed in with three separate conductors. In this case, reverse therubber sealing piece so that the three small recesses are facing each other andform three small holes (see Figure 19). Use the three holes for routing theconductor cables.4. Connect the power supply cable to the power connector in the powersupply unit.5. Close the power supply connector shield and tighten the screws.
Cabinet cablingDN991456 © Nokia Corporation 57 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 19. Power supply unit and power connector alternativesAC 230 V AC 110 V DCConnector alternatives:Sealing for 1 wire Sealing for 3 wires
Installation58 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNoteNote8.4 Transmission unitThe cabling of the transmission unit is dependent on the transmission unit type.This section instructs how to cable each transmission unit type.It is a good procedure to label the TX and RX cables when you connect them tothe transmission unit. This makes any subsequent maintenance or upgradeprocedures easier.8.4.1 FC E1/T1 transmission unitEither separate 75 Ω RX and TX connectors (type BT-43), or one 120/100 ΩTX/RX connector (type TQ) can be used.The 75 Ω TX and RX connectors are connected to each other with a groundingbridge (see Figure 20). If the grounding bridge is removed, the grounding of theRX connector’s outer conduct changes from direct grounding to capacitivegrounding.
Cabinet cablingDN991456 © Nokia Corporation 59 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 20. Cabling alternatives for the FC E1/T1 transmission unitCabling an FC E1/T1 75 Ω transmission unit1. If you want to remove the grounding bridge (see Figure 20), use a 10 mmhexagon socket to loosen both connectors and pull out the bridge. Re-tighten the connectors.2. Connect the connector of the received (RX) signal line to the 75 Ω RXconnector on the FC E1/T1 front panel.3. Connect the connector of the transmitted (TX) signal line to the 75 Ω TXconnector on the FC E1/T1 front panel.Cabling an FC E1/T1 120/100 Ω transmission unit• Connect the connector of TX/RX signal line to the 100/120 Ω TX/RXconnector on the FC E1/T1 front panel (see Figure 20). Tighten theconnector nut properly.RX lineTX lineRX/TX lineFC E1/T1120/10075Groundingbridge
Installation60 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNote8.4.2 FXC E1 transmission unitThe FXC E1 has four pairs of 75 Ω connectors (type BT-43). Each pair forms atransmission interface (IF). The upper connector is always the TX connector ofany given transmission interface. The lower connector is always the RXconnector of any given transmission interface (see Figure 21).The 75 Ω TX and RX connectors are connected to each other with a groundingbridge (see Figure 21). If the grounding bridge is removed, the grounding of theRX connector’s outer conduct changes from direct grounding to capacitivegrounding.Figure 21. Cabling of the FXC E1 transmission unitRX line, IF4TX line, IF4TX line, IF3RX line, IF3RX line, IF2TX line, IF2TX line, IF1RX line, IF1 Grounding bridge
Cabinet cablingDN991456 © Nokia Corporation 61 (72)Issue 3 en Nokia Proprietary and ConfidentialCabling an FXC E1 transmission unit1. If you want to remove the grounding bridge (see Figure 21), use a 10 mmhexagon socket to loosen both connectors and pull out the bridge. Re-tighten the connectors.2. Connect the connector of the received (RX) signal line to the 75 Ω RXconnector on IF1.3. Connect the connector of the transmitted (TX) signal line to the 75 Ω TXconnector on IF1.4. Cable the other IFs in the same manner (see Figure 21).8.4.3 FXC E1/T1 transmission unitFXC E1/T1 has four 100/120 Ω TX/RX connectors (type TQ).Figure 22. Cabling of the FXC E1/T1 transmission unitFXC E1/T1RX/TX line 4RX/TX line 3RX/TX line 2RX/TX line 1
Installation62 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enCabling an FXC E1/T1 transmission unit• Connect the connectors of the TX/RX signal lines to the 100/120 ΩTX/RXconnectors on the FXC E1/T1 front panel (see Figure 22). Tighten theconnector nut properly.8.4.4 FXC RRI transmission unitFigure 23. Cabling of the FXC RRI transmission unitCabling the FXC RRI transmission unit• Connect the RX/TX (Flexbus) cable from the radio outdoor unit to theTNC connector(s) on the FXC RRI transmission unit (see Figure 23).RX/TX(Flexbus) radio 2RX/TX(Flexbus) radio 1 FXC RRI
Cabinet cablingDN991456 © Nokia Corporation 63 (72)Issue 3 en Nokia Proprietary and ConfidentialNote8.5 Interface unitFigure 24. Cabling of the interface unitWhen you have connected the cables, push the rubber seals onto the connectors.Cabling the interface unit1. Connect the external alarms and controls cable to the EAC connector (26-pin, mini-D connector).EAC cableLMP cable(connect onlybeforecommissioning)Q1 cableInterface unit
Installation64 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enNoteNoteCautionNote2. Connect the Q1 cable to the Q1 connector (type TQ) on the interface unit.Only connect the LMP cable from your MetroSite BTS Manager PC to the LMPconnector (BQ) just before starting the commissioning.The extension interface connectors are not used yet.8.6 Transceiver units (TRXs)Diversity cables and antenna feeders are connected to the TRXs. See also NokiaMetroSite EDGE Base Station: Product Description.Cabling the TRXs1. Disconnect the diversity cables from the SMA type connectors on theTRXs (if needed).2. Reconnect the diversity cables to form the desired diversity configuration.Examples of different sectoring alternatives and their diversity cabling arepresented in Figure 25.Diversity cables may only be connected between TRXs that belong to the samesector!3. Connect the antenna feeders to the N-type connectors on the TRXsaccording to the sectoring solution planned.The diversity cabling solution is always dependent on the antenna solution.
Cabinet cablingDN991456 © Nokia Corporation 65 (72)Issue 3 en Nokia Proprietary and Confidential4. Use a torque spanner/wrench for tightening the antenna diversity cables.Tighten the SMA type connectors to 1 Nm (0.74 lb ft).Figure 25. Examples of diversity cabling alternatives2 TRX omni 3 TRX omni 2+2 TRX 4 TRX omniDIVOUTDIVOUTDIVINDIVINTRX1TRX2DIVINDIVOUTDIVOUTDIVINDIVOUTDIVINTRX1TRX2TRX4DIVOUTDIVINDIVINDIVOUTDIVOUTDIVOUTDIVINDIVINTRX4TRX3TRX1TRX2DIVOUTDIVINDIVINDIVOUTDIVOUTDIVOUTDIVINDIVINTRX1TRX2TRX4TRX3Possible antenna solutions- 2 single port  antennas- 1 dual port  antenna- 1 dual port  and 1 single  port antenna- 3 single port  antennas- 2 dual port  antennas- 4 single port  antennas- 2 dual port  antennas- 4 single port  antennas
Installation66 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en8.7 Completing the cablingCompleting the cabling procedure1. Route the cables through the opened cable entry block, as presented earlierin Figure 17.2. Close the cable entry block with the two Allen screws. Use a torque driverwith a 4 mm Allen bit.3. Replace the sealing strip around the cable entry block.4. Route the antenna feeder cables and power supply cable to the front of theperforated plastic panel (see [1] in Figure 26). Fix the cables to theperforated panel with cable ties. Use side-cutting pliers to cut off theextruding parts of the cable ties.5. Route the transmission cables, the grounding cable and the cables comingfrom the interface unit behind the perforated plastic panel at the lower edgeof the BTS (see [2] in Figure 26). Fix the cables to the perforated panel withat least two cable ties. Use side-cutting pliers to cut off the extruding partsof the cable ties.6. Attach the cable cover support on the grips at the far end of the perforatedpanel (see [A] in Figure 26).7. Push the cables towards the cable cover support at the far end of theperforated panel.8. Place the cable cover onto the hook at the near end of the perforated panel.Align it to the recesses on the cable cover support and slide it downwardsuntil it locks to the cable cover support (see [B] in Figure 26).
Cabinet cablingDN991456 © Nokia Corporation 67 (72)Issue 3 en Nokia Proprietary and ConfidentialFigure 26. Routing the cables and closing the cable coverABCable cover Cable coversupport
Installation68 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 en
Completing the installationDN991456 © Nokia Corporation 69 (72)Issue 3 en Nokia Proprietary and Confidential9Completing the installationWith the BTS safely fixed to a wall or a pole, commissioning can be started.Commissioning can be left to a later stage if there are no qualified personnel onthe site during installation. To complete the installation, the BTS cover is fitted tothe chassis and the BTS cabinet is locked.Commissioning the BTS1. Switch the BTS power ON.2. Connect the LMP cable from the MetroSite BTS Manager PC to the LMPconnector on the interface unit.3. Proceed to the BTS commissioning tasks. Refer to Nokia MetroSite EDGEBase Station: Commissioning.Fitting the cover and locking the cabinet1. Bring the BTS cover to the BTS chassis (see Figure 27). Attach the safetystrap to the fixing point provided under the top of the cover.2. Make sure that the cover is secured with the safety strap (see Figure 27).3. Place the cover over the cabinet and align the locking hooks on the coverto the locking rail on the chassis. Push the cover into the chassis and pulldownwards to lock the hooks firmly into the rail.4. Check that the cover is firmly secured by pushing the cover from the sides.5. Lock the cabinet with the key.6. Clean the site. Recycle any applicable material.
Installation70 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enFigure 27. Hanging the BTS coverFixing pointfor safety strapunder thecover top
DN991456 ©Nokia Corporation 71 (72)Issue 3 en Nokia Proprietary and ConfidentialIndexAAC power warnings 55antenna solutions 64antistatic wrist strap 25,49assembling pole brackets 36,43Bband length for pole mounting 41,43bracket blocks for pole mountingback block 35front block 35Ccabinet installation 29cable cover 66cable entry block 52cablesantenna feeders 52extension 52external alarms and controls 52grounding 52power supply 52transmission 52cablingantenna feeders 64diversity cables 64grounding 53interface unit 63power supply 55transmission unit 58TRX unit 64capacitive grounding 58cardboard template 30commissioning 69completing the cabling 66cover 69DDC power 56delivery contents 21dimensionsmounting rack 30pole diameter 35wall space 32direct grounding 58diversity cabling alternatives 64EEAC connector 63electro-static discharge (ESD) protection 25,49FFC E1/T1 58FXC E1 60FXC E1/T1 61FXC RRI 62Ggrounding 53grounding bridge 58IinstallingBTS onto a pole 37BTS onto a wall 32BTS onto the mounting rack 38,46cabinet 29mounting rack onto a pole 44pole brackets onto a pole 44units 49interface unitcabling 63Kkey for BTS cabinet lock 20LL-beam 34LMP connector 64locking device 43Mmounting kit 35mounting kit for pole mounting 41mounting rack 29,34mounting rack installation 37,44Ooffset screws 34
Installation72 (72) © Nokia Corporation DN991456Nokia Proprietary and Confidential Issue 3 enPparts for installation 16,30pole bracket assembly 36,43pole bracket installation 44pole diameter 35,41,43pole mounting 34pole mounting kit 22power supply connectors 56power supply unitcabling 55preparationscabling 51QQ1 connector 64Rremoving units 25Ssafety strap 69sealing strip 51sectoring solutions 64shield units 21,25,49site requirements 15SMA type connectors 64Ttemplate for wall mounting 30tools for installation 16transceiver unit (TRX)cabling 64transmission unitcabling 58transportation package 19Uunit installation 49unit removal 25unpacking the delivery 19Wwall mounting 32

Navigation menu