LampSiteInstallation GuideIssue 08Date 2015-01-15HUAWEI TECHNOLOGIES CO., LTD.
  Copyright © Huawei Technologies Co., Ltd. 2015. All rights reserved.No part of this document may be reproduced or transmitted in any form or by any means without prior writtenconsent of Huawei Technologies Co., Ltd. Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.All other trademarks and trade names mentioned in this document are the property of their respective holders. NoticeThe purchased products, services and features are stipulated by the contract made between Huawei and thecustomer. All or part of the products, services and features described in this document may not be within thepurchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,and recommendations in this document are provided "AS IS" without warranties, guarantees or representationsof any kind, either express or implied.The information in this document is subject to change without notice. Every effort has been made in thepreparation of this document to ensure accuracy of the contents, but all statements, information, andrecommendations in this document do not constitute a warranty of any kind, express or implied.       Huawei Technologies Co., Ltd.Address: Huawei Industrial BaseBantian, LonggangShenzhen 518129People's Republic of ChinaWebsite: http://www.huawei.comEmail: support@huawei.comIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.i
About This DocumentOverviewThis document describes how to install the modules and cables for the RHUB3908, pRRU3901indoors. It also provides checklists for hardware installation.Product VersionThe following table lists the product version related to this document.Product Name Solution Version Product VersionDBS3900 lSRAN9.0 and later versionslRAN16.0 and later versionsleRAN7.0 and later versionsleRAN TDD 7.0 and laterversionsV100R009C00 and later versions Intended AudienceThis document is intended for:lBTS installation personnelLampSiteInstallation Guide About This DocumentIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.ii
ContentsAbout This Document.....................................................................................................................ii1 Changes in LampSite Installation Guide.................................................................................12 Installation Preparations..............................................................................................................62.1 Reference Documents.....................................................................................................................................................72.2 Preparing Tools and Instruments....................................................................................................................................72.3 Requirements for Installation Personnel.........................................................................................................................83 Unpacking and Checking............................................................................................................94 Installing a BBU...........................................................................................................................115 Installing an RHUB3908.............................................................................................................125.1 Information About the Installation...............................................................................................................................135.1.1 RHUB3908 Installation Scenarios.............................................................................................................................135.1.2 Installation Clearance Requirements of an RHUB3908............................................................................................175.1.3 Installation Environment of an RHUB3908..............................................................................................................195.2 Installation Process.......................................................................................................................................................215.3 Installing an RHUB3908..............................................................................................................................................215.3.1 Installing an RHUB3908 in a 19-Inch Cabinet or Rack............................................................................................215.3.2 Installing an RHUB3908 in a 19-Inch Shelf.............................................................................................................245.3.3 Installing an RHUB3908 on a Wall...........................................................................................................................275.4 Installing RHUB3908 Cables.......................................................................................................................................315.4.1 Requirements for Cable Layout.................................................................................................................................315.4.2 RHUB3908 Cable List...............................................................................................................................................345.4.3 Cable Connections.....................................................................................................................................................355.4.4 RHUB3908 Cable Installation Process......................................................................................................................355.4.5 Installing an RHUB3908 PGND Cable.....................................................................................................................365.4.6 Installing an Ethernet Cable......................................................................................................................................385.4.7 Installing CRPI Optical Cables..................................................................................................................................405.4.8 Installing an RHUB3908 Alarm Cable (Optional)....................................................................................................425.4.9 Installing an RHUB3908 Power Cable......................................................................................................................435.5 Checking the RHUB3908 Hardware Installation.........................................................................................................445.6 Power-on Check on an RHUB3908..............................................................................................................................46LampSiteInstallation Guide ContentsIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.iii
6 Installing a pRRU3901................................................................................................................486.1 Information About the Installation...............................................................................................................................506.1.1 pRRU3901 Product Family.......................................................................................................................................506.1.2 pRRU3901 Installation Scenario...............................................................................................................................506.1.3 Space Requirements..................................................................................................................................................546.1.4 pRRU3901 Installation Environment Requirements.................................................................................................556.2 Obtaining the MAC Address (Optional) .....................................................................................................................566.3 Installation Process.......................................................................................................................................................576.4 Installing a pRRU3901.................................................................................................................................................586.4.1 pRRU3901 Installation Kits......................................................................................................................................586.4.2 pRRU3901 Installed on a Wall..................................................................................................................................606.4.3 pRRU3901 Installed on a Ceiling..............................................................................................................................636.4.4 pRRU3901 Installed on a Pole..................................................................................................................................666.4.5 pRRU3901 Installed on a Plate.................................................................................................................................686.4.6 pRRU3901 Installed on a Keel..................................................................................................................................716.5 Installing pRRU3901 Cables........................................................................................................................................746.5.1 Requirements for Cable Layout.................................................................................................................................746.5.2 pRRU3901 Cable List...............................................................................................................................................756.5.3 Cable Connections.....................................................................................................................................................766.5.4 Cable Connections (LTE TDD).................................................................................................................................796.5.5 pRRU3901 cable installation process........................................................................................................................806.5.6 Installing an Ethernet Cable......................................................................................................................................806.5.7 Installing pRRU3901 Jumpers (Optional).................................................................................................................826.6 Checking the pRRU3901 Hardware Installation..........................................................................................................846.7 Powering on the pRRU3901.........................................................................................................................................857 Installing the Extender (Optional)...........................................................................................878 Appendix.......................................................................................................................................908.1 MAC Collection Template...........................................................................................................................................918.2 LampSite Engineering Label........................................................................................................................................918.3 Attaching an L-Shaped Label.......................................................................................................................................95LampSiteInstallation Guide ContentsIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.iv
1 Changes in LampSite Installation GuideThis chapter describes the changes in the LampSite Installation Guide.08 (2015-01-15)This is the eighth commercial release.Compared with 07 (2014-11-15), this issue includes the following new topics:l4 Installing a BBUCompared with 07 (2014-11-15), this issue incorporates the following changes:Content Change DescriptionEntire document lChanged RHUB, and pRRU toRHUB3908, and pRRU3901,respectively.lAdded the pRRU3901 with threetransmission ports plus no PWR port (orthe pRRU3901a for use in NorthAmerica) .6.7 Powering on the pRRU3901 Deleted the description that the pRRU3901supports AC/DC power supply. Compared with 07 (2014-11-15), no information is deleted.07 (2014-11-15)This is the seventh commercial release.Compared with 06 (2014-09-30), no information is added.Compared with 06 (2014-09-30), this issue incorporates the following change:LampSiteInstallation Guide 1 Changes in LampSite Installation GuideIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.1
Content Change DescriptionSpace Requirements Added the requirements on the installation spacewhen the pRRU3901 working on the 2.6 GHz bandand the Wi-Fi module need to process servicesconcurrently. Compared with 06 (2014-09-30), this issue excludes the following topic:lInstalling RF Daughter Boards on a pRRU3901 (in Capacity Expansion Scenarios)06 (2014-09-30)This is the sixth commercial release.Compared with 05 (2014-08-30), no information is added.Compared with 05 (2014-08-30), this issue incorporates the following changes:Content Change DescriptionpRRU Installation EnvironmentRequirementsChanged the operating temperature ofpRRU3901s to a range from - 5°C to + 40°C.Requirements for Cable Layout Added the cabling requirements for Ethernetcables.Requirements for Cable Layout Compared with 05 (2014-08-30), no information is deleted.05 (2014-08-30)This is the fifth commercial release.Compared with 04 (2014-07-30), no information is added.Compared with 04 (2014-07-30), this issue incorporates the following changes:Content Change DescriptionInstallation Clearance Requirements of anRHUBAdded the security precautions for theRHUB3908 installation environment.Requirements for Cable LayoutInstalling an Ethernet Cable Added the Ethernet cable specifications andrequirements on flame spread rating.Installing an Ethernet Cable Compared with 04 (2014-07-30), no information is deleted.LampSiteInstallation Guide 1 Changes in LampSite Installation GuideIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.2
04 (2014-07-30)This is the fourth commercial release.Compared with 03 (2014-06-30), no information is added.Compared with 03 (2014-06-30), this issue incorporates the following change:Content Change Description7 Installing the Extender (Optional) Added the descriptions about installing aExtender on a Ceiling. Compared with 03 (2014-06-30), no information is deleted.03 (2014-06-30)This is the third commercial release.Compared with 02 (2014-05-30), this issue includes the following new topics:l8.2 LampSite Engineering Labell8.3 Attaching an L-Shaped LabelCompared with 02 (2014-05-30), this issue incorporates the following changes:Content Change DescriptionCable Connections Modified the description about cableconnections of the RHUB3908.Installing RHUB Cables Added the steps for attaching labels to cables.Installing pRRU CablesInstalling an Ethernet Cable Added the steps for making Ethernet cables.Installing an Ethernet CableInstalling RF Daughter Boards on apRRU3901 (in Capacity ExpansionScenarios)Added the descriptions about the supportedblock type. Compared with 02 (2014-05-30), no information is deleted.02 (2014-05-30)This is the second commercial release.Compared with 01 (2014-04-26), no information is added.Compared with 01 (2014-04-26), this issue incorporates the following change:LampSiteInstallation Guide 1 Changes in LampSite Installation GuideIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.3
Content Change DescriptionEntire document Added the descriptions about the LTE FDD+LTE FDD mode. Compared with 01 (2014-04-26), no information is deleted.01 (2014-04-26)This is the first commercial release.Compared with Draft C (2014-03-26), no information is added.Compared with Draft C (2014-03-26), this issue incorporates the following change:Content Change DescriptionEntire document Changed the pRRU3901 name frompRRU3901 with two Ethernet ports topRRU3901 with two transmission ports, andpRRU3901 with three Ethernet ports topRRU3901 with three transmission ports. Compared with Draft C (2014-03-26), no information is deleted.Draft C (2014-03-26)This is a draft release.Compared with Draft B (2014-02-28), no information is added.Compared with Draft B (2014-02-28), this issue incorporates the following changes:Content Change DescriptionInstalling CRPI Optical Cables Added the description of connecting theCPRI cable to the TX and RX ports of theoptical module crossly.pRRU Installation EnvironmentRequirementsThe operating temperature of pRRU3901 isupdated. Compared with Draft B (2014-02-28), no information is deleted.Draft B (2014-02-28)This is a draft release.Compared with draft A (2013-11-30), this issue includes the following new topics:LampSiteInstallation Guide 1 Changes in LampSite Installation GuideIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.4
lObtaining the MAC Address (Optional)lCable ConnectionslMAC Collection TemplateCompared with draft A (2013-11-30), this issue incorporates the following changes:Content Change DescriptionEntire document Added descriptions about pRRU3901s withthree transmission ports. Such pRRU3901ssupport integrated Wi-Fi services.Added the descriptions about the UMTS, LTEFDD and UMTS+LTE FDD mode.LampSite Installation Guide Optimized descriptions about matchingproduct versions.Installing an Ethernet Cable Changed the cable name from RHUB3908-pRRU3901 Ethernet cable to Ethernet cable.Installing an Ethernet Cable Compared with draft A (2013-11-30), this issue excludes the following topics:lInstalling External Antennas (Optional)lRHUB3908 ExteriorlRHUB3908 Ports and IndicatorslpRRU3901 ExteriorlpRRU3901 Ports and IndicatorsDraft A (2013-11-30)This is a draft release.LampSiteInstallation Guide 1 Changes in LampSite Installation GuideIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.5
2 Installation PreparationsAbout This ChapterBefore starting the installation, you must obtain the required reference documents, tools, andinstruments, and familiarize yourself with the skills required.2.1 Reference DocumentsBefore the installation, you must read the following documents:2.2 Preparing Tools and InstrumentsThis section describes the tools and instruments that must be prepared before the installation.2.3 Requirements for Installation PersonnelThis section describes requirements for installation engineers. They must be qualified andtrained, and familiar with correct operation methods and safety precautions before performingany operations.LampSiteInstallation Guide 2 Installation PreparationsIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.6
2.1 Reference DocumentsBefore the installation, you must read the following documents:lLampSite Hardware DescriptionlInstallation ReferenceFor details about how to install a baseband unit (BBU), see DBS3900 Installation Guide.2.2 Preparing Tools and InstrumentsThis section describes the tools and instruments that must be prepared before the installation.MarkerLevelTorque screwdriver (M4 to M6)Diagonal pliersPower cable crimping tool RJ11 crimping tool Cable cutterRubber mallet T20 torque torx screwdriver Wire stripperHammer drill (Ø6, Ø8 andØ12)Torque wrench (Ø10 mm) Protective glovesGuarded blade utility knife ESD gloves Long measuring tapeLampSiteInstallation Guide 2 Installation PreparationsIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.7
Multimeter Network cable tester Vacuum cleanerLadder Torque wrench for SMAconnectorSocket wrench (M6) 2.3 Requirements for Installation PersonnelThis section describes requirements for installation engineers. They must be qualified andtrained, and familiar with correct operation methods and safety precautions before performingany operations.Before the installation, pay attention to the following items:lTechnical engineers must take Huawei training and be familiar with proper installation andoperation methods.lThe number of installation personnel depends on the engineering schedule and installationenvironment. Generally, three to five persons are required. Generally, only three to fiveonsite personnel are necessary.LampSiteInstallation Guide 2 Installation PreparationsIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.8
3 Unpacking and CheckingThis section describes how to unpack and check the delivered equipment to ensure that thematerials are complete and intact.ContextNOTEThe following lists important notes when you are transporting, lifting, or installing the equipment orcomponents:lProtect them from colliding with doors, walls, shelves, or other objects.lWear clean gloves and do not touch them with bare hands, sweat-soaked gloves, or dirty gloves.NOTICEYou must power on the RHUB3908 or pRRU within 7 days after it is unpacked.ProcedureStep 1 Count the total number of the shipments.If... Then...The total number of the components isconsistent with that recorded in thepacking lists on all packing boxesGo to Step 2.The total number of the components isinconsistent with that recorded in thepacking lists on all packing boxesReport the problems and causes to the localHuawei office.Step 2 Check the exterior of each packing box.LampSiteInstallation Guide 3 Unpacking and CheckingIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.9
If... Then...The exterior of each packing box is intact Go to Step 3.It is damaged or soaked Report the problems and causes to the localHuawei office.The collision label is red Do not unpack the packing box and claim forcompensation from the transportationcompany.Step 3 Check the type and quantity of the equipment in the boxes according to the packing list.If... Then...The type and number are consistent withthe packing list on each packing listSign the Packing List with the operator.There is any shortage, wrong delivery, ordamaged equipmentReport the problems and causes to the localHuawei office.NOTICEPerform the following operations to protect the components from any damages and help findout the cause of any damage in future: 1. Store the unpacked equipment and packing materialsindoors. 2. Take photos of the storeroom, rusted or eroded equipment, packing box, and packingmaterials. 3. File the photos.----EndLampSiteInstallation Guide 3 Unpacking and CheckingIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.10
4 Installing a BBUThis chapter describes the process of installing a BBU.The BBU can have BBU3900 and BBU3910. Unless otherwise specified, the BBU refers to boththe BBU3900 and BBU3910 in this document.For details about the installation of the BBU, see DBS3900 Installation Guide.LampSiteInstallation Guide 4 Installing a BBUIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.11
5 Installing an RHUB3908About This ChapterThis chapter describes the process of installing an RHUB3908.5.1 Information About the InstallationThis section describes the information to be learnt before RHUB3908 installation, including theRHUB3908 installation scenarios, clearance, and installation environment.5.2 Installation ProcessThe RHUB3908 installation involves installing an RHUB3908 module, installing RHUB3908cables, checking the RHUB3908 hardware installation, and powering on the RHUB3908.5.3 Installing an RHUB3908An RHUB3908 can be installed in a cabinet, rack, shelf, or on a wall.5.4 Installing RHUB3908 CablesThis section describes how to install cables for an RHUB3908.5.5 Checking the RHUB3908 Hardware InstallationAfter an RHUB3908 is installed, check the installation of hardware including the devices andrelated cables.5.6 Power-on Check on an RHUB3908This section describes the power-on check on the RHUB3908 after the RHUB3908 hardware isinstalled and checked.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.12
5.1 Information About the InstallationThis section describes the information to be learnt before RHUB3908 installation, including theRHUB3908 installation scenarios, clearance, and installation environment.5.1.1 RHUB3908 Installation ScenariosAn RHUB3908 can be installed in a 19-inch cabinet, rack, shelf, or on a wall.The RHUB3908 supports that mounting ears are installed in standard mode or reverse mode.The reverse mode is used by default. The two installation modes are defined as follows:lIn standard mode, the front of the mounting ear is aligned with the RHUB3908 panel, asshown in Figure 5-1.Figure 5-1 Installing mounting ears in standard modelIn reverse mode, the front of the mounting ear is 31 mm away from the RHUB3908 panel,as shown in Figure 5-2.Figure 5-2 Installing mounting ears in reverse modeLampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.13
Installing an RHUB3908 in a 19-Inch Cabinet or RackInstalling an RHUB3908 in a 19-inch cabinet or rack: Secure the mounting ear to the mountingbracket by using M6 screws.lIf there is no other modules installed in the 1 U space near the RHUB3908, install theRHUB3908 directly. Otherwise, remove the modules before installing the RHUB3908.lBefore installation, you need to check the installation mode supported by the rack and adjustthe position of the mounting ear.Figure 5-3 and Figure 5-4 show RHUB3908s installed in a cabinet or rack, respectively.Figure 5-3 Installing an RHUB3908 in a 19-inch cabinet or rack in standard modeFigure 5-4 Installing an RHUB3908 in a 19-inch cabinet in reverse modeInstalling an RHUB3908 in a 19-Inch ShelfWhen an RHUB3908 is installed in a 19-inch shelf, the shelf must be installed on a wall. Oneshelf can house multiple RHUB3908s with 1 U space between two RHUB3908s.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.14
Figure 5-5 and Figure 5-6 show RHUB3908s installed in a 19-inch shelf.Figure 5-5 RHUB3908 installed in a 19-inch shelf in standard modeLampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.15
Figure 5-6 RHUB3908 installed in a 19-inch shelf in reverse modeInstalling an RHUB3908 on a WallAn RHUB3908 can be installed on a wall.The wall on which an RHUB3908 is installed must meet the following requirements:lWhen a single RHUB3908 is installed, the wall must have a capacity of bearing at leastfour times the weight of the RHUB3908.lExpansion bolts must be tightened to 10 N·m (88.507 bf·in.) to ensure the bolts workproperly and the wall remains intact without cracks in it.Figure 5-7 shows an RHUB3908 installed on a wall.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.16
Figure 5-7 RHUB3908 installed on a wall5.1.2 Installation Clearance Requirements of an RHUB3908When an RHUB3908 is installed in a 19-inch cabinet, rack, shelf, or on a wall, a minimumclearance is required for easy cabling and operation and maintenance. A recommendedinstallation clearance is provided based on experience.NOTICElDo not install or place inflammable materials above or under an RHUB3908.lA clearance of 350 mm must be reserved in front of the air intake vent of the fan of the powersupply unit (PSU) for maintenance.Figure 5-8 shows the installation clearance for the RHUB3908 installed in a 19-inch cabinet,rack, or shelf.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.17
Figure 5-8 Installation clearance for an RHUB3908 installed in a 19-inch cabinet, rack, or shelfFigure 5-9 and Figure 5-10 shows the recommended and minimum installation clearancerespectively when the RHUB3908 is installed on a wall.Figure 5-9 Recommended installation clearance for a wall-mounted RHUB3908 (unit: mm)LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.18
Figure 5-10 Minimum installation clearance for a wall-mounted RHUB3908 (unit: mm)5.1.3 Installation Environment of an RHUB3908The installation environment of an RHUB3908 involves the running environment specificationsfor the RHUB3908 and other specifications.RHUB3908 Running Environment SpecificationsTable 5-1 shows the environment specifications for the RHUB3908 installed indoors.lThe temperature and humidity of the installation position must ensure normal operation. Acool and ventilated place is recommended.lThe heat dissipation holes on the RHUB3908 cannot be blocked.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.19
Table 5-1 RHUB3908 environment specificationsSpecificationsInstallationScenarioRHUB3908QuantityCondition RemarksOperatingtemperatureInstalled on awall or in a 19-inch rack.N/A -5°C to +50°CN/AInstalled in ashelf.1 -5°C to +45°CN/A2 -5°C to +43°CN/A3 -5°C to +40°CN/ARelativehumidityInstalled in allscenarios.N/A 5% RH to95% RHN/AAltitude N/A N/A -60 m to+1800 mWorks properly.1800 m to4000 mAbove the 1800 m altitude,the maximum operatingtemperature decreases by 1°Ceach time the altitudeincreases by 220 m. NOTEInstalling more than one RHUB3908, 1 U space is required between two RHUB3908s.Other Running Environment SpecificationslThe RHUB3908 cannot be installed at an air outlet of the heat dissipation box of an airconditioner or other heat-generating appliances.lThe RHUB3908 cannot be installed near a strong heat source.lThe RHUB3908 cannot be installed in a position with water dripping, such as outdoorequipment of air conditioners, pipe, and leaking or dripping roofs.lThe installation position must be far from rains. If the RHUB3908 is installed on a wall,there must be no window on either side of the wall.lThe installation position must be far away from high voltage, highly corrosive devices,flammable or explosive substances, and electromagnetic interference.lThe RHUB3908 must be installed in a dry, ventilating, and dust-proof place.lIf the RHUB3908 is installed in parking areas or basements, the installation position mustbe well-ventilated.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.20
5.2 Installation ProcessThe RHUB3908 installation involves installing an RHUB3908 module, installing RHUB3908cables, checking the RHUB3908 hardware installation, and powering on the RHUB3908.Figure 5-11 shows the RHUB3908 installation process.Figure 5-11 RHUB3908 installation process5.3 Installing an RHUB3908An RHUB3908 can be installed in a cabinet, rack, shelf, or on a wall.5.3.1 Installing an RHUB3908 in a 19-Inch Cabinet or RackThis section describes how to install an RHUB3908 in a 19-inch cabinet.ProcedurelThe following describes how to install an RHUB3908 with mounting ears in reverse mode:NOTEIf necessary, request one more person for assistance.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.21
1. With one hand holding it, align the mounting holes with the installation holes, slowlypush the RHUB3908 into the required position in the cabinet, as shown in Figure5-12.Figure 5-12 Pushing an RHUB3908 into a cabinet2. Use a torque screwdriver or Phillips screwdriver to tighten the four M6×16 screwswith a torque of 2 N•m, as shown in Figure 5-13.Figure 5-13 Tightening screwslThe following describes how to install an RHUB3908 with mounting ears aligned with theRHUB3908 panel:NOTEIf necessary, request one more person for assistance.1. Remove the mounting ears on both sides of the RHUB3908 by removing the fourM4×8 screws, as shown in Figure 5-14.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.22
Figure 5-14 Removing mounting ears and screws2. Use a torque screwdriver or Phillips screwdriver to tighten the four M4×8 screws witha torque of 1.4 N•m to install the removed mounting ears again, as shown in Figure5-15. The mounting ears must be aligned with the RHUB3908 panel.Figure 5-15 Installing mounting ears in standard mode3. With one hand holding it, align the mounting holes with the installation holes, slowlypush the RHUB3908 into the required position in the cabinet, as shown in Figure5-16.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.23
Figure 5-16 Pushing an RHUB3908 into a cabinet4. Use a torque screwdriver or Phillips screwdriver to tighten the four M6×16 screwswith a torque of 2 N•m, as shown in Figure 5-17.Figure 5-17 Tightening screws----End5.3.2 Installing an RHUB3908 in a 19-Inch ShelfIf a shelf houses more than one RHUB3908, 1 U space is required between two RHUB3908s.The PSU must be installed at the bottom of the cabinet.ProcedurelThe following describes how to install an RHUB3908 with mounting ears installed inreverse mode:NOTEIf necessary, request one more person for assistance.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.24
1. With one hand holding it, align the mounting holes with the installation holes, slowlypush the RHUB3908 into the required position in the shelf.2. Use a torque screwdriver or Phillips screwdriver to tighten the four M6×16 screwswith a torque of 2 N•m, as shown in Figure 5-18.Figure 5-18 Tightening screwslThe following describes how to install an RHUB3908 with mounting ears installed instandard mode:NOTEIf necessary, request one more person for assistance.1. Remove the mounting ears on both sides of the RHUB by removing the four M4×8screws, as shown in Figure 5-19.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.25
Figure 5-19 Removing mounting ears and screws2. Use a torque screwdriver or Phillips screwdriver to tighten the four M4×8 screws witha torque of 1.4 N•m to install the removed mounting ears again, as shown in Figure5-20. The mounting ears must be aligned with the RHUB panel.Figure 5-20 Installing mounting ears in standard mode3. With one hand holding it, align the mounting holes with the installation holes, slowlypush the RHUB3908 into the required position in the cabinet, as shown in .4. Use a torque screwdriver or Phillips screwdriver to tighten the four M6×16 screwswith a torque of 2 N•m, as shown in Figure 5-21.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.26
Figure 5-21 Tightening screws----End5.3.3 Installing an RHUB3908 on a WallAn RHUB3908 can be installed on a wall.ProcedureStep 1 The mounting ears are installed in reverse mode by default. Before installing an RHUB3908 ona wall, modify the installation mode of the mounting ears on the RHUB3908.lUse a torque screwdriver or Phillips screwdriver to remove the mounting ears on both sidesof the RHUB3908 by removing the four M4×8 screws, as shown in Figure 5-22.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.27
Figure 5-22 Removing screws and mounting earslRotate the mounting ears 90 degrees clockwise, and use a torque screwdriver or Phillipsscrewdriver to secure the mounting ear with a torque of 1.4 N•m, as shown in Figure 5-23.Figure 5-23 Installing mounting ears and screwsStep 2 Determine the position on the wall for installing the RHUB3908 based on the requirements inthe engineering blueprint and Installation Clearance Requirements of an RHUB. Place theRHUB3908 to the position to be installed against the wall, and then mark the four anchor pointswhere the mounting ear screws are fastened using a marker, as shown in Figure 5-24.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.28
Figure 5-24 Anchor points for installing an RHUB3908 on a wall(1) Level (2) RHUB3908 (3) WallCAUTIONTo prevent inhalation or eye contact with dust, take adequate preventive measures when drillingholes.Step 3 Drill holes at the anchor point and install expansion bolts, as shown in Figure 5-25.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.29
Figure 5-25 Drilling holes and installing expansion bolts(1) M6×60expansion bolt(2) Nut (3) Spring washer (4) Flat washer (5) Extension tub1. Use a hammer drill with bit 8 to drill holes with a diameter of 8 mm and a depth of 45 mmto 50 mm at the marked anchor points. All the holes have the same depth.2. Use a vacuum cleaner to clear the dust inside and around each hole. If the distance betweentwo holes is incorrect, mark and drill holes again.3. Partially tighten an expansion bolt and place it vertically into each hole.4. Use a rubber mallet to hit the expansion bolt until the entire expansion sleeve is in the hole.5. Remove the M6×60 bolt, nut, spring washer, and flat washer from each expansion bolt insequence.NOTICEAfter removing an expansion bolt, ensure that the top of the expansion sleeve is level withthe wall. If it is not level, the RHUB3908 cannot be installed on the concrete floor evenlyand securely.Step 4 Align the mounting holes with the four M6×60 expansion bolts. Install spring washer 6 and flatwasher 6 in sequence on each M6×60 expansion bolt, insert the bolts to each expansion tub, andthen use a torque wrench or socket wrench to tighten the four M6×60 bolts with a torque of 5N•m to secure the RHUB3908 to the wall, as shown in Figure 5-26.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.30
Figure 5-26 Installing an RHUB3908 on a wallNOTEAs shown in the preceding figure, when the RHUB3908 is placed against the wall, ensure that theRHUB3908 panel is vertical to the ground and the PSU is on the lower part of the RHUB3908 panel.----End5.4 Installing RHUB3908 CablesThis section describes how to install cables for an RHUB3908.5.4.1 Requirements for Cable LayoutCables must be routed according to the specified cabling requirements to prevent signalinterference.NOTEIf a cable listed below is not required, skip the requirements for routing the cable.General Requirements for Cable Layout中国标准LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.31
l综合布线系统工程设计规范 GB 50311-2007l综合布线工程验收规范(含条文说明) GB 50312-2007l安全防范工程技术规范 GB 50348-2004l电子信息系统机房施工及验收规范 GB 50462-2008l智能建筑工程质量验收规范 GB 50339-2003l建筑电气工程施工质量验收规范 GB 50303-2002l通信管道工程施工及验收技术规范 GB 50374-2006国际标准l用户建筑综合布 ISO/IEC 11801l商业建筑电信布线标准 EIA/TIA 568l商业建筑电信布线安装标准 EIA/TIA 569l商业建筑通信基础结构管理规范 EIA/TIA 606l商业建筑通信接地要求 EIA/TIA 60l信息系统通用布线标准 EN 50173l信息系统布线安装标准 EN 50174Bending radiuslThe bending radius of a power cable or a protection ground (PGND) cable is at least threetimes the diameter of the cable.lThe bending radius of an optical cable is at least 20 times the diameter of the optical cable,and the minimum bending radius of the branch at each end of the optical cable is 30 mm.lThe bending radius of the signal cable must be at least five times the diameter of the cable.Cable BindinglCables of the same type are bound together.lDifferent types of cables must be separately routed with a minimum spacing of 30 mm andcannot be entangled or crossed.lThe cables are bound tightly and neatly and the cable sheath is intact.lThe cable ties face the same direction and all cable ties bound at similar positions must bein a straight line.lThe extra length of each indoor cable tie must be cut off. A slack of 5 mm is reserved foreach outdoor cable tie. All cut surfaces have no sharp edges.lLabels or nameplates are attached to both ends, joints, or turns of cables after they areinstalled.Safetyl穿管/线槽采用钢管或阻燃聚氯乙烯硬质管,线槽的截面利用率应为30%~50%,穿管的截面利用率应为25%~30%。lCables are placed away from sharp objects or wall burrs. If these positions are inevitable,protection pipes are required for the cables.lCables are routed away from heat sources, or heat-insulation materials are added betweencables and heat sources.lCables are routed away the cooling vents of the RHUB3908.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.32
lA clearance is reserved at turns of a cable or the position close to a device, facilitating cableand device maintenance. The recommended clearance is about 0.1 m.Requirements for Special CablesEthernet CablelA maximum of 100 Ethernet cables can be bundled if no PVC pipes are used. If pipes areused, a maximum of 24 Ethernet cables can be led through a pipe. In this case, ensure that1/3 space inside the pipes must be vacant.Power cablelPositions for routing power cables meet requirements of the engineering design.lCables are routed only by qualified and trained personnel before all preparations are made.lCables are routed in an untangled and orderly fashion.PGND cablelPGND cables are buried in the ground or routed indoors. They cannot be routed overheadbefore they are routed into the equipment room.lOuter conductors of coaxial cables and both ends of the shield layers on shielded cablesare in proper electrical contact with the metal surface of the equipment to which they areconnected.lPGND cables and signal cables are installed in an untangled and orderly fashion. A certaindistance is reserved between them to prevent interference from each other.lFuses or switches are not allowed on PGND cables.lOther devices cannot be used for electrical connections of PGND cables.lAll the metal parts in the equipment are reliably connected to the ground terminal.Optical cablelCables are routed in an untangled and orderly fashion.lOptical fibers cannot be bound at turns.lOptical fibers cannot be stretched with too much force or stepped on, and they are far awayfrom sharp objects. Heavy objects cannot be placed on optical cables.lWhen optical cables are routed, the extra length of the cables is coiled around specialdevices, such as a fiber coiler.lEven strength is applied when optical cables are coiled and optical cables cannot be bentin a forcible manner.lVacant optical connectors are covered with dust-proof caps.lFiber optic cables cannot be squeezed by the cabinet door when routed through the cabinet.lIf optical cables need to be routed on the tower platform, the optical cables are routed alongthe inner side of the guard rail and the distance between the guard rail and the cable is theshortest one.lIf optical cables need to be routed close to a device on the tower, the optical cables aresecured to the guard rail or pole with cable clips and the device cannot be far away fromthe position for securing the optical cables.lIf the optical cable close to a device on the tower is too long, the optical cables are wrappedand secured to the tower.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.33
5.4.2 RHUB3908 Cable ListThis section describes the connector types and connections of the RHUB3908 cables.Table 5-2 lists RHUB3908 cables.Table 5-2 RHUB3908 cable listCable One End The Other EndConnector Connectedto...Connector Connected to...PGND cable OT terminal (M4,6 mm2 [0.009 in.2])Ground screwson theRHUB3908OT terminal(M6, 6 mm2[0.009 in.2])Ground terminalon the externalground barRHUB3908PowerSupply CableC13 femaleconnectorAC powerinput socket onthe RHUB39083-pin connector External powerinput socketCPRI OpticalFiberDLC connector CPRI port onthe LBBP,WBBP orUBBP in theBBUDLC connector CPRI0 or CPRI1port on theRHUB3908CPRI0 orCPRI1 port onthe RHUB3908DLC connector CPRI0 or CPRI1port on theRHUB3908CPRI port onthe LBBP,WBBP orUBBP in theBBUFC connector,SC connector, orLC connectorODFCPRI0 orCPRI1 port onthe RHUB3908FC connector,SC connector, orLC connectorODFEthernetCableRJ45 connector CPRI_E0~CPRI_E7 port onthe RHUB3908RJ45 connector CPRI_E0~CPRI_E1 port on thepRRU3901(Optional)RHUB3908Alarm CableRJ45 connector EXT_ALMport on theRHUB3908Bare end Alarm signal portof the monitoredequipment LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.34
NOTElIf one end of the CPRI cable is connected to the DLC connector, the other end connects the BBU, orRHUB3908 through the DLC connector. If one end of the CPRI cable is connected to the ODF adapter,the other end connects the BBU or RHUB3908 through a connector corresponding to the adapter. Theconnectors include the FC connector, SC connector, and LC connector.lThe Extender can be used to lengthen the distance between the RHUB3908 and the pRRU3901connected using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts,one between the RHUB3908 and the Extender and the other between the Extender and the pRRU3901.5.4.3 Cable ConnectionsThis section describes the cable connections for an RHUB3908.Figure 5-27 shows the cable connections for an RHUB3908. The port of GE0, GE1 and ETHare reserved.Figure 5-27 Cable connections for an RHUB3908(1) CPRI optical cable (2) RHUB3908 alarm cable (3) Ethernet cable(4) RHUB3908 power cable (5) PGND cable -NOTEThe Extender can be used to lengthen the distance between the RHUB3908 and the pRRU3901 connectedusing the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one betweenthe RHUB3908 and the Extender and the other between the Extender and the pRRU3901.5.4.4 RHUB3908 Cable Installation ProcessThis section describes the process of installing RHUB3908 cables.Figure 5-28 shows the RHUB3908 cable installation process.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.35
Figure 5-28 RHUB3908 cable installation process5.4.5 Installing an RHUB3908 PGND CableAn RHUB3908 PGND cable ensures proper grounding of an RHUB3908.PrerequisitesThe OT terminals at both ends of the PGND cable are prepared.ContextThe yellow and green or green PGND cable is a single cable. The cross-sectional area of thePGND cable is 6 mm2 (0.009 in.2). Both ends of the cable are OT terminals, as shown in Figure1.Figure 5-29 Exterior of a PGND cable(1) OT terminal (6 mm2 [0.009 in.2], M4) (2) OT terminal (6 mm2 [0.009 in.2], M6)LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.36
NOTElIf the PGND cable is provided by the customer, a copper-core cable with a minimum cross-sectionalarea of 6 mm2 (0.009 in.2) or 10 AWG is recommended.lThe OT terminals at both ends of the PGND cable are assembled at the site.lThe M6 OT terminal has the default size. You can replace it with another OT terminal of the expectedsize based on the site requirement. NOTICElEnsure proper grounding of the RHUB3908 using a PGND cable.lWhen installing the PGND cable, tightly press the OT terminal in the correct direction, asshown in Figure 5-30.Figure 5-30 Correct direction of an OT terminal for the PGND cableProcedureStep 1 Route the PGND cable by referring to Requirements for Cable Layout.Step 2 Use a torque screwdriver or Phillips screwdriver to secure the M4 OT terminal at one end of thePGND cable to the ground screw on the RHUB3908 panel with a torque of 1.4 N•m. If the OTterminal is a one-hole OT terminal, connect it to the ground screw on the lower part of theRHUB3908 panel, as shown in Figure 5-31.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.37
Figure 5-31 Installing an RHUB3908 PGND cableStep 3 Use a torque screwdriver or Phillips screwdriver to secure the M8 OT terminal at one end of thePGND cable to the wiring terminal on the ground bar at the site with a torque of 1.4 N•m.----EndFollow-up Procedure1. Route the cable, and then use a cable tie to bind the cable. For details, see Requirementsfor Cable Layout.2. Label the installed cable. For details, see section 8.3 Attaching an L-Shaped Label.5.4.6 Installing an Ethernet CableThis section describes how to install an Ethernet cable. A pRRU3901 can have two transmissionports or three transmission ports, requiring the same installation operations. This section usesthe pRRU3901 with three transmission ports as an example.PrerequisiteslEthernet cables are not delivered, and they must be prepared onsite. You need to use anetwork cable tester to test the Ethernet cable connection.lThe Ethernet cable must be of Category 5e (enhanced) or higher. In addition, its cross-sectional area must be 24 AWG or larger and frame spread rating must be CM or higher.With the internal PoE module providing power, the maximum length of an Ethernet cableis 100 m. With the Extender, the distance of the pRRU3901 and RHUB3908 can beextended by the Extender up to a total distance of 200 m.ContextThe Ethernet cable has the following functions:lProvides power supply for the pRRU when connected to the CPRI_E0 port on the pRRU.lTransmits CPRI signals between an RHUB3908 and a pRRU.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.38
Using the CPRI_E1 port on the pRRU3901 has the same Ethernet cable connection to theRHUB3908 as using the CPRI_E0 port. The following section describes the connection usingthe CPRI_E0 port.ProcedureStep 1 Make the Ethernet cables.1. Assemble an RJ45 connector and an Ethernet cable by following instructions in Assemblingthe Unshielded RJ45 Connector and the Ethernet Cable of Installation Reference.NOTEFollow pin assignment instructions described in section Ethernet Cable in LampSite HardwareDescription to assemble the unshielded RJ45 connector and the Ethernet cable. Otherwise, thetransmission signal quality deteriorates and CPRI links may be disconnected.2. Check whether the made RJ45 connector is qualified by following instructions in Checkingthe Appearance of Metal Contact Strips.3. To complete the assembly of the other end, repeat Step 1.1 and Step 1.2.4. Check whether the touch points on the connectors at both ends are normally conducted andwell contacted and whether the connections are correct by following instructions in Testingthe Connection of Assembled Cables of Installation Reference.Step 2 Remove the dustproof cap of the CPRI_E0 port on the pRRU3901.Step 3 Connect the RJ45 connector at one end of the Ethernet cable to the CPRI_E0 port on thepRRU3901 panel.Step 4 Optional: Connect the RJ45 connector at the other end of the Ethernet cable to the output portof the Extender. Then, connect the RJ45 connector at one end of another Ethernet cable to theinput port of the Extender.If the Extender is used, the Ethernet cable is divided into two parts, one between the RHUB3908and the Extender and the other between the Extender and the pRRU3901.Step 5 Connect the RJ45 connector at the other end of the Ethernet cable to any port ranging fromCPRI_E0 to CPRI_E7 on the RHUB3908 panel based on the engineering design, as shown inFigure 5-32.Figure 5-32 Install an Ethernet cable between an RHUB3908 and a pRRU3901(1) Ethernet cable (2) CPRI_E0 port on the pRRU3901LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.39
NOTEThe pRRU3901 can have two transmission ports plus PWR port or three transmission ports (plus PWRport or no PWR port). The Ethernet cable connection between the pRRU3901 in any appearance and theRHUB3908 is similar. This section uses the pRRU3901 with three transmission ports plus no PWR portas an example.----EndFollow-up Procedure1. Route the cable, and then use a cable tie to bind the cable. For details, see 5.4.1Requirements for Cable Layout.2. Label the installed cable. For details, see section 8.3 Attaching an L-Shaped Label.5.4.7 Installing CRPI Optical CablesOptical fibers can be used to interconnect BBU and RHUB3908s, or cascade RHUB3908s.ContextlMulti-mode optical modules for CPRI ports are labeled MM and each has a black or graypuller.lSingle-mode optical modules are labeled SM and each has a blue puller.lFor details about the connection of CPRI optical cables, see Typical Networking inLampSite Technical Description and CPRI Optical Fiber in LampSite HardwareDescription.lAn optical module to be installed must match the rate of its corresponding port.NOTICEThe performance of an optical module that is exposed to the air for more than 20 minutes maybe abnormal. Therefore, you must insert a fiber optic cable into an unpacked optical modulewithin 20 minutes.ProcedureStep 1 Install an optical module, as shown in Figure 5-33 and Figure 5-34.1. Remove the dust-proof cap from the CPRI port on the RHUB3908 panel.2. Remove the dust-proof cap on the optical module.3. Lower the puller of the optical module.4. Insert the optical module into the CPRI port on the RHUB3908, BBU or ODF.5. Raise the puller of the optical module.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.40
Figure 5-33 Removing the dust-proof cap from a portFigure 5-34 Installing an optical moduleStep 2 Install a CPRI optical cable, as shown in Figure 5-35.1. Remove the dust-proof cap from the optical cable connector.2. Install the optical cables by referring to Table 5-3.Table 5-3 CPRI optical cable connectionsOne End The Other EndConnectorConnected to Connector Connected toDLCconnectorBBU3900/LBBP&WBBP&UBBP/CPRI portDLC connector CPRI0 or CPRI1 port onthe RHUB3908CPRI0 or CPRI1 port on theRHUB3908CPRI0 or CPRI1 port onthe RHUB3908BBU3900/LBBP&WBBP&UBBP/CPRI portFC, SC, or LCconnectorODFCPRI0 or CPRI1 port on theRHUB3908 LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.41
NOTElIf one end of the CPRI cable is connected to the DLC connector, the other end connects the BBU orRHUB3908 through the DLC connector. If one end of the CPRI cable is connected to the ODF adapter,the other end connects the BBU or RHUB3908 through a connector corresponding to the adapter. Theconnectors include the FC connector, SC connector, and LC connector.lWhen connecting the CPRI cable to the TX and RX ports of the optical module through connectors ina cross manner, ensure that one end of a core of the CPRI cable is connected to the TX port and theother end is connected to the RX port. Figure 5-35 shows how to install a CPRI optical cable forconnecting the BBU and RHUB3908s.Figure 5-35 Installing an CRPI optical cable----EndFollow-up Procedure1. Route the cable, and then use a cable tie to bind the cable. For details, see 5.4.1Requirements for Cable Layout.2. Label the installed cable. For details, see section 8.3 Attaching an L-Shaped Label.5.4.8 Installing an RHUB3908 Alarm Cable (Optional)An RHUB3908 alarm cable transmits dry node alarm signals.PrerequisitesConnectors for an alarm cable are prepared.ContextFigure 5-36 shows the exterior of an RHUB3908 alarm cable. RHUB Cable List shows theinstallation position on both ends of the RHUB3908 cable.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.42
Figure 5-36 RHUB3908 alarm cableProcedureStep 1 Connect the RJ45 connector on one end of the alarm cable to the EXT_ALM port on theRHUB3908.Step 2 Connect the other end of the alarm cable to the alarm cable port on the device to be monitored.----EndFollow-up Procedure1. Route the cable, and then use a cable tie to bind the cable. For details, see 5.4.1Requirements for Cable Layout.2. Label the installed cable. For details, see section 8.3 Attaching an L-Shaped Label.5.4.9 Installing an RHUB3908 Power CableThe RHUB3908 power cable provides 110 V AC/220 V AC power supply for the RHUB3908.ProcedureStep 1 Route the power cable by referring to Requirements for Cable Layout.Step 2 Connect the power connector on the X1 end to the AC power input port on the RHUB3908 panel,as shown in Figure 5-37.Step 3 Connect the power connector on the X2 end to the external power supply port, as shown inFigure 5-37.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.43
Figure 5-37 Installing an RHUB3908 power cable----EndFollow-up Procedure1. Route the cable, and then use a cable tie to bind the cable. For details, see 5.4.1Requirements for Cable Layout.2. Label the installed cable. For details, see section 8.3 Attaching an L-Shaped Label.5.5 Checking the RHUB3908 Hardware InstallationAfter an RHUB3908 is installed, check the installation of hardware including the devices andrelated cables.Table 5-4 lists the hardware installation checking items.Table 5-4 Hardware installation checking listNo. Item1The position for each device conforms to the engineering design and meets thespace requirement.2 Ensure that the RHUB3908 is properly installed.3 The surface of the RHUB3908 is neat and clean. The external paint is intact. Thelabels, tags, and nameplates are correct, legible, and complete. Table 5-5 lists the checking list of the power cable and PGND cable connections.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.44
Table 5-5 Checklist for power cable and PGND cable connectionsNo. Item1The power cables and PGND cables comply with the requirements of localregulations.2 The power cables or the PGND cables are not inversely connected or short-circuited.3 The power cables and PGND cables are bound separately from other cables.4 Labels are attached to both ends of the power cables, PGND cables, optical fibers,and Ethernet cables.5 The power cables and PGND cables are intact.6 The power cables and PGND cables have no weld nugget.7 No breaking device such as a switch or fuse lies in the electric connection of thegrounding system.8 The redundant part of PGND cable is stripped off.9 The lugs at both ends of the power cable or PGND cable are securely soldered orcrimped.10 The flat washers and spring washers are fixed securely and closely at all the wiringterminals.11 The work GND cable and PGND cable of the BTS share a group of groundingconductors with the lightning and GND cables of the building. Table 5-6 lists the check items of the signal cable connection.Table 5-6 Checklist for the signal cable connectionNo. Item1The connectors of the signal cables must securely connected.2 The connectors of the signal cables are intact.3 The signal cables are intact.4 The cable ties are evenly spaced. The signal cables are bound neatly with cableties to proper tightness, and arranged at even intervals in the same direction.5 The extra length of the cable ties is cut and removed. The cut surfaces of the indoorcables are smooth and have no sharp edges.6 The cable layout facilitates maintenance and expansion.7 Correct and clear labels are attached to both ends of the signal cables.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.45
No. Item8The distance between the bundled fiber tails and the RHUB3908 panel is less than70 mm. Table 5-7 lists the checking items for other cable connections.Table 5-7 Checklist for other cable connectionsNo. Item1The connectors of the other cables must securely connected.2 Labels on the cables are legible and bound based on the engineering requirements.The cables must be bound tightly and neatly. The sheaths of the cables must notbe damaged.3 Positions for routing the cables must meet requirements of the engineering design. 5.6 Power-on Check on an RHUB3908This section describes the power-on check on the RHUB3908 after the RHUB3908 hardware isinstalled and checked.ContextDANGERPower-on check involves high-voltage operation. Be cautious when conducting the power-oncheck. Any direct contact with the input voltage or indirect contact through damp objects mightendanger your life.ProcedureStep 1 Measure the RHUB3908 earth resistance.If... Then...The RHUB3908 earth resistance is lessthan 10 ohmsGo to Step 2.The RHUB3908 earth resistance is equalto or larger than 10 ohmsFind out the cause and ensure that the resistancemeets requirement. Then, go to Step 2. Step 2 Measure the voltage of the RHUB3908.LampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.46
If... Then...The external power supply ranges from100 V AC to 240 V ACGo to Step 3.The external power supply does notrange from 100 V AC to 240 V ACFind out the cause and ensure that the resistancemeets requirement. Then, go to Step 3. Step 3 Power on the RHUB3908. Wait 3 to 5 minutes, check the status of the RUN indicator of theRHUB3908 after the RHUB3908 runs properly.If the Status ofthe RUNIndicator...It Indicates that... Then...Steady on The power supply isnormal while the board isfaulty.Power off the RHUB3908, and power on itagain after rectifying the board fault.Steady off There is no power inputor the board is faulty.Power off the RHUB3908, and check thepower input again. Rectify the board faultyand power on the RHUB3908 again if thepower input is normal.On for 1s and offfor 1sThe devices workproperly.End the operation.On for 0.125s andoff for 0.125sThe board software isbeing uploaded.Power off the RHUB3908 if the uploading isnot finished in 5 minutes, and check whetherthe configuration file is correct. Power on theRHUB3908 again after the fault is rectified.----EndLampSiteInstallation Guide 5 Installing an RHUB3908Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.47
6 Installing a pRRU3901About This ChapterThis chapter describes the pRRU3901 installation process. The pRRU3901 can have twotransmission ports (plus PWR port) or three transmission ports (plus PWR port or no PWR port).Unless otherwise specified, this document uses the pRRU3901 with three transmission portsplus no PWR port as an example.NOTEThe pRRU3901 with three transmission ports plus no PWR port is named the pRRU3901a in NorthAmericain.6.1 Information About the InstallationThis section describes the information that you must be familiar with before installing apRRU3901, including the pRRU3901 product family, installation scenarios, installation spaceand environment requirements.6.2 Obtaining the MAC Address (Optional)Before installing a pRRU3901, record the media access control (MAC) address, which will beused during pRRU3901 commissioning. This section applies only when a pRRU3901 with threetransmission ports is configured with a Wi-Fi daughter board.6.3 Installation ProcessThis section describes the pRRU3901 installation process, which involves installing apRRU3901, and cables, checking the pRRU3901 hardware installation, and powering on thepRRU3901.6.4 Installing a pRRU3901This section describes the pRRU3901 installation process. A pRRU3901 can be installed on awall, ceiling, indoor metal pole, or keel.6.5 Installing pRRU3901 CablesThis section describes the procedure of installing the pRRU3901 cables.6.6 Checking the pRRU3901 Hardware InstallationpRRU3901 hardware installation checking includes hardware and cable installation checking.6.7 Powering on the pRRU3901LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.48
This section describes the power-on check on the pRRU3901 after the pRRU3901 hardware isinstalled and checked.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.49
6.1 Information About the InstallationThis section describes the information that you must be familiar with before installing apRRU3901, including the pRRU3901 product family, installation scenarios, installation spaceand environment requirements.6.1.1 pRRU3901 Product FamilyThis chapter describes the configurations and functions of the pRRU3901 components.Table 6-1 lists the pRRU3901 product family.Table 6-1 pRRU3901 product familyCategoryEquipment OptionalItemQuantity FunctionMainequipmentpRRU3901 Mandatory 1 Processes the radio frequencysignals.ExternalantennaOptional 2 Provides external antennas forthe pRRU3901.NOTEConfigure two external antennasfor each RF daughter board.AuxiliarydeviceMounting kits Mandatory 1 Supports the pRRU3901installation on a wall, pole,ceiling, or keel. The mountingkits vary with the pRRU3901installation mode.Extender Optional 1 Extends the distance betweenthe pRRU3901 andRHUB3908. 6.1.2 pRRU3901 Installation ScenarioThe pRRU3901 can be installed on a wall, ceiling, pole, or keel. The following table describesthe installation in different scenarios.Installing a pRRU3901 on a wallNOTElThe pRRU3901 must keep a minimum of 0.5 m away from the power equipment with interference,and keep a minimum of 2 m away from the source with radiation.lThe pRRU3901 must keep away from a metal wall to avoid the impact on the antenna performance.When a pRRU3901 is installed on a wall, installation modes vary with the quality of wall, asshown in Table 6-2.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.50
Table 6-2 Wall-mounted suggestionInstallationModeRequirements Mounting Brackets InstallationDiagramInstalling thepRRU3901 ona wall bydrilling holesFor details, seepRRUInstalled on aWall.lThe wall can beara load at least fourtimes the weightof a pRRU3901.lThe screws mustbe tightened witha torque of 10N·m. This ensuresthe screws workproperly and thewall remainsintact withoutcracks in it.1. Plate2. Screw (M6X50)3. Plastic expansionsleeve4. Flat washerInstalling thepRRU3901 ona wall using aV clampthrough anattachmentplateFor details, seepRRUInstalled on aPlate.lThe wall can beara load at least fourtimes the weightof a pRRU3901.lThe thickness ofthe wall is lessthan the boltlength (80 mm).1. Plate2. V clamp3. Bolt (M6X80)Installing thepRRU3901 ona wall using aplate on ametal walllThe wall cannotbear a load at leastfour times theweight of thepRRU3901. Forexample, EPSwalls, MDFwalls, or wallscannot be drilled.lThe wall is toothick to drill, andthe pRRU3901cannot beinstalled on a wallusing a V clampthrough anattachment plate.The plate is prepared bycustomers. LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.51
Installing a pRRU3901 on a ceilingWhen a pRRU3901 is installed on a ceiling, installation modes vary with the quality of theceiling, as shown in Table 6-3.Table 6-3 Ceiling-mounted suggestionInstallationModeRequirements Mounting Brackets InstallationDiagramInstalling thepRRU3901 ona ceiling bydrilling holesFor details, seepRRUInstalled on aCeiling.lThe ceiling, suchas a concreteceiling, can bear aload at least fourtimes the weightof thepRRU3901.lThe screws mustbe tightened witha torque of 10N·m. This ensuresthe screws workproperly and theceiling remainsintact withoutcracks in it.1. Plate2. Screw (M6X50)3. Plastic expansionsleeve4. Flat washerInstalling thepRRU3901 ona ceiling usinga V clampthrough anattachmentplateFor details, seepRRUInstalled on aPlate.lThe ceiling, suchas a concreteceiling, can bear aload at least fourtimes the weightof thepRRU3901.lThe thickness ofthe ceiling is lessthan the boltlength (80 mm).1. Plate2. V clamp3. Bolt (M6X80)Installing thepRRU3901 ona poleFor details, seepRRUInstalled on aPole.A pole under theceiling can bear aload at least fourtimes the weight ofthe pRRU3901.For details, see Table6-4.For details, see Table6-4.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.52
InstallationModeRequirements Mounting Brackets InstallationDiagramInstalling thepRRU3901 ona keelFor details, seepRRUInstalled on aKeel.A keel under theceiling can bear aload at least fourtimes the weight ofthe pRRU3901.For details, see Table6-5.For details, see Table6-5. Installing the pRRU3901 on a poleWhen a pRRU3901 is installed on a pole, installation modes vary with the diameter of the pole,as shown in Table 6-4.Table 6-4 Pole-mounted suggestionInstallationModeRequirements Mounting Brackets InstallationDiagramInstalling thepRRU3901 ona poleFor details, seepRRUInstalled on aPole.The diameter of thepole ranges from 30mm to 70 mm.1. Plate2. V clamp3. Bolt (M6X80)The diameter of thepole ranges from 70mm to 110 mm.1. Plate2. Hose clamp, which isprepared by thecustomer Installing the pRRU3901 on a keelThe pRRU3901 can be installed on a keel of U-shape, T-shape, or H-shape. For the keels ofother shapes, they are determined based on the onsite requirements.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.53
Table 6-5 Keel-mounted installation suggestionInstallationModeRequirements Mounting Brackets InstallationDiagramInstalling thepRRU3901 ona keelFor details, seepRRUInstalled on aKeel.The keel is in U-shape, T-shape, H-shape, or othershapes.1. Plate2. V clamp3. Bolt (M6X80)shows the pRRU3901installed on a U-shaped keel. 6.1.3 Space RequirementsWhen the pRRU3901 is installed on a wall, ceiling, pole or keel, the minimum space is requiredfor easy cabling and O&M. Based on the engineering practice, the recommendation for theinstallation space is provided.NOTEDuring installation, a minimum clearance of 2 m must be reserved between the pRRU3901 working on the2.6 GHz band and the Wi-Fi module if they need to process services concurrently.Figure 6-1 shows the recommended space requirements of the pRRU3901 when the externalantenna is required.Figure 6-1 Recommended space requirements of the pRRU3901When the external antenna is required, the recommended space for installing a single pRRU3901is described as follows:lAt least 300 mm above the pRRU3901 is reserved for maintenance.lAt least 300 mm under the pRRU3901 is reserved for cabling.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.54
lAt least 300 mm on the left of the pRRU3901 is reserved for maintenance.lAt least 300 mm on the right of the pRRU3901 is reserved for maintenance.lAt least 400 mm in front of the pRRU3901 is reserved for maintenancelAt least 20 mm on the back of the pRRU3901 is reserved for ventilation.Figure 6-2 shows the minimum space requirements of the pRRU3901 when the external antennais not required.Figure 6-2 Minimum space requirements of the pRRU3901When the external antenna is not required, the minimum space for installing a single pRRU3901is described as follows:lAt least 50 mm above the pRRU3901 is reserved for maintenance.lAt least 150 mm under the pRRU3901 is reserved for cabling.lAt least 50 mm on the left of the pRRU3901 is reserved for maintenance.lAt least 50 mm on the right of the pRRU3901 is reserved for maintenance.lAt least 50 mm in front of the pRRU3901 for maintenance.lAt least 20 mm on the back of the pRRU3901 is reserved for ventilation.6.1.4 pRRU3901 Installation Environment RequirementsThe installation environment of a pRRU3901 involves the running environment specificationsfor the pRRU3901 and other specifications.pRRU3901 Running Environment SpecificationsTable 6-6 shows the environment specifications for the pRRU3901 installed indoors.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.55
Table 6-6 pRRU3901 environment specificationsSpecificationsCondition RemarksOperatingtemperature- 5°C to + 40°C -Relativehumidity5% RH to 95% RH -Altitude - 60 m to + 1800 m Works properly.1800 m to 4000 m Above the 1800 m altitude, themaximum operating temperaturedecreases by 1°C each time the altitudeincreases by 220 m. Other Running Environment SpecificationslThe pRRU3901 cannot be installed at an air outlet of the heat dissipation box of an airconditioner or other heat-generating appliances.lThe pRRU3901 cannot be installed near a strong heat source.lThe pRRU3901 cannot be installed in a position with water dripping, such as outdoorequipment of air conditioners, pipe, and leaking or dripping roofs.lThe installation position must be far from rains. If the pRRU3901 is installed on a wall,there must be no window on either side of the wall.lThe installation position must be far away from high voltage, highly corrosive devices,flammable or explosive substances, and electromagnetic interference.lThe pRRU3901 must be installed in a dry, ventilating, and dust-proof place.lIf the pRRU3901 is installed in parking areas or basements, the installation position mustbe well-ventilated.6.2 Obtaining the MAC Address (Optional)Before installing a pRRU3901, record the media access control (MAC) address, which will beused during pRRU3901 commissioning. This section applies only when a pRRU3901 with threetransmission ports is configured with a Wi-Fi daughter board.ContextThe MAC address indicates the IP address through which a device can be reached.ProcedureStep 1 Remove the backup WIFI MAC label from the front housing of the pRRU3901 and keep themsecure, as shown in Figure 6-3.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.56
NOTElDo not remove the WIFI MAC label on the side of the pRRU3901 housing.lBefore removing the backup WIFI MAC label, photograph it.Figure 6-3 Removing backup WIFI MAC labelStep 2 Save the MAC according to MAC Collection Template, and report it to the pRRU3901commissioning personnel.----End6.3 Installation ProcessThis section describes the pRRU3901 installation process, which involves installing apRRU3901, and cables, checking the pRRU3901 hardware installation, and powering on thepRRU3901.Figure 6-4 shows the pRRU3901 installation process.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.57
Figure 6-4 pRRU3901 installation process6.4 Installing a pRRU3901This section describes the pRRU3901 installation process. A pRRU3901 can be installed on awall, ceiling, indoor metal pole, or keel.NOTElThe pRRU3901 cannot be grounded. If the pRRU3901 is grounded but the RHUB3908 connected tothis pRRU3901 is not, the pRRU3901 may fail to be powered on.lA minimum distance of 50 cm must be reserved between the pRRU3901 and the incandescent lamp.lThe installation spacing between the pRRU3901 and the temperature sensor must be greater than 50cm.lIt is good practice to install the pRRU3901 on materials that can tolerate a temperature higher than 65°C and have an ignition point higher than 70°C.6.4.1 pRRU3901 Installation KitsThis section describes the pRRU3901 installation kits.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.58
Figure 6-5 shows the exterior of the pRRU3901 installation kits.Figure 6-5 pRRU3901 installation kits(1) V clamp (2) Plate (3) Screw (M6x50)(4) Plastic expansion sleeve (5) Bolt (M6x80) (6) Flat washerThe following figure shows the specifications of the installation plate.Figure 6-6 Plate specificationsLampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.59
6.4.2 pRRU3901 Installed on a WallIf the wall indoors has sufficient load bearing capacity and space, the pRRU3901 isrecommended to install on a wall. If the wall cannot bear the capacity, choose an installationmode based on site requirements.ContextNOTICEThis section only describes the procedure of installing the pRRU3901 on a wall without anyother auxiliary devices. The installation procedure of other wall-mounted modes is similar tothat of installing the pRRU3901 on a wall without auxiliary devices.ProcedureStep 1 Determine the position for installing the pRRU3901 based on the construction blueprint and thespace requirements.NOTEFor pRRU3901 installation space requirements, see Space Requirements.Step 2 Place the plate in the installation position against the wall. Then, level the plate and mark thetwo anchor points using a marker, as shown in Figure 6-7.Figure 6-7 Anchor points of the pRRU3901 installation kits (unit: mm)(1) Wall (2) Plate (3) Anchor pointLampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.60
CAUTIONTo prevent inhalation or eye contact with dust, take adequate preventive measures when drillingholes.Step 3 Use a hammer drill with a φ 8 bit to drill holes at the marked anchor points as shown in as shownin Figure 6-8. Use the cleaner to clean the dust inside and around the holes and measure thedistance between them. If they are inaccurately positioned, re-measure and re-drill the holes.Then, use a rubber mallet to push the two plastic expansion sleeve into the holes.Figure 6-8 Drilling holes and installing expansion boltsStep 4 Lead the M6x50 screw through the washer, and then through the drilling holes of the plate tothe plastic expansion sleeve, and tighten the screw to a torque of 5 N•m, as shown in Figure6-9.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.61
Figure 6-9 Installing the plateNOTEIf the screws cannot be tightened using a Phillips screwdriver, use a hex key or an electric screwdriver toassist the installation.Step 5 Fit the four hooks of the pRRU3901 into the installation kits, as shown in Figure 6-10. If thehooks are properly installed, a slight clack can be heard.NOTEIt is recommended that you observe the installation from one side of the pRRU3901 when inserting hooksinto the kits.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.62
Figure 6-10 Installing the pRRU3901 on a plate----End6.4.3 pRRU3901 Installed on a CeilingThis section describes the procedure of installing a pRRU3901 on the ceiling, such as theconcrete ceiling, when the ceiling has sufficient load bearing capacity and installation space.ContextNOTICEIf the pRRU3901 is installed on the ceiling, the temperature of the ceiling may increase by amaximum of 30 degrees. Therefore, whether a pRRU3901 can be installed on a ceiling dependson the ceiling material.ProcedureStep 1 Determine the position for installing the pRRU3901 based on the construction blueprint and thespace requirements.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.63
NOTEFor pRRU3901 installation space requirements, see Space Requirements.Step 2 Place the plate in the installation position against the ceiling. Then, level the plate and mark thetwo anchor points using a marker, as shown in Figure 6-11.Figure 6-11 Anchor points of the pRRU3901 installation kits (unit: mm)(1) Ceiling (2) Plate (3) Anchor point of the boltCAUTIONTo prevent inhalation or eye contact with dust, take adequate preventive measures when drillingholes.Step 3 Use a hammer drill with a φ 8 bit to drill holes at the marked anchor points as shown in as shownin Figure 6-12. Use the cleaner to clean the dust inside and around the holes and measure thedistance between them. If they are inaccurately positioned, re-measure and re-drill the holes.Then, use a rubber mallet to push the two plastic expansion sleeve into the holes.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.64
Figure 6-12 Drilling holes and installing expansion boltsStep 4 Lead the M6x50 screw through the washer, and then through the drilling holes of the plate tothe plastic expansion sleeve, and use a torque screwdriver to tighten the screw with a torque of5 N•m, as shown in Figure 6-13.Figure 6-13 Installing the plateNOTEIf the screws cannot be tightened using a Phillips screwdriver, use a hex key or an electric screwdriver toassist the installation.Step 5 Fit the four hooks of the pRRU3901 into the installation kits, as shown in Figure 6-14. If thehooks are properly installed, a slight clack can be heard.NOTEIt is recommended that you observe the installation from one side of the pRRU3901 when inserting hooksinto the kits.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.65
Figure 6-14 Installing a pRRU3901----End6.4.4 pRRU3901 Installed on a PoleA pRRU3901 can be installed on a metal pole indoors.ProcedureStep 1 Determine the position for installing the pRRU3901 based on the construction blueprint and thespace requirements.NOTEFor pRRU3901 installation space requirements, see Space Requirements.Step 2 If the diameter of the pole ranges from 30 mm to 70 mm, use the delivered V clamp, installationplate, and bolts to install the pRRU3901 on the pole. Lead the M6x80 bolt through the plate,and tighten the bolt to a torque of 5 N•m, as shown in Figure 6-15.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.66
Figure 6-15 Securing the pRRU3901 installation kits on the metal poleIf the diameter of the pole is larger than 70 mm, use the hose clamp to install the plate on thepole. The hose clamp is prepared by customers. Tighten the bolt with a torque of 5 N•m, asshown in Figure 6-16.Figure 6-16 Securing the pRRU3901 installation kits on the metal poleLampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.67
Step 3 Fit the four hooks of the pRRU3901 into the installation kits, as shown in Figure 6-17. If thehooks are properly installed, a slight clack can be heard.NOTEIt is recommended that you observe the installation from one side of the pRRU3901 when inserting hooksinto the kits.Figure 6-17 Installing a pRRU3901----End6.4.5 pRRU3901 Installed on a PlateIf the plate on the ceiling has sufficient load bearing capacity and space installation, thepRRU3901 can be installed on the plate of the ceiling indoors.ProcedureStep 1 Determine the position for installing the pRRU3901 based on the construction blueprint and thespace requirements.NOTEFor pRRU3901 installation space requirements, see Space Requirements.Step 2 Place the plate in the installation position against the wall. Then, level the plate and mark thetwo anchor points using a marker, as shown in Figure 6-18.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.68
Figure 6-18 Anchor points of the pRRU3901 installation kits (unit: mm)(1) Panel (2) Plate (3) Anchor pointCAUTIONTo prevent inhalation or eye contact with dust, take adequate preventive measures when drillingholes.Step 3 Use a hammer drill with bit 8 to drill holes at the anchor points.Step 4 Lead the bolt M6x80 through the panel and daughter board, and tighten the torque screwdriverto a torque of 5 N•m, as shown in Figure 6-19.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.69
Figure 6-19 Installing the pRRU3901 installation kitsStep 5 Fit the four hooks of the pRRU3901 into the installation kits, as shown in Figure 6-20. If thehooks are properly installed, a slight clack can be heard.NOTEIt is recommended that you observe the installation from one side of the pRRU3901 when inserting hooksinto the kits.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.70
Figure 6-20 Installing a pRRU3901----End6.4.6 pRRU3901 Installed on a KeelIf the ceiling cover cannot bear the pRRU3901, the pRRU3901 can be installed on the keel ofa ceiling.ContextBefore installing the pRRU3901 on a keel, ensure that the keel is strong enough to bear thepRRU3901.lThe installation kits of the pRRU3901 can be installed on the keel of the followingspecifications: GBT 11981-2008, JIS A6517-2002, and ASTM C635 C635M-2007. Theinstallation mode must depends on onsite requirements because there are various keels.lThis section describes the procedure of installing a pRRU3901 on the keel of JIS standardused in Japan. The procedure of installing a pRRU3901 on other keels is the same as thatof installing a pRRU3901 on the keel of JIS standard.ProcedureStep 1 Determine the position for installing the pRRU3901 based on the construction blueprint and thespace requirements.NOTEFor pRRU3901 installation space requirements, see Space Requirements.Step 2 Lead the V clamp on across the keel, and mark the projective position on the cover with a marker,as shown in Figure 6-21.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.71
Figure 6-21 Anchor points on a plate (unit: mm)CAUTIONTo prevent inhalation or eye contact with dust, take adequate preventive measures when drillingholes.Step 3 Use a hammer drill to drill holes at the anchor points. You are advised to use the hammer drillФ12.Step 4 Lead the bolt M6x80 through the installation plate and ceiling cover, and then socket to tightenthe bolt to a torque of 5 N•m, as shown in Figure 6-22.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.72
Figure 6-22 Installing the pRRU3901 installation kitsStep 5 Fit the four hooks of the pRRU3901 into the installation kits, as shown in Figure 6-23. If thehooks are properly installed, a slight clack can be heard.NOTEIt is recommended that you observe the installation from one side of the pRRU3901 when inserting hooksinto the kits.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.73
Figure 6-23 Installing a pRRU3901----End6.5 Installing pRRU3901 CablesThis section describes the procedure of installing the pRRU3901 cables.6.5.1 Requirements for Cable LayoutCables must be routed according to the specified cabling requirements to prevent signalinterference.NOTEIf certain cables listed below are not required, skip the requirements for routing these cables.General Requirements for Cable Layout中国标准l综合布线系统工程设计规范 GB 50311-2007l综合布线工程验收规范(含条文说明) GB 50312-2007l安全防范工程技术规范 GB 50348-2004l电子信息系统机房施工及验收规范 GB 50462-2008l智能建筑工程质量验收规范 GB 50339-2003l建筑电气工程施工质量验收规范 GB 50303-2002l通信管道工程施工及验收技术规范 GB 50374-2006LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.74
国际标准l用户建筑综合布 ISO/IEC 11801l商业建筑电信布线标准 EIA/TIA 568l商业建筑电信布线安装标准 EIA/TIA 569l商业建筑通信基础结构管理规范 EIA/TIA 606l商业建筑通信接地要求 EIA/TIA 60l信息系统通用布线标准 EN 50173l信息系统布线安装标准 EN 50174Bending radiuslThe bending radius of a 1/4'' jumper, a 1/2'' softer jumper, and a 1/2'' common jumper mustbe longer than 35 mm, 50 mm, and 127 mm, respectively.lThe bending radius of a power cable is at least three times the diameter of the cable.lThe bending radius of a signal cable must be at least five times of the diameter of the cable.Cable bindinglCables of the same type are bound together.lDifferent types of cables must be separately routed with a minimum spacing of 30 mm andcannot be entangled.lThe cables are bound tightly and neatly and the sheaths of the cables is intact.lThe cable ties face the same direction and all cable ties bound at similar positions must bein a straight line.lThe extra length of each indoor cable tie must be cut off. A slack of 5 mm is reserved foreach outdoor cable tie before the extra length is cut off. All cut surfaces are without sharpedges.lLabels or nameplates are attached to both ends, joints, or turns of cables after they areinstalled.SafetylCables are placed away from sharp objects or wall burrs. If these positions are inevitable,protection pipes are required for the cables.lCables are routed away from heat sources, or heat-insulation materials are added betweencables and heat sources.lA clearance is reserved at turns of a cable or the position close to a device, facilitating cableand device maintenance. The recommended clearance is about 0.1 m.Requirements for Special CablesEthernet CablelA maximum of 100 Ethernet cables can be bundled if no PVC pipes are used. If pipes areused, a maximum of 24 Ethernet cables can be led through a pipe. In this case, ensure that1/3 space inside the pipes must be vacant.6.5.2 pRRU3901 Cable ListThis section describes pRRU3901 cable connections.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.75
Table 6-7 lists pRRU3901 cables.Table 6-7 List of pRRU3901 cablesCable One End The Other EndConnector Connectedto ...Connector Connected to ...EthernetCableRJ45 connector RHUB3908/CPRI_E0~CPRI_E7 portRJ45 connector pRRU3901/CPRI_E0~CPRI_E1 portRJ45 connector AC orTransmissionportRJ45 connector pRRU3901/GEport(Optional)pRRU3901RF JumperSMA straightmale connectorExternalantenna TX/RX RF port onthe pRRU3901Based on the portmodel of theantenna system.Antenna system NOTElThe Extender can be used to lengthen the distance between the RHUB3908 and the pRRU3901connected using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts,one between the RHUB3908 and the Extender and the other between the Extender and the pRRU3901.lThe Ethernet cable used for connecting the GE port on the pRRU3901 to the AC transmission port isrequired only when the pRRU3901 have three transmission ports and is configured with the Wi-Fidaughter board.6.5.3 Cable ConnectionsThis section describes the cable connections for a single pRRU3901 and multiple pRRU3901sin UMTS, LTE FDD, UMTS+LTE FDD, LTE FDD+LTE FDD mode.Before installing the pRRU3901 cables, you must be aware of the following information:lThe pRRU3901 can obtain power supply through the power over Ethernet (PoE).lFor external antennas corresponding to RF daughter board 1, the TX port and RX port areANT0 and ANT1, respectively. For external antennas corresponding to RF daughter board2, the TX port and RX port are ANT2 and ANT3, respectively. For external antennascorresponding to RF daughter board 3, the TX port and RX port are ANT4 and ANT5,respectively.lThe external antenna system is optional, and the pRRU3901 jumpers are not delivered. Bydefault, the pRRU3901s are configured with built-in antennas. If the external antennasystem is connected, the antenna system automatically switches to the external one. Oneend of the pRRU3901 RF jumper is the SMA male connector, which is connected to theexternal antenna TX/RX RF port on the pRRU3901. The other end of the pRRU3901 RFjumper is the type N male connector, which is connected to the antenna system. For thestandard of the pRRU3901 RF jumper, see (Optional) pRRU3901 RF Jumper of theLampSite Hardware Description.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.76
Figure 6-24 shows the cable connection when the pRRU3901 is configured with only one RFDaughter Board.Figure 6-24 pRRU3901 cable connection (1)(1) Ethernet cable (2) RF jumperNOTElThe Extender can be used to lengthen the distance between the RHUB3908 and the pRRU3901connected using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts,one between the RHUB3908 and the Extender and the other between the Extender and the pRRU3901.lWhen two Ethernet cables are used to transmit CPRI signals, connect one end of the cables to theCPRI_E0 and CPRI_E1 ports on the pRRU3901 panel and the other end to any two ports of CPRI_E0to CPRI_E7 on the RHUB3908 panel. This document describes signal transmission using one Ethernetcable as an example.Figure 6-25 shows the cable connection when the pRRU3901 is configured with two RFDaughter Boards.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.77
Figure 6-25 pRRU3901 cable connection (2)(1) Ethernet cable (2) RF jumperNOTElThe Extender can be used to lengthen the distance between the RHUB3908 and the pRRU3901connected using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts,one between the RHUB3908 and the Extender and the other between the Extender and the pRRU3901.lWhen two Ethernet cables are used to transmit CPRI signals, connect one end of the cables to theCPRI_E0 and CPRI_E1 ports on the pRRU3901 panel and the other end to any two ports of CPRI_E0to CPRI_E7 on the RHUB3908 panel. This document describes signal transmission using one Ethernetcable as an example.Figure 6-26 shows the cable connection when the pRRU3901 is configured with two RFDaughter Boards and one Wi-Fi daughter board.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.78
Figure 6-26 pRRU3901 cable connection (3)(1) Ethernet cable (2) RF jumperNOTElThe Extender can be used to lengthen the distance between the RHUB3908 and the pRRU3901connected using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts,one between the RHUB3908 and the Extender and the other between the Extender and the pRRU3901.lWhen two Ethernet cables are used to transmit CPRI signals, connect one end of the cables to theCPRI_E0 and CPRI_E1 ports on the pRRU3901 panel and the other end to any two ports of CPRI_E0to CPRI_E7 on the RHUB3908 panel. This document describes signal transmission using one Ethernetcable as an example.6.5.4 Cable Connections (LTE TDD)This section describes the cable connections for a single pRRU3901 and multiple pRRU3901sin LTE TDD mode.Before installing the pRRU3901 cables, you must be aware of the following information:lThe pRRU3901 can obtain power supply through the power over Ethernet (PoE).lFor external antennas corresponding to RF daughter board 1, the TX port and RX port areANT0 and ANT1, respectively. For external antennas corresponding to RF daughter board2, the TX port and RX port are ANT2 and ANT3, respectively. For external antennascorresponding to RF daughter board 3, the TX port and RX port are ANT4 and ANT5,respectively.lThe external antenna system is optional, and the pRRU3901 jumpers are not delivered. Bydefault, the pRRU3901s are configured with built-in antennas. If the external antennasystem is connected, the antenna system automatically switches to the external one. Oneend of the pRRU3901 RF jumper is the SMA male connector, which is connected to theexternal antenna TX/RX RF port on the pRRU3901. The other end of the pRRU3901 RFjumper is the type N male connector, which is connected to the antenna system. For thestandard of the pRRU3901 RF jumper, please see (Optional) pRRU RF Jumper of theLampSite Hardware Description.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.79
Figure 6-27 shows the cable connection when the pRRU3901 is configured with only one RFDaughter Board.Figure 6-27 pRRU3901 cable connection (1)(1) Ethernet cable (2) RF jumperNOTEThe Extender can be used to lengthen the distance between the RHUB and the pRRU connected using theEthernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one between the RHUBand the Extender and the other between the Extender and the pRRU.6.5.5 pRRU3901 cable installation processThis section describes the process of installing pRRU3901 cables.Figure 6-28 shows the process of installing pRRU3901 cables.Figure 6-28 pRRU3901 cable installation process6.5.6 Installing an Ethernet CableThis section describes how to install an Ethernet cable.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.80
PrerequisiteslEthernet cables are not delivered, and they must be prepared onsite. You need to use anetwork cable tester to test the Ethernet cable connection.lThe Ethernet cable must be of Category 5e (enhanced) or higher. In addition, its cross-sectional area must be 24 AWG or larger and frame spread rating must be CM or higher.With the internal PoE module providing power, the maximum length of an Ethernet cableis 100 m. With the Extender, the distance of the pRRU3901 and RHUB3908 can beextended by the Extender up to a total distance of 200 m.ContextThe Ethernet cable has the following functions:lProvides power supply for the pRRU3901 when the cable connects the CPRI_E0 port onthe pRRU3901 to the RHUB.lTransmits CPRI signals between an RHUB3908 and a pRRU3901.lProvides Wi-Fi services for the pRRU3901 when the cable connects the GE port on thepRRU3901 with three transmission ports to the AC.Using the CPRI_E1 port on the pRRU3901 has the same Ethernet cable connection to theRHUB3908 as using the CPRI_E0 port. The following section describes the connection usingthe CPRI_E0 port.ProcedureStep 1 Make the Ethernet cables.1. Assemble an RJ45 connector and an Ethernet cable by following instructions in Assemblingthe Unshielded RJ45 Connector and the Ethernet Cable of Installation Reference.NOTEFollow pin assignment instructions described in section Ethernet Cable in LampSite HardwareDescription to assemble the unshielded RJ45 connector and the Ethernet cable. Otherwise, thetransmission signal quality deteriorates and CPRI links may be disconnected.2. Check whether the made RJ45 connector is qualified by following instructions in Checkingthe Appearance of Metal Contact Strips.3. To complete the assembly of the other end, repeat Step 1.1 and Step 1.2.4. Check whether the touch points on the connectors at both ends are normally conducted andwell contacted and whether the connections are correct by following instructions in Testingthe Connection of Assembled Cables of Installation Reference.Step 2 Install an Ethernet cable between an RHUB3908 and a pRRU3901.1. Remove the dustproof cap of the CPRI_E0 port on the pRRU3901.2. Connect the RJ45 connector at one end of the Ethernet cable to the CPRI_E0 port on thepRRU3901 panel.3. Optional: Connect the RJ45 connector at the other end of the Ethernet cable to the outputport of the Extender. Then, connect the RJ45 connector at one end of another Ethernet cableto the input port of the Extender.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.81
4. Connect the RJ45 connector at the other end of the Ethernet cable to any port ranging fromCPRI_E0 to CPRI_E7 on the RHUB3908 panel based on the engineering design, as shownin Figure 6-29.Step 3 Optional: Install the Ethernet cable between the pRRU3901 and the AC. This operation isrequired when the pRRU3901 with three transmission ports is configured with a Wi-Fi daughterboard.1. Remove the dustproof cap of the GE port on the pRRU3901.2. Connect the RJ45 connector at one end of the Ethernet cable to the GE port on thepRRU3901 panel.3. Connect the RJ45 connector at the other end of the Ethernet cable to the transmission portof the AC based on the engineering design, as shown in Figure 6-29.Figure 6-29 Installing an Ethernet cable(1) Ethernet cable (2) GE port on the pRRU3901 (3) CPRI_E0 port on the pRRU3901NOTEThe pRRU3901 can have two transmission ports plus one PWR port or three transmission ports (plus onePWR port or no PWR port), requiring the same installation operations. This section uses the pRRU3901with three transmission ports no PWR port as an example.----EndFollow-up Procedure1. Route the cable, and then use a cable tie to bind the cable. For details, see 6.5.1Requirements for Cable Layout.2. Label the installed cable. For details, see section 8.3 Attaching an L-Shaped Label.6.5.7 Installing pRRU3901 Jumpers (Optional)pRRU3901 jumpers transmit radio frequency signals. One end of the jumper is the SMA straightmale connector, and the other end is the type N connector.ContextlIf the RF jumper is provided by the customer, the jumper must not be lower than the RG316specifications. In addition, the jumpers can be used after they are checked by Huaweiengineers.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.82
lpRRU3901s can be connected to external whip antennas or external remote antennas(through pRRU3901 RF jumpers). Whip antennas are delivered optionally. RF jumpers arenot delivered.ProcedureStep 1 Expose the SMA female connector by removing the pRRU3901 antenna housing, as shown inFigure 6-30.Figure 6-30 Removing the pRRU3901 antenna housingStep 2 Use a torque wrench with a torque of 0.6 N•m to connect the SMA straight male connector ona jumper to the ANT port on the pRRU3901 panel.NOTICETighten it with hands, and then use a torque wrench to tighten it with a rotational speed of lessthan or equal to 2.4 rpm to tighten it.Step 3 Connect the type N female connector of the jumper to the type N male connector of the RF feederconnected to the built-in antenna.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.83
NOTICETighten the feeder close to the type N connector to ensure that the jumper is not tightened. Inthis way, the connectors on both ends of a jumper are not affected by the external force.Figure 6-31 Installing jumpers between the pRRU3901 and external antennas----EndFollow-up Procedure1. Route the cable, and then use a cable tie to bind the cable. For details, see 6.5.1Requirements for Cable Layout.2. Label the installed cable. For details, see section 8.3 Attaching an L-Shaped Label.6.6 Checking the pRRU3901 Hardware InstallationpRRU3901 hardware installation checking includes hardware and cable installation checking.Table 6-8 lists the hardware installation checking items.Table 6-8 Hardware installation checking listNo. Item1Ensure that the pRRU3901 is not grouned.2 The position for each device conforms to the engineering design and meets thespace requirement.3 Ensure that the pRRU3901 is properly installed.4 The surface of the pRRU3901 is neat and clean. The external paint is intact. Thelabels, tags, and nameplates are correct, legible, and complete. LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.84
Table 6-9 lists the check items of the signal cable connection.Table 6-9 Checklist for the signal cable connectionNo. Item1The connectors of the signal cables must securely connected.2 The connectors of the signal cables are intact.3 The signal cables are intact.4 The cable ties are evenly spaced. The signal cables are bound neatly with cableties to proper tightness, and arranged at even intervals in the same direction.5 The extra length of the cable ties is cut and removed. The cut surfaces of the indoorcables are smooth and have no sharp edges.6 The cable layout facilitates maintenance and expansion.7 Correct and clear labels are attached to both ends of the signal cables. Table 6-10 lists the checking items for other cable connections.Table 6-10 Checklist for other cable connectionsNo. Item1The connectors of the other cables must securely connected.2 Labels on the cables are legible and bound based on the engineering requirements.The cables must be bound tightly and neatly. The sheaths of the cables must notbe damaged.3 Positions for routing the cables must meet requirements of the engineering design. 6.7 Powering on the pRRU3901This section describes the power-on check on the pRRU3901 after the pRRU3901 hardware isinstalled and checked.ProcedureStep 1 Power on the pRRU3901.The pRRU3901 can be powered in PoE mode. The RHUB3908 adopts the PoE power supplyto provide power for the pRRU3901 over the CPRI_E0 port.Step 2 Power on the pRRU3901. Wait 3 to 5 minutes, check the status of the RUN indicator on thepRRU3901.LampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.85
If the RUN Indicator... Because... Then...Steady on There is power input, but theboard is faulty.Power off the power supply,rectify the fault, and power onthe pRRU3901.Steady off There is no power input, or analarm is reported on the board.Power off the power supplyand check the power input. Ifno fault is found after thepRRU3901 is powered off,clear the fault on the board, andpower on the pRRU3901.On for 1s and off for 1s The device works properly. End this operation.On for 0.125s and off for0.125sThe software of the board isloading.Wait five minutes for thesoftware to be successfullyloaded. If the software isloading five minutes later, shutoff the power supply. Checkwhether the data configurationfile is correct. After the fault isrectify, power on thepRRU3901 again.----EndLampSiteInstallation Guide 6 Installing a pRRU3901Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.86
7 Installing the Extender (Optional)This section describes the Extender installation process.ContextWhen an RHUB3908 and a pRRU need extended install, use extender. With the Extender, thedistance of the pRRU and RHUB3908 can be extended by the Extender up to a total distance of200 m.The Extender can be installed on a wall or ceiling in the same mode. This section describes wall-mounted installation as an example.Only space above and under the Extender is required to be reserved when installing the Extender.The recommended space for installing the Extender is described as follows:lAt least 150 mm above the Extender is reserved for cabling.lAt least 150 mm under the Extender is reserved for cabling.ProcedureStep 1 Use a marker to mark the two anchor points according to inter-hole spacing, as shown in Figure7-1.LampSiteInstallation Guide 7 Installing the Extender (Optional)Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.87
Figure 7-1 Marking anchor pointsStep 2 Drill holes at the anchor points, and install expansion bolt assemblies, as shown in Figure 7-2.The diameter of the hole is 6 mm, and the depth is 25 mm to 30 mm.Figure 7-2 Drilling holes and installing expansion boltsStep 3 Place the Extender in the corresponding position and use an M4 Phillips screwdriver to tightenthe screws to 1.4 N•m, as shown in Figure 7-3.LampSiteInstallation Guide 7 Installing the Extender (Optional)Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.88
Figure 7-3 Installing Extender----EndLampSiteInstallation Guide 7 Installing the Extender (Optional)Issue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.89
8 AppendixAbout This ChapterThis chapter describes reference information during installation.8.1 MAC Collection TemplateThis section describes the MAC collection template for a pRRU3901 with three transmissionports.8.2 LampSite Engineering LabelThis section describes the content and presents the exterior of LampSite engineering labels.8.3 Attaching an L-Shaped LabelThis section describes the procedure and precautions to be taken for attaching an L-shaped label.LampSiteInstallation Guide 8 AppendixIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.90
8.1 MAC Collection TemplateThis section describes the MAC collection template for a pRRU3901 with three transmissionports.The MAC collection template is used to record the installation position, MAC address of thesite at the initial installation stage to facilitate subsequent commissioning and maintenance.Table 8-1 shows the MAC collection template.Table 8-1 MAC collection templateNo. SiteNumberSite Name WIFI MAC Location InformationSample01 pRRU3901 xx floor, xx building, xxmansion                                                                                 Note: The MAC collection template is essential to the engineering stage and subsequentmaintenance, especially when multiple devices are installed at a short distance. This isbecause the template defines the radio network to access. Maintain this template withcaution. 8.2 LampSite Engineering LabelThis section describes the content and presents the exterior of LampSite engineering labels.Label ContentThe LampSite engineering labels include the RHUB3908 power label, RHUB3908 ground label,RHUB3908 alarm or monitoring label, RHUB3908 optical transmission label, and RHUB3908network transmission label, the pRRU3901 power label, pRRU3901 network transmission label,pRRU3901 antenna label. The engineering labels are used for LampSite units RHUB3908 andpRRU3901 for indoor scenarios.LampSiteInstallation Guide 8 AppendixIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.91
By default, blank labels are delivered for LampSite and must be filled in onsite. Table 8-2describes the content of engineering labels.Table 8-2 LampSite Engineering Label ContentNE Label Content Description Correspondingport on the basestationRHUB3908PowerlabelRHUB3908xPWRLabel for the RHUB3908xpower cable.x specifies the number ofRHUB3908s and cannotexceed the maximumRHUB3908 numbersupported by thenetworking.PWRGroundlabelRHUB3908xPGNDLabel for the RHUB3908xground cable.x specifies the number ofRHUB3908s and cannotexceed the maximumRHUB3908 numbersupported by thenetworking.Alarm ormonitoring labelRHUB3908xEXT_ALMLabel for the RHUB3908xalarm cable.x specifies the number ofRHUB3908s and cannotexceed the maximumRHUB3908 numbersupported by thenetworking.EXT-ALMLampSiteInstallation Guide 8 AppendixIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.92
NE Label Content Description Correspondingport on the basestationOpticaltransmission labelRHUB3908xBBU/RHUB3908a/RHUB3908bLabel for the RHUB3908xCPRI cable.lx specifies the number ofRHUB3908s and cannotexceed the maximumRHUB3908 numbersupported by thenetworking.la can be set to 0 or 1. 0and 1 respectivelycorrespond to CPRI0port and CPRI1 port ofthe upper-levelRHUB3908.lb can be set to 0 or 1. 0and 1 respectivelycorrespond to CPRI0port and CPRI1 port ofthe lower-levelRHUB3908.CPRI0 or CPRI1Networktransmission labelRHUB3908xCPRI_EaLabel for the RHUB3908xEthernet cable.lx specifies the number ofRHUB3908s and cannotexceed the maximumRHUB3908 numbersupported by thenetworking.la can be set to 0 or 1. 0and 1 respectivelycorrespond to CPRI_E0port and CPRI_E1 portof the pRRU3901.CPRI_E0 toCPRI_E7pRRU3901PowerlabelpRRU3901yPWRLabel for the pRRU3901ypower cable.y specifies the number ofpRRU3901s and cannotexceed the maximumpRRU3901 numbersupported by thenetworking.PWR or CPRI_E0LampSiteInstallation Guide 8 AppendixIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.93
NE Label Content Description Correspondingport on the basestationNetworktransmission labelpRRU3901yCPRI_EaLabel for the pRRU3901yEthernet cable.ly specifies the number ofpRRU3901s and cannotexceed the maximumpRRU3901 numbersupported by thenetworking.la can be set to 0 to 7,which respectivelycorrespond to CPRI_E0port to CPRI_E7 port ofthe RHUB3908.CPRI_E0 orCPRI_E1AntennalabelpRRU3901yANTaLabel for the pRRU3901yRF Jumper.ly specifies the number ofpRRU3901s and cannotexceed the maximumpRRU3901 numbersupported by thenetworking.la can be set to 0 to 5,which respectivelycorrespond to ANT0port and ANT5 port ofthe pRRU3901.ANT0 to ANT5 NOTElIn the label, RHUB3908 and pRRU3901 identify the specific LampSite NEs.lIf only one RHUB3908 is deployed, mark it as RHUB39080 on the label. If multiple RHUB3908s aredeployed, mark them in ascending sequence, beginning with RHUB39080.lIf only one pRRU3901 is deployed, mark it as pRRU39010 on the label. If multiple pRRU3901s aredeployed, mark them in ascending sequence, beginning with pRRU39010.lFor details about the maximum number of RHUB3908s and pRRU3901s in the LampSite solution, seeTypical Configurations in LampSite Technical Description.Label StructureUsing the RHUB3908 power label as an example, Figure 8-1 shows the structure of a LampSiteengineering label.LampSiteInstallation Guide 8 AppendixIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.94
Figure 8-1 Label structure8.3 Attaching an L-Shaped LabelThis section describes the procedure and precautions to be taken for attaching an L-shaped label.ContextlThis section applies to Huawei sign plate labels. If other engineering labels in accordancewith local standards are used on site, follow the local standards for attaching sign platelabels.lIn the LampSite solution, blank L-Shaped engineering labels are delivered by default.lThe L-shaped label is usually used for the signal cable, E1/T1 cable, optical cable, andpower cable. The description in this section takes the Ethernet cable in a base station as anexample.ProcedureStep 1 Obtain the engineering label to be attached from the whole set of the L-shaped engineering labels,as shown in Figure 8-2.Figure 8-2 Engineering label to be attached Step 2 Attach the long end of the engineering label to the cable in the position 20 mm away from theconnector, and then turn over the long end along the adhesive face. Ensure that the edges of theturned-over engineering label are in a line, as shown in Figure 8-3.NOTEBy default, the label is attached in the position 20 mm away from the connector. If required, you can changethe position to make installation faster and more efficient. Consistency and neatness, however, must bemaintained.Step 3 Adhere the long end to the labeling area. Ensure that the spacing between the cable and thelabeling area is 2 mm to 3 mm.LampSiteInstallation Guide 8 AppendixIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.95
Figure 8-3 Adhering the long end to the labeling area Step 4 Turn over the labeling area along the adhesive face from the bottom, and then finish attachingthe engineering label, as shown in Figure 8-4 and Figure 8-5. Ensure that the edges of the turned-over labeling area are in a line.Figure 8-4 Turning over the labeling area along the adhesive face Figure 8-5 Attached engineering label Step 5 Fill in the attached blank label by referring to 8.2 LampSite Engineering Label.----EndLampSiteInstallation Guide 8 AppendixIssue 08 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.96
               pRRU3901, pRRU3901 AWS+PCS+WIFI   Issue: 02              Date: 2014.12.11                                  HUAWEI TECHNOLOGIES CO., LTD.
 Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. i    Copyright © Huawei Technologies Co., Ltd. 2010. All rights reserved. No part of this  document  may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.  Trademarks and Permissions   and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All  other  trademarks  and  trade  names  mentioned  in  this  document  are  the  property  of their  respective holders.  Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer.  All or part  of the products, services  and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS" without warranties, guarantees or representations of any kind, either express or implied. The information in this document is subject to change without notice. Every effort has been made in the preparation  of  this  document  to  ensure  accuracy  of  the  contents,  but  all  statements,  information,  and recommendations in this document do not constitute the warranty of any kind, express or implied.     Huawei Technologies Co., Ltd. Address: Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China Website: http://www.huawei.com Email: support@huawei.com
  1 Safety  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 1-1  1 Safety About This Chapter 1.1    Health and Safety 1.2    Equipment Safety 1.3 Electromagnetic Field exposure 1.1 Health and Safety 1.1.1    Overview 1.1.2    Electrical Safety 1.1.3    Inflammable Environment cbb000002_1_41.1.4  Working at Heights 1.1.5  Mechanical Safety 1.1.6  Bundling Signal Cables 1.1.1 Overview Introduction This section describes the safety precautions you must take before installing or maintaining Huawei equipment.  To ensure safety of humans and the equipment, pay attention to the safety symbols on the equipment and all the safety instructions in this document.  The "NOTE", "CAUTION", and "WARNING" marks in other documents do not represent all the safety instructions. They are only supplements to the safety instructions.  Installation and maintenance personnel must understand basic safety precautions to avoid hazards.  When operating Huawei equipment, in addition to following the general precautions in this document, follow the specific safety instructions given by Huawei.
1 Safety    1-2 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)   Only trained and qualified personnel are allowed to install, operate, and maintain Huawei equipment. Local Safety Regulations When operating Huawei equipment, you must follow the local laws and regulations. The safety instructions in this document are only supplements to the local laws and regulations. General Requirements To minimize risk of personal injury and damage to equipment, read and follow all the precautions in this document before performing any installation or maintenance. Ensure that the instructions provided in this document are followed completely. This section also provides guidelines for selecting the measuring and testing devices. Installation  The device (or system) must be installed in an access-controlled location.    The device can be mounted only on concrete or non-combustible surfaces.  The device must be fixed securely on the floor or to other immovable objects such as walls and mounting racks before operation.  When installing the unit, always make the ground connection first and disconnect it at the end.  Tighten the thumbscrews by using a tool after initial installation and subsequent access to the panel. Ground  Do not damage the ground conductor or operate the device in the absence of a properly installed ground conductor. Conduct the electrical inspection carefully.  The device (or system) must be connected permanently to the protection ground before an operation. The cross-sectional area of the protective ground conductor must be at least 16 mm2.   Power Supply  For DC-supplied model: The device applies to DC power source that complies with the Safety Extra-Low Voltage (SELV) requirements in IEC 60950-1 based safety standards.  Prepared conductors are connected to the terminal block, and only the appropriate AWG/Type of wire is secured with the lug terminals.  Short-circuit (overcurrent) protection of the device varies according to the building's installation. Ensure that a circuit breaker no larger than 125 VDC, 10 A (fuse) for DC supplied model is used on the phase conductors (all current-carrying conductors).  For this device, a readily accessible disconnect device must be incorporated in the building installation wiring. Human Safety  Do not operate the device or cables during lightning strikes.    To avoid electric shock, do not connect safety extra-low voltage (SELV) circuits to telecommunication network voltage (TNV) circuits.
  1 Safety  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 1-3   Move or lift the chassis by holding its lower edge. Do not hold the handles on certain modules such as power supply, fans, and boards because they cannot support the weight of the device.  Do not look into the optical port without eye protection.  Do not wear jewelry or watches when you operate the device. Operator  Only qualified professional personnel are allowed to install, configure, operate, and disassemble the device.    Only the personnel authenticated or authorized by Huawei are allowed to replace or change the device of the parts of the device (including the software).    Any fault or error that might cause safety problems must be reported immediately to a supervisor.  Only qualified personnel are allowed to remove or disable the safety facilities and to troubleshoot and maintain the device. 1.1.2 Electrical Safety High Voltage   The high voltage power supply provides power for the device operation. Direct or indirect contact (through damp objects) with high voltage and AC mains supply may result in fatal danger.  During the installation of the AC power supply facility, follow the local safety regulations. The personnel who install the AC facility must be qualified to perform high voltage and AC operations.  Do not wear conductive articles, such as watches, hand chains, bracelets, and rings during the operation.  When water is found in the rack or the rack is damp, switch off the power supply immediately.  When the operation is performed in a damp environment, make sure that the device is dry.   Non-standard and improper high voltage operations may result in fire and electric shock. Therefore, you must abide by the local rules and regulations when bridging and wiring AC cables. Only qualified personnel are allowed to perform high voltage and AC operations.
1 Safety    1-4 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)   Before powering on a device, ground the device. Otherwise, personal injury or device damage may be caused by high leakage current. Thunderstorm   Do not perform any operation, including high voltage and AC operations, on a steel tower or mast during a thunderstorm. Tools   Dedicated tools must be used during high voltage and AC operations. Avoid using ordinary tools. High Electrical Leakage   Ground the device before powering it on. Otherwise, personal injury or device damage may be caused by high leakage current. If a "high electrical leakage" tag is present on the power terminal of the device, you must ground the device before powering it on. Power Cable   Do not install or remove power cables when the device is on. Transient contact between the core of the power cable and the conductor may generate electric arcs or sparks, which may cause fire or hurt human eyes.  Before installing or removing the power cable, turn off the power switch.  Before connecting a power cable, check that the label on the power cable is correct.
  1 Safety  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 1-5     If the device is connected with the DC power supply, use 16 mm² minimum power supply cord.    Use type H03VV-F or light PVC-sheathed flexible cord according to IEC 60227. 1.1.3 Inflammable Environment Operating the electrical device in an inflammable environment can be fatal.   Do not place the device in an environment that has inflammable and explosive air or gas. Do not perform any operation in this environment. . 1.1.4 Working at Heights   Avoid object falling when you work at heights.   When working at heights, fulfill the following requirements:  Only trained personnel can work at heights.    Prevent the devices and tools that you carry from falling down.  Take safety and protection measures, for example, wear a helm and safety belt.  Wear warm clothes when working at heights in a cold region.    Before working at heights, check that all the lifting facilities are in good condition. Hoisting Heavy Objects   Do not walk below the cantilever or hoisted objects when heavy objects are being hoisted.    Only trained and qualified personnel can perform hoisting operations.    Before hoisting heavy objects, check that the hoisting tools are complete and in good condition.
1 Safety    1-6 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)   Before hoisting heavy objects, ensure that the hoisting tools are fixed to a secure object or wall with good weight capacity.    Issue orders with short and explicit words to avoid misoperations.  Ensure that the angle formed by two cables is not larger than 90 degrees. See Figure 1-1. Figure 1-1 Hoisting heavy objects   Using Ladders Checking a Ladder  Before using a ladder, check whether the ladder is damaged. Only the ladder in good condition can be used.    Before using a ladder, you should know the maximum weight capacity of the ladder. Avoid overweighing the ladder.   Placing a Ladder The recommended gradient of ladders is 75 degrees. You can measure the gradient of the ladder with an angle square or your arms. When using a ladder, ensure that the wider feet of the ladder are downward, or take protection measures for the ladder feet to prevent the ladder from sliding. Ensure that the ladder is placed securely.
  1 Safety  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 1-7  Climbing Up a Ladder When climbing up a ladder, note the following:  Ensure that the center of gravity of your body does not deviate from the edges of the two long sides.    To minimize the risk of falling, hold your balance on the ladder before any operation.  Do not climb higher than the fourth rung of the ladder (counted from up to down).    If you want to climb up a roof, ensure that the ladder top is at least one meter higher than the roof. 1.1.5 Mechanical Safety Drilling Holes   Do not drill the cabinet at will. Drilling holes without complying with the requirements affects the electromagnetic shielding performance of the cabinet and damages the cables inside the cabinet. In addition, if the scraps caused by drilling enter the cabinet, the printed circuit boards (PCBs) may be short circuited.    Before you drill a hole in the cabinet, wear insulated gloves and remove the internal cables from the cabinet.  Wear an eye protector when drilling holes. This is to prevent your eyes from being injured by the splashing metal scraps.    Ensure that the scraps caused by drilling do not enter the cabinet.  Drilling holes without complying with the requirements affects the electromagnetic shielding performance of the cabinet.  After drilling, clean the metal scraps immediately. Sharp Objects   Before you hold or carry a device, wear protective gloves to avoid getting injured by sharp edges of the device.  Lifting Heavy Objects
1 Safety    1-8 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)   When heavy objects are being lifted, do not stand or walk under the cantilever or the lifted object. 1.1.6Bundling Signal Cables    Do not bundle signal cables with high current cables or high voltage cables.  Maintain a minimum space of 150 mm between adjacent ties. 1.2 Equipment Safety 1.2.1    Electricity Safety 1.2.2    Electrostatic Discharge 1.2.3    Installing and Removing a Board 1.2.4    Laying Cables 1.2.1 Electricity Safety Thunderstorm   During thunderstorms, the electromagnetic field generated in the thunderstorm area may damage the electronic parts. To prevent damage to the device during lightning, ground the device properly. High Electrical Leakage   If the "high electrical leakage" tag is present on the power terminal of the device, you must ground the device before powering it on.
  1 Safety  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 1-9  Fuse   If a fuse is to be replaced, the new fuse must be of the same type and specifications. Table 1-1 lists the fuses that affect the safety of the device (or system). Use fuses according to this list. Table 1-1 Fuse description Position Manufacturer Type Rating Fuse (F7000)on pRRU3901 19040112 LITTELFUSE INC 0451010.MRL 125VAC/DC,10 A CONQUER ELECTRONICS CO LTD SEF010 125VAC/DC,10 A BEL FUSE INC SSQ10 125VAC/86 VDC, 10 A Fuse (F7001)on pRRU3901 19040110 LITTELFUSE INC 0452004.MRL 125VAC/DC, 4 A CONQUER ELECTRONICS CO LTD SET004 125VAC, 32 VDC, 4 A BEL FUSE INC SST4 125VAC, 4 A  1.2.2Electrostatic Discharge   The static electricity generated by human bodies may damage the electrostatic-sensitive components on boards, for example, the large-scale integrated (LSI) circuits. Human body movement, friction between human bodies and clothes, friction between shoes and floors, or handling of plastic articles causes static electromagnetic fields on human bodies. These static electromagnetic fields cannot be eliminated until the static is discharged.   To prevent electrostatic-sensitive components from being damaged by the static on human bodies, you must wear a well-grounded ESD wrist strap when touching the device or handling boards or application-specific integrated circuits (ASICs). Figure 1-2 shows how to wear an ESD wrist strap.
1 Safety    1-10 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)  Figure 1-2 Wearing an ESD wrist strap   1.2.3 Installing and Removing a Board   When installing a board, use proper force to prevent the pins on the backplane from being leaned. When installing or removing a board, note the following:  Insert the board along the guide rails.  Prevent the surface of a board from contacting the surface of another board. This is to prevent the boards from being short-circuited or scratched.  To prevent electrostatic-sensitive devices from being damaged by the ESD, do not touch the circuits, components, connectors, or connection slots on boards. 1.2.4 Laying Cables When the temperature is very low, violent strike or vibration may damage the cable sheathing. To ensure safety, comply with the following requirements:  Cables can be laid or installed only when the temperature is higher than 0℃.  Before laying cables which have been stored in a temperature lower than 0℃, move the cables to an environment of the ambient temperature and store them at the ambient temperature for at least 24 hours.  Handle cables with caution, especially at a low temperature. Do not drop the cables directly from the vehicle.
  1 Safety  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 1-11  1.3 Electromagnetic Field Exposure Introduction The Base Transceiver Station (BTS) emits Radio Frequency (RF) radiation. Follow the local safety regulations when installing and operating the BTS to avoid radiation hazard. Location of Base Station Antennas Base station antennas, the source of the radiation, are usually mounted:  On freestanding towers, with a height up to 30 m  On a tower on the top of buildings  To the side of buildings, on rare occasions   Generally, the antenna cannot be located in a position lower than 10 m. The energy usually forms a horizontal main beam and is slightly tilted downwards. The remaining energy forms into weaker beams on both sides of the main beam. The main beam, however, does not reach the ground if the antenna is around 50–200 m away from the ground. The highest level of emission would be expected in close vicinity of the antenna and in line of sight to the antenna. Exclusion Zones The requirements for exclusion zones are as follows:  The antenna should be properly located to prevent the public from accessing the area where the RF radiation exceeds the previously mentioned limits.  If areas with excessive RF radiation are accessible to the operation and maintenance (O&M) personnel, ensure that they know the source of radiation and can power off or shut down the transmitters before entering high radiation areas. In addition, such areas must be confined within a distance of 10 m from the antennas.  Each exclusion zone should be defined by a physical barrier and by a recognizable sign warning the public or O&M personnel. Guidelines on Choosing Antenna Sites The guidelines on choosing the antenna sites are as follows:  For roof-mounted antennas, raise the antennas above the height of the personnel who may have to work on the rooftop.  For roof-mounted antennas, keep the transmitter antennas away from the areas accessible to the public, such as roof access points, telephone service points, and HVAC devices.  For roof-mounted directional antennas, place the antennas near the periphery, and do not make the antennas face the building.  Consider the trade-off between large aperture antennas (lower maximum RF) and small aperture antennas (lower visual impact).  Keep higher-power antennas away from accessible areas.  Keep the antennas in a site that is far away from urban areas, though this may contradict the coverage area requirements.
1 Safety    1-12 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)   Exercise extra caution when designing co-location sites, that is, antennas owned by different companies are located in the same site or are co-sited. This applies particularly to sites that include high-power broadcast (FM/TV) antennas. Local zone often favors co-location, but co-location may cause safety problems.  Take special precautions for antenna sites near hospital and schools. Location of BTS The BTS is shielded from RF radiation hazards. The device has been tested to comply with the radioactive spurious emission requirements of international standards or local regulations. Therefore, the BTS under normal operating conditions does not cause danger to the public and O&M engineers. However, the limits for RF radiation might be exceeded due to faulty antenna cables or for other causes.  BTS sites shall not be accessible to the public. Only authorized and trained personnel can access BTS sites or equipment rooms.  A sign of excessive RF radiation must be present on the doors of the sites or equipment rooms to warn the personnel inside the site or equipment room of excessive RF radiation.  BTS sites must be regularly monitored and inspected after installation. Prediction of the Exposure to Electromagnetic Fields This section provides a theoretical approach to calculate possible exposure to electromagnetic radiation around a BTS antenna. Precise statements are possible either with measurements or complex calculations considering the complexity of the environment, such as soil conditions, nearby buildings and other obstacles. The complexity may cause reflection, deflection, and scattering of electromagnetic fields. The maximum output power (given in EIRP) of a BTS is usually limited by license conditions of the network operator. A rough estimation of the expected exposure in power flux density on a given point can be made with the following equation: S = (P(W) x Gnumeric)/(4 x r²(m) x π) Where, P = Maximum output power at antenna port of the BTS in W Gnumeric = Numeric gain (see below) r = Distance between the antenna and the point of exposure in meters For the calculation of the Gnumeric, Gnumeric = 10GdB/10 GdB = Gantenna(dB) – Bcable(dB) – Bvertical-attenutation(dB) – Bhorizontal-attenuation(dB) B = attenuation in dB
LampSiteSite Maintenance GuideIssue 05Date 2015-01-15HUAWEI TECHNOLOGIES CO., LTD.
  Copyright © Huawei Technologies Co., Ltd. 2015. All rights reserved.No part of this document may be reproduced or transmitted in any form or by any means without prior writtenconsent of Huawei Technologies Co., Ltd. Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.All other trademarks and trade names mentioned in this document are the property of their respective holders. NoticeThe purchased products, services and features are stipulated by the contract made between Huawei and thecustomer. All or part of the products, services and features described in this document may not be within thepurchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,and recommendations in this document are provided "AS IS" without warranties, guarantees or representationsof any kind, either express or implied.The information in this document is subject to change without notice. Every effort has been made in thepreparation of this document to ensure accuracy of the contents, but all statements, information, andrecommendations in this document do not constitute a warranty of any kind, express or implied.       Huawei Technologies Co., Ltd.Address: Huawei Industrial BaseBantian, LonggangShenzhen 518129People's Republic of ChinaWebsite: http://www.huawei.comEmail: support@huawei.comIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.i
About This DocumentOverviewThis document describes routine maintenance items for a RHUB3908, pRRU3901, such asequipment maintenance, and power-on and power-off operations. It also explains how to replacethe components and modules.NOTEFor details of the BBU site maintenance guide, see DBS3900 Site Maintenance Guide.Product VersionThe following table lists the product version related to this document.Product Name Solution Version Product VersionDBS3900 lSRAN9.0 and later versionslRAN16.0 and later versionsleRAN7.0 and later versionsleRAN TDD 7.0 and laterversionsV100R009C00 and later versions Intended AudienceThis document is intended for:lSystem engineerslSite maintenance engineersOrganization1 Changes in LampSite Site Maintenance GuideLampSiteSite Maintenance Guide About This DocumentIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.ii
This chapter provides information about the changes in different document versions ofLampSite Site Maintenance Guide.2 RHUB3908 Maintenance ItemsThis chapter describes the RHUB3908 maintenance items, involving the equipment room,equipment, power system, and grounding system.3 pRRU3901 Maintenance ItemsThis chapter describes the pRRU3901 maintenance items, involving equipment and powersystem.4 Powering On and Powering Off the RHUB3908After the RHUB3908 is powered on, check the indicator status. Power off the RHUB3908 innormal or emergency mode as required.5 Powering On and Powering Off the pRRU3901After the pRRU3901 is powered on, check the power supply voltage and indicator status. Poweroff the pRRU3901 based on the power supply mode.6 Replacing the RHUB3908The RHUB3908 is an indoor convergence unit. It converges multiple pRRUs to the BBU3900.Replacing the RHUB3908 interrupts services carried on the serving cell.7 Replacing an Optical ModuleAn optical module provides a port for opto-electronic conversion. This enables the transmissionbetween the RHUB3908 and BBU3900 through the optical fiber. Replacing the optical modulerequires removing the optical fibers. This interrupts all the services.8 Replacing the pRRU3901pRRU3901 is an indoor remote radio unit. It processes RF signals. Replacing the pRRU3901interrupts all the services carried on it.ConventionsSymbol ConventionsThe symbols that may be found in this document are defined as follows.Symbol DescriptionIndicates an imminently hazardous situation which, if notavoided, will result in death or serious injury.Indicates a potentially hazardous situation which, if notavoided, could result in death or serious injury.Indicates a potentially hazardous situation which, if notavoided, may result in minor or moderate injury.LampSiteSite Maintenance Guide About This DocumentIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.iii
Symbol DescriptionIndicates a potentially hazardous situation which, if notavoided, could result in equipment damage, data loss,performance deterioration, or unanticipated results.NOTICE is used to address practices not related to personalinjury.Calls attention to important information, best practices andtips.NOTE is used to address information not related to personalinjury, equipment damage, and environment deterioration. General ConventionsThe general conventions that may be found in this document are defined as follows.Convention DescriptionTimes New Roman Normal paragraphs are in Times New Roman.Boldface Names of files, directories, folders, and users are inboldface. For example, log in as user root.Italic Book titles are in italics.Courier New Examples of information displayed on the screen are inCourier New. Command ConventionsThe command conventions that may be found in this document are defined as follows.Convention DescriptionBoldface The keywords of a command line are in boldface.Italic Command arguments are in italics.[ ] Items (keywords or arguments) in brackets [ ] are optional.{ x | y | ... } Optional items are grouped in braces and separated byvertical bars. One item is selected.[ x | y | ... ] Optional items are grouped in brackets and separated byvertical bars. One item is selected or no item is selected.{ x | y | ... }*Optional items are grouped in braces and separated byvertical bars. A minimum of one item or a maximum of allitems can be selected.LampSiteSite Maintenance Guide About This DocumentIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.iv
Convention Description[ x | y | ... ]*Optional items are grouped in brackets and separated byvertical bars. Several items or no item can be selected. GUI ConventionsThe GUI conventions that may be found in this document are defined as follows.Convention DescriptionBoldface Buttons, menus, parameters, tabs, window, and dialog titlesare in boldface. For example, click OK.>Multi-level menus are in boldface and separated by the ">"signs. For example, choose File > Create > Folder. Keyboard OperationsThe keyboard operations that may be found in this document are defined as follows.Format DescriptionKey Press the key. For example, press Enter and press Tab.Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt+A means the three keys should be pressed concurrently.Key 1, Key 2 Press the keys in turn. For example, pressing Alt, A meansthe two keys should be pressed in turn. Mouse OperationsThe mouse operations that may be found in this document are defined as follows.Action DescriptionClick Select and release the primary mouse button without movingthe pointer.Double-click Press the primary mouse button twice continuously andquickly without moving the pointer.Drag Press and hold the primary mouse button and move thepointer to a certain position.LampSiteSite Maintenance Guide About This DocumentIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.v
ContentsAbout This Document.....................................................................................................................ii1 Changes in LampSite Site Maintenance Guide.......................................................................12 RHUB3908 Maintenance Items...................................................................................................53 pRRU3901 Maintenance Items....................................................................................................94 Powering On and Powering Off the RHUB3908...................................................................114.1 Powering On the RHUB3908.......................................................................................................................................124.2 Powering Off the RHUB3908......................................................................................................................................135 Powering On and Powering Off the pRRU3901....................................................................145.1 Powering On the pRRU3901........................................................................................................................................155.2 Powering Off the pRRU3901.......................................................................................................................................166 Replacing the RHUB3908...........................................................................................................177 Replacing an Optical Module...................................................................................................218 Replacing the pRRU3901............................................................................................................25LampSiteSite Maintenance Guide ContentsIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.vi
1 Changes in LampSite Site MaintenanceGuideThis chapter provides information about the changes in different document versions ofLampSite Site Maintenance Guide.05 (2015-01-15)This is the fifth commercial release.Compared with 04 (2014-07-30), this issue includes the following new topic:l8 Replacing the pRRU3901Compared with 04 (2014-07-30), this issue incorporates the following changes:Content Change DescriptionEntire document lChanged RHUB, and pRRU toRHUB3908, and pRRU3901,respectively.lAdded the pRRU3901 with threetransmission ports plus no PWR port (orthe pRRU3901a for use in NorthAmerica) .5 Powering On and Powering Off thepRRU3901Deleted the description that the pRRU3901supports AC/DC power supply. Compared with 04 (2014-07-30), no information is deleted.04 (2014-07-30)This is the fourth commercial release.Compared with 03 (2014-06-30), no information is added.Compared with 03 (2014-06-30), this issue incorporates the following change:LampSiteSite Maintenance Guide 1 Changes in LampSite Site Maintenance GuideIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.1
Content Change DescriptionReplacing an Optical Module Modified the steps of replacing an OpticalModule. Compared with 03 (2014-06-30), no information is deleted.03 (2014-06-30)This is the third commercial release.Compared with 02 (2014-05-30), no information is added.Compared with 02 (2014-05-30), this issue incorporates the following changes:Content Change DescriptionReplacing the RF Daughter Board Added descriptions about the block typesupported in the LampSite solution.Replacing the pDock Mother BoardReplacing the Wi-Fi Daughter Board Compared with 02 (2014-05-30), no information is deleted.02 (2014-05-30)This is the second commercial release.Compared with 01 (2014-04-26), no information is added.Compared with 01 (2014-04-26), this issue incorporates the following change:Content Change DescriptionEntire document Added the descriptions about the LTE FDD+LTE FDD mode. Compared with 01 (2014-04-26), no information is deleted.01 (2014-04-26)This is the first commercial release.Compared with Draft C (2014-03-26), no information is added.Compared with Draft C (2014-03-26), this issue incorporates the following changes:LampSiteSite Maintenance Guide 1 Changes in LampSite Site Maintenance GuideIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.2
Content Change DescriptionEntire document Changed the pRRU3901 name frompRRU3901 with two Ethernet ports topRRU3901 with two transmission ports, andpRRU3901 with three Ethernet ports topRRU3901 with three transmission ports.Replacing the pDock Mother Board Changed the pDock name from pDock withtwo Ethernet ports to pDock with twotransmission ports, and pDock with threeEthernet ports to pDock with threetransmission ports. Compared with Draft C (2014-03-26), this issue excludes the following topic:lReplacing a PSUDraft C (2014-03-26)This is a draft release.Compared with Draft B (2014-02-28), no information is added.Compared with Draft B (2014-02-28), this issue incorporates the following change:Content Change DescriptionReplacing the RHUB Deleted the operation of resetting theRHUB3908 after replacing. Compared with Draft B (2014-02-28), no information is deleted.Draft B (2014-02-28)This is a draft release.Compared with draft A (2013-11-30), this issue includes the following new topic:lReplacing the Wi-Fi Daughter BoardCompared with draft A (2013-11-30), this issue incorporates the following changes:Content Change DescriptionEntire document Added descriptions about pRRU3901s withthree transmission ports. Such pRRU3901ssupport integrated Wi-Fi services.LampSiteSite Maintenance Guide 1 Changes in LampSite Site Maintenance GuideIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.3
Content Change DescriptionAdded the descriptions about the UMTS, LTEFDD and UMTS+LTE FDD mode.LampSite Site Maintenance Guide Optimized descriptions about matchingproduct versions.Replacing the RF Daughter Board Added the procedures for removing andattaching labels.Replacing the Wi-Fi Daughter Board Compared with draft A (2013-11-30), this issue excludes the following topic:lReplacing the pRRU3901Draft A (2013-11-30)This is a draft release.LampSiteSite Maintenance Guide 1 Changes in LampSite Site Maintenance GuideIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.4
2 RHUB3908 Maintenance ItemsThis chapter describes the RHUB3908 maintenance items, involving the equipment room,equipment, power system, and grounding system.Equipment Room Maintenance ItemsTable 2-1 lists the equipment room maintenance items.Table 2-1 Equipment room maintenance itemsItem Check Frequency Operation ReferenceStandardEnvironment alarmsin the equipmentroomDaily Check whether anypower alarm, firealarm, or smokealarm is reported.No power alarm, firealarm, or smokealarm is reported.Temperature in theequipment roomEach timemaintenance isperformedRecord temperaturesin the equipmentroom measured by athermometer.-5°C to +50°CHumidity in theequipment roomEach timemaintenance isperformedRecord humidity inthe equipment roommeasured by ahygrometer.5%RH to 95%RHLighting system inthe equipment roomEvery other month Check whether theroutine lightingsystem andemergency lightingsystem are runningproperly.-Air conditioner Every other month Check whether theair conditioner isrunning properly.-LampSiteSite Maintenance Guide 2 RHUB3908 Maintenance ItemsIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.5
Item Check Frequency Operation ReferenceStandardDisaster protectiondevicesEvery one month Check whether thedisaster protection,equipmentprotection, andfirefighting devicesare normal.lThe equipmentroom is equippedwith portablefoam-typeextinguishers,and the pressureand expirationdate must bechecked.lThe equipmentroom has nomice, ants, flyinginsects, or otherrisks.Cleanness Every one month Check whether thecabinet, equipmenthousing, equipmentinterior, desktop,floor, door, andwindow are cleanand tidy.All these items areclean and tidy. Equipment Maintenance ItemsTable 2-2 lists the equipment maintenance items.Table 2-2 Equipment maintenance itemsItem Check Frequency Operation ReferenceStandardFan in the PSU Monthly or quarterly Check whether thefan is workingproperly.The fan worksproperly without anyabnormal smell orsound.Equipment surface Monthly or quarterly Check whether theequipment surface isintact.The equipmentsurface is intact andthe label of thecabinet is legible.Equipment cleanness Monthly or quarterly Check whether theequipment is clean.The equipmentsurface is clean.LampSiteSite Maintenance Guide 2 RHUB3908 Maintenance ItemsIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.6
Item Check Frequency Operation ReferenceStandardIndicators Monthly or quarterly Check whether theindicators on theequipment areworking properly.For details about theindicator status, seeRHUB3908 Portsand Indicators inLampSite HardwareDescription.Electrostaticdischarge (ESD)wrist strapQuarterly Check the ESD wriststrap in either of thefollowing ways:lUse an ESD wriststrap tester tocheck the ESDwrist strap.lUse a multimeterto test the groundresistance of theESD wrist strap.If you use an ESDwrist strap tester, theGOOD indicator ison. If you use amultimeter, theground resistance ofthe ESD wrist strapranges from 0.75ohms to 10 ohms. Maintenance Items for the Power System and Grounding SystemTable 2-3 lists the maintenance items for the power system and grounding system.Table 2-3 Maintenance items for the power system and grounding systemItem Check Frequency Operation ReferenceStandardPower cables Monthly or quarterly Check the powercable connections.The power cables aresecurely connectedand not deteriorating.The joints are notcorroded.Voltage Monthly or quarterly Use a multimeter tomeasure the voltageof the power supply.The voltage is in thepermissible range.PGND cables Monthly or quarterly Checks whether thePGND cables andground bar aresecurely connected.The joints are secureand not corroded.The PGND cablesand ground bar arenot deteriorated andare protected fromcorrosion.LampSiteSite Maintenance Guide 2 RHUB3908 Maintenance ItemsIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.7
Item Check Frequency Operation ReferenceStandardGround resistance Monthly or quarterly Use a groundresistance tester tomeasure the groundresistance and recordthe measurementresult.The groundresistance is equal toor less than 10 ohms.LampSiteSite Maintenance Guide 2 RHUB3908 Maintenance ItemsIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.8
3 pRRU3901 Maintenance ItemsThis chapter describes the pRRU3901 maintenance items, involving equipment and powersystem.Equipment Maintenance ItemsTable 3-1 lists the equipment maintenance items for the pRRU3901.Table 3-1 Equipment maintenance itemsItem Check Frequency Operation ReferenceStandardEquipment surface Monthly or quarterly Check whether theequipment surface isintact.The equipmentsurface is intact andthe label of thecabinet is legible.Equipment cleanness Monthly or quarterly Check whether theequipment is clean.The equipmentsurface is clean.Indicators Monthly or quarterly Check whether theindicators on theequipment areworking properly.For details about theindicator status, seepRRU3901 Ports andIndicators inLampSite HardwareDescription. Power System Maintenance ItemsTable 3-2 lists the power system maintenance items for the pRRU3901.LampSiteSite Maintenance Guide 3 pRRU3901 Maintenance ItemsIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.9
Table 3-2 Power system maintenance itemsItem Check Frequency Operation ReferenceStandardPower cables Monthly or quarterly Check the powercable connections.The power cables aresecurely connectedand not deteriorating.The joints are notcorroded.Voltage Monthly or quarterly Use a multimeter tomeasure the voltageof the power supply.The voltage is in thepermissible range.LampSiteSite Maintenance Guide 3 pRRU3901 Maintenance ItemsIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.10
4 Powering On and Powering Off theRHUB3908About This ChapterAfter the RHUB3908 is powered on, check the indicator status. Power off the RHUB3908 innormal or emergency mode as required.4.1 Powering On the RHUB3908The RHUB3908 is powered by AC input.4.2 Powering Off the RHUB3908An RHUB3908 can be powered off in two ways: normal power-off and emergency power-off.You need to perform a normal power-off in scenarios such as an equipment swap or foreseeableregional blackout, and you need to perform an emergency power-off in emergencies such as afire, smoke, or water damage in indoor scenarios.LampSiteSite Maintenance Guide 4 Powering On and Powering Off the RHUB3908Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.11
4.1 Powering On the RHUB3908The RHUB3908 is powered by AC input.PrerequisitesThe power cable of the RHUB3908 is not connected to power, that is, the power plug is removed.ContextNOTICEThe RHUB3908 must be powered on within 7 days after it is unpacked, and the period of itspower-off state cannot exceed 7 days during maintenance.ProcedureStep 1 Insert the power plug to power on the RHUB3908.Step 2 Wait 3 to 5 minutes. Then check the status of the RUN indicator.If the RUN Indicator Is... It Indicates that... Then...Steady on There is power input, but theboard is faulty.Disable the power supply,rectify the board fault, andthen power on theRHUB3908 again.Steady off There is no power input, or analarm about the board isreported.Disable the power supply andcheck the power input again.If the power input is normal,rectify the board fault, andthen power on theRHUB3908 again.1s on and 1s off The RHUB3908 is runningproperly.End the power-on check task.0.125s on and 0.125s off The board software is beingloaded.If the loading is not completeafter 5 minutes, disable thepower supply and checkwhether the data in theconfiguration file is correct.Rectify the fault and thenpower on the RHUB3908again. ----EndLampSiteSite Maintenance Guide 4 Powering On and Powering Off the RHUB3908Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.12
4.2 Powering Off the RHUB3908An RHUB3908 can be powered off in two ways: normal power-off and emergency power-off.You need to perform a normal power-off in scenarios such as an equipment swap or foreseeableregional blackout, and you need to perform an emergency power-off in emergencies such as afire, smoke, or water damage in indoor scenarios.ProcedurelNormal power-offNOTICEPowering off the RHUB3908 interrupts services, and therefore perform associatedoperations before a power-off.1. Remove the power plug to disconnect the RHUB3908 with the external power input.2. If the RHUB3908 is equipped with an external power device, turn off the switch ofthe external power device.lEmergency power-off1. Turn off the switch of the external power device.----EndLampSiteSite Maintenance Guide 4 Powering On and Powering Off the RHUB3908Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.13
5 Powering On and Powering Off thepRRU3901About This ChapterAfter the pRRU3901 is powered on, check the power supply voltage and indicator status. Poweroff the pRRU3901 based on the power supply mode.5.1 Powering On the pRRU3901After the pRRU3901 is powered on, check its running status by observing the indicator status.5.2 Powering Off the pRRU3901A pRRU3901 can be powered off in two ways: normal power-off and emergency power-off.You need to perform a normal power-off in scenarios such as an equipment swap or foreseeableregional blackout, and you need to perform an emergency power-off in emergencies such as afire, smoke, or water damage in indoor scenarios.LampSiteSite Maintenance Guide 5 Powering On and Powering Off the pRRU3901Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.14
5.1 Powering On the pRRU3901After the pRRU3901 is powered on, check its running status by observing the indicator status.PrerequisitesThe pRRU3901 and the cables are correctly installed.ContextNOTICEThe pRRU3901 must be powered on within 7 days after it is unpacked, and the period of itspower-off state cannot exceed 7 days during maintenance.ProcedureStep 1 Power on the pRRU3901.The pRRU3901 can be powered in PoE mode. The RHUB3908 adopts the PoE power supplyto provide power for the pRRU3901 over the CPRI_E0 port.Step 2 Wait 3 to 5 minutes. Then Check the status of the RUN indicator.If the RUN Indicator Is... It Indicates that... Then...Steady on There is power input, but theboard is faulty.Disable the power supply,rectify the board fault, andthen power on thepRRU3901 again.Steady off There is no power input. Disable the power supply andcheck the power input again.On for 1s and off for 1s The pRRU3901 is runningproperly.End the power-on check task.On for 0.125s and off for0.125sThe board software is beingloaded.If the loading is not completeafter 5 minutes, disable thepower supply. Checkwhether the data in theconfiguration file is correct.Rectify the fault and thenpower on the pRRU3901again. ----EndLampSiteSite Maintenance Guide 5 Powering On and Powering Off the pRRU3901Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.15
5.2 Powering Off the pRRU3901A pRRU3901 can be powered off in two ways: normal power-off and emergency power-off.You need to perform a normal power-off in scenarios such as an equipment swap or foreseeableregional blackout, and you need to perform an emergency power-off in emergencies such as afire, smoke, or water damage in indoor scenarios.ProcedurelNormal power-offNOTICEPowering off the pRRU3901 interrupts services, and therefore perform associatedoperations before a power-off.1. Remove the Ethernet cable.lEmergency power-off1. Turn off the switch of the external power device.----EndLampSiteSite Maintenance Guide 5 Powering On and Powering Off the pRRU3901Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.16
6 Replacing the RHUB3908The RHUB3908 is an indoor convergence unit. It converges multiple pRRUs to the BBU3900.Replacing the RHUB3908 interrupts services carried on the serving cell.PrerequisiteslA new RHUB3908 is available.lThe labels and connections of the cables connected to the RHUB3908 are recorded.lThe following tools are available: a Phillips screwdriver, an ESD wrist strap, and a rubbermallet.ContextIt takes about 10 minutes to replace the RHUB3908.ProcedurelReplace the RHUB3908 installed on a 19-inch rack, in a 19-inch cabinet or in a 19-InchShelf.NOTEThe procedures for replacing the RHUB3908 installed on a 19-inch rack are the same for replacingthe RHUB3908 installed in a 19-inch cabinet or in a 19-Inch Shelf. The following uses the RHUB3908installed on a 19-inch rack as an example.1. Power off the RHUB3908 by referring to 4.2 Powering Off the RHUB3908.2. Record the cable connections.3. Take insulation measures, and then remove all cables from the RHUB3908.4. Use a torque screwdriver or Phillips screwdriver to remove the four screws on themounting ear of the RHUB3908, as shown in Figure 6-1.LampSiteSite Maintenance Guide 6 Replacing the RHUB3908Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.17
Figure 6-1 Removing the mounting ear5. Remove the RHUB3908 from the rack.6. Install the new RHUB3908. For details, see LampSite Installation Guide.NOTICETake proper ESD protection measures, such as wearing an ESD wrist strap or ESDgloves to prevent electrostatic damage to the boards, modules, or electroniccomponents.7. Connect all the cables to the new RHUB3908 according to the recorded installations.8. Power on the RHUB3908 by referring to 4.1 Powering On the RHUB3908.9. Determine whether the new RHUB3908 is working properly according to the indicatorstatus on the RHUB3908. For details about the indicator status, see RHUB3908 Portsand Indicators in LampSite Hardware Description.lReplace the RHUB3908 installed on a wall.1. Power off the RHUB3908 by referring to 4.2 Powering Off the RHUB3908.2. Record the cable connections.3. Take insulation measures, and then remove all cables from the RHUB3908.4. Use a torque wrench or socket wrench to remove the four expansion bolts on themounting ear, and then remove the RHUB3908, as shown in Figure 6-2.LampSiteSite Maintenance Guide 6 Replacing the RHUB3908Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.18
Figure 6-2 Removing the mounting ear5. Install the new RHUB3908 on a wall. For details, see LampSite Installation Guide.NOTICETake proper ESD protection measures, such as wearing an ESD wrist strap or ESDgloves to prevent electrostatic damage to the boards, modules, or electroniccomponents.6. Connect all the cables to the new RHUB3908 according to the recorded installations.7. Power on the RHUB3908 by referring to 4.1 Powering On the RHUB3908.8. Determine whether the new RHUB3908 is working properly according to the indicatorstatus on the RHUB3908. For details about the indicator status, see RHUB3908 Portsand Indicators in LampSite Hardware Description.----EndLampSiteSite Maintenance Guide 6 Replacing the RHUB3908Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.19
Follow-up ProcedurelPlace the replaced RHUB3908 into an ESD box or bag. Then, place the ESD box or baginto a foam-padded carton or the packing box of the new optical module.lRecord the information about the faulty component in the fault card.lContact the local Huawei office to deal with the faulty component.LampSiteSite Maintenance Guide 6 Replacing the RHUB3908Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.20
7 Replacing an Optical ModuleAn optical module provides a port for opto-electronic conversion. This enables the transmissionbetween the RHUB3908 and BBU3900 through the optical fiber. Replacing the optical modulerequires removing the optical fibers. This interrupts all the services.PrerequisiteslThe number and type of faulty optical modules are confirmed, and new optical modulesare available.The new optical modules to be installed must match CPRI rates.lThe position for installing an optical module and the cable connection are recorded.lThe following tools and materials are available: an ESD wrist strap or ESD gloves, and anESD box or bag.ContextlThe optical modules are connected to the CPRI0 and CPRI1 ports on the RHUB3908 panel.lAn optical module or CPRI fiber optic cable cannot be inserted into or removed from thisCPRI port when the power supply is connected.lReplacing an optical module involves removing an optical fiber and the faulty opticalmodule, installing a new optical module, connecting the optical fiber to the optical module,and recovering the links. The operation takes about 10 minutes.NOTICETake proper ESD protection measures, such as wearing an ESD wrist strap or ESD gloves toprevent electrostatic damage to the boards, modules, or electronic components.ProcedureStep 1 Wear ESD gloves.Step 2 Record the optical module and fiber connections.Step 3 Power off the RHUB3908 according to the instructions in 4.2 Powering Off the RHUB3908.LampSiteSite Maintenance Guide 7 Replacing an Optical ModuleIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.21
CAUTIONAfter removing the optical fiber from the optical module, do not look directly at the opticalmodules without eye protection.Step 4 Press the latch on the connector of the optical fiber connector, and remove the connector fromthe faulty optical module, use the dust-proof cap to protect the optical fiber, as shown in Figure7-1.Figure 7-1 Removing the optical fiberStep 5 Turn the ring-pull on the faulty optical module outwards. Hold the ring-pull and take the faultyoptical module out of the slot to remove it from the CPRI0 or CPRI1 port, as shown in Figure7-2.Figure 7-2 Removing the optical moduleStep 6 Install the new optical module onto the corresponding CPRI port, as shown in Figure 7-3.LampSiteSite Maintenance Guide 7 Replacing an Optical ModuleIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.22
Figure 7-3 Installing the new optical moduleStep 7 Remove the dust-proof caps from the optical module and optical fiber, and connect the opticalfiber connector to the new optical module, as shown in Figure 7-4.Figure 7-4 Installing the optical fiberStep 8 Power on the RRU according to the instructions in 4.1 Powering On the RHUB3908.Step 9 Check whether CPRI signal transmission recovers by observing the CPRI indicator on theRHUB3908 panel.If... Then...The CPRI indicator is green CPRI signal transmission recovers and theoptical fiber replacement is successful.The CPRI indicator is red or in another color CPRI signal transmission is abnormal. Checkwhether the optical fiber and optical moduleare securely installed. Step 10 Take off the ESD gloves and pack up all the tools.----EndLampSiteSite Maintenance Guide 7 Replacing an Optical ModuleIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.23
Follow-up ProcedurelPlace the replaced optical module into an ESD box or bag. Then, place the ESD box or baginto a foam-padded carton or the packing box of the new optical module.lRecord the information about the faulty component in the fault card.lContact the local Huawei office to deal with the faulty component.LampSiteSite Maintenance Guide 7 Replacing an Optical ModuleIssue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.24
8 Replacing the pRRU3901pRRU3901 is an indoor remote radio unit. It processes RF signals. Replacing the pRRU3901interrupts all the services carried on it.PrerequisiteslReplacing the pRRU3901 when:–The functional modules inside a pRRU3901 or the housing of pRRU3901 is damaged.–Adding the RF daughter board or Wi-Fi daughter board.lThe hardware type is confirmed and a new pRRU3901 is available.lThe labels and connections of the cables connected to the pRRU3901 are recorded.lThe following tools are available: an electrostatic discharge (ESD) wrist strap and ESDgloves.ContextIt takes about 5 minutes to replace the pRRU3901.NOTEThe pRRU3901 can be installed on a metal pole, wall, or ceiling, and the procedures for replacing thepRRU3901 are almost the same. The following uses a ceiling-mounted pRRU3901 as an example.ProcedureStep 1 Instruct the network operator to block the pRRU3901.NOTEThe LampSite solution supports immediate block, idle block, and delayed block. Application of idle blockand delayed block produces the same effect as application of immediate block.lOn the UMTS side, log in to the LMT and run the BLK BRD command to block the RFdaughter board of the pRRU3901.lOn the LTE side, log in to the LMT and run the BLK BRD command to block the RF daughterboard of the pRRU3901.Step 2 Wear ESD gloves.LampSiteSite Maintenance Guide 8 Replacing the pRRU3901Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.25
CAUTIONlTake proper ESD protection measures, such as wearing ESD gloves to prevent electrostaticdamage to the boards, modules, or electronic components.lA pRRU3901 that has just been powered off has afterheat. Take scald-proof measures whenremoving the pRRU3901.Step 3 Power off the pRRU3901. For details, see 5.2 Powering Off the pRRU3901.Step 4 Record the cable connections.Step 5 Take insulation measures, and then remove all cables from the pRRU3901.Step 6 Hold the pRRU3901 case in one hand and pull the hoist clamp on the mounting bracket with theother hand, as shown in step a in Figure 8-1. Then, remove the mounting bracket from thepRRU3901, as shown in step b in Figure 8-1.Figure 8-1 Removing the pRRU3901Step 7 Install the new pRRU3901. The installation must be based on different scenarios. For details,see LampSite Installation Guide.NOTICETake proper ESD protection measures, such as wearing an ESD wrist strap or ESD gloves toprevent electrostatic damage to the boards, modules, or electronic components.Step 8 Connect the cables to the pRRU3901 according to the recorded positions.Step 9 Power on the pRRU3901 by referring to 5.1 Powering On the pRRU3901.LampSiteSite Maintenance Guide 8 Replacing the pRRU3901Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.26
Step 10 Check whether the new pRRU3901 is working properly according to the indicator status on thepRRU3901. For details about the indicator status, see pRRU3901 Ports and Indicators inLampSite Hardware Description.Step 11 Instruct the network operator to unblock the pRRU3901.1. On the UMTS side, log in to the NodeB LMT and run the UBL BRD command to unblockthe RF daughter board of the pRRU3901.2. On the LTE side, log in to the eNodeB LMT and run the UBL BRD command to unblockthe RF daughter board of the pRRU3901.Step 12 Take off the ESD gloves and pack up all the tools.----EndLampSiteSite Maintenance Guide 8 Replacing the pRRU3901Issue 05 (2015-01-15) Huawei Proprietary and ConfidentialCopyright © Huawei Technologies Co., Ltd.27
        Regulatory Compliance Statement    pRRU3901, pRRU3901 AWS+PCS+WIFI        Issue: 02  Date:2014-12-11  HUAWEI TECHNOLOGIES CO., LTD.
 Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. i    Copyright © Huawei Technologies Co., Ltd. 2010. All rights reserved. No  part  of  this  document  may  be  reproduced  or  transmitted  in  any  form  or  by  any  means  without  prior  written consent of Huawei Technologies Co., Ltd.  Trademarks and Permissions   and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.  Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document  are  provided  "AS  IS"  without  warranties,  guarantees  or  representations  of  any  kind,  either  express  or implied. The information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute the warranty of any kind, express or implied.     Huawei Technologies Co., Ltd. Address: Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China Website: http://www.huawei.com Email: support@huawei.com
  1 Regulatory Compliance Statement  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 1-1  1 Regulatory Compliance Statement About This Chapter 1.1    Declaration of Conformity to European Directives
1 Regulatory Compliance Statement    1-2 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    ()  1.1 Declaration of Conformity to European Directives Figure 1-1 Declaration of Conformity to European Directives
  2 Regulatory Compliance Information  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 2-1  2 Regulatory Compliance Information About This Chapter 2.1    Regulatory Compliance Standards 2.2    European Regulatory Compliance 2.3    U.S.A Regulatory Compliance                                   2.4  Canada Regulatory Compliance 2.5  Japanese Regulatory Compliance 2.6  CISPR 22 Compliance   2.7  China RoHS hazardous substance table 2.8  India RoHS hazardous substance table 2.9  Other Markets 2.1 Regulatory Compliance Standards The Product complies with the standards listed in Table 2-1.
2 Regulatory Compliance Information    2-2 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)  Table 2-1 Regulatory compliance standards Discipline Standards EMC  CISPR22 Class B  CISPR24  EN55022 Class B  EN50024  ETSI EN 301 489 Class B  CFR 47 FCC Part 15 Class B  ICES 003 Class B  AS/NZS CISPR22 Class B  GB9254 Class B  VCCI Class B  CNS 13438 Class B  IEC/EN61000-3-2  IEC/EN61000-3-3  IEC/EN61000-6-1  IEC/EN61000-6-3 RF  ETSI EN 301 908-1  ETSI EN 301 908-3  ETSI EN 301 908-14  ETSI EN 300 328  ETSI EN 301 893 Heath  ICNIRP Guideline  1999-519-EC  EN 50385  OET Bulletin 65  IEEE Std C95.1  EN 60215  EN 62311 Safety  IEC/EN 60950-1  IEC/EN41003  EN 60950-1  UL 60950-1  CSA C22.2 No 60950-1  AS/NZS 60950.1  BS EN 60950-1  IS 13252  GB4943
  2 Regulatory Compliance Information  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 2-3  Discipline Standards Environmental protection  2011/65/EU (RoHS)  EC NO. 1907/2006 (REACH)  2002/96/EC (WEEE) Grounding  ITU-T K.27  ETSI EN 300 253 NOTE EMC: electromagnetic compatibility NEBS: Network Equipment Build Standard RF: radio frequency CISPR: International Special Committee on Radio Interference EN: European Standard ETSI: European Telecommunications Standards Institute CFR: Code of Federal Regulations FCC: Federal Communication Commission IEC: International Electrotechnical Commission AS/NZS: Australian/New Zealand Standard VCCI: Voluntary Control Council for Interference CNS: Chinese National Standard UL: Underwriters Laboratories CSA: Canadian Standards Association BS: British Standard IS: Indian Standard GR: General Requirement FDA: Food and Drug Administration BTS: Base Transceiver Station GSM: Global System for Mobile communications WLAN: wireless local area network ICNIRP: International Commission on Non-Ionizing Radiation Protection OET: Office of Engineering Technology IEEE: Institute of Electrical and Electronics Engineers RoHS: restriction of the use of certain hazardous substances  2.2   European Regulatory Compliance The Product complies with the following European directives and regulations.  2004/108/EC (EMC)  2006/95/EC (low voltage)  1999/5/EC (R&TTE)  2011/65/EU (RoHS)  EC NO. 1907/2006 (REACH)
2 Regulatory Compliance Information    2-4 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)   2002/96/EC (WEEE) Product complies with Directive 2002/95/EC, 2011/65/EU and other similar regulations from the countries outside the European Union, on the RoHS in electrical and electronic equipment. The  device  does  not  contain  lead,  mercury,  cadmium,  and  hexavalent  chromium  and brominated flame retardants (Polybrominated Biphenyls (PBB) or Polybrominated Diphenyl Ethers  (PBDE))  except  for  those  exempted  applications  allowed  by  RoHS  directive  for technical reasons.   Product complies with Regulation EC NO. 1907/2006 (REACH) and other similar regulations from the countries outside the European Union. Huawei will notify to the European Chemical Agency (ECHA) or the customer when necessary and regulation requires.  Product  complies  with  Directive  2002/96/EC on  waste  electrical  and  electronic  equipment (WEEE).  Huawei  is  responsible  for  recycling  its  end-of-life  devices,  and  please  contact Huawei local service center when recycling is required. Huawei strictly complies with the EU Waste Electrical and Electronic Equipment Directive (WEEE Directive) and electronic waste management regulations enacted by different countries worldwide. In addition, Huawei has established a system for recycling and reuse of electronic wastes, and it can provide service of dismantling and recycling for WEEE. By Huawei recycling system, the waste can be handled environmentally  and  the  resource can be recycled  and  reused  fully,  which  is  also  Huawei WEEE  stratagem  in  the  word.  Most  of  the  materials  in  product  are  recyclable,  and  our packaging is designed to be recycled and should be handled in accordance with your local recycling policies.   In accordance with  Article 11(2) in Directive 2002/96/EC  (WEEE), products  were  marked with the following symbol: a cross-out wheeled waste bin with a bar beneath as below:   2.3 U.S.A Regulatory Compliance    2.3.1FCC Part 15 The Product complies with Part 15 of the FCC Rules. Operation is subject to the following two conditions:  This device does not cause harmful interference.  This device must accept any interference received, including interference that may cause undesired operation.
  2 Regulatory Compliance Information  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 2-5  If this device is modified without authorization from Huawei, the device may no longer comply with FCC requirements for Class B digital devices. In that a case, your right to use the device may be limited by FCC regulations. Moreover, you may be required to correct any interference to radio or television communications at your own expense. This device has been tested and found to comply with the limits for a Class B digital device, pursuant to Part 15 of the FCC rules. These limits are designed to provide reasonable protection against harmful interference in a residential installation. This device generates, uses and radiates radio frequency energy. If it is not installed and used in accordance with the instructions, it may cause harmful interference to radio communications. However, there is no guarantee that interference will not occur in a particular installation. If this device does cause harmful interference to radio or television reception, which can be determined by turning the device off and on, the user may take one or more of the following measures:  Reorient or relocate the receiving antenna.  Reinforce the separation between the device and receiver.  Connect the device into an outlet on a circuit different from that to which the receiver is connected.  Consult the dealer or an experienced radio or TV technician for assistance.  This product may contains FCC ID QISPRU01B02 or FCC ID QISPRU01B01 or QISPRU02WLAN or their combination both or three transmitters  2.4 Canada Regulatory Compliance 2.4.1 RSS-Gen statement This device complies with Industry Canada licence-exempt RSS standard(s). Operation is subject to the following two conditions: (1) this device may not cause interference, and (2) this device must accept any interference, including interference that may cause undesired operation of the device. Le présent appareil est conforme aux CNR d'Industrie Canada applicables aux appareils radio exempts de licence. L'exploitation est autorisée aux deux conditions suivantes : (1) l'appareil ne doit pas produire de brouillage, et (2) l'utilisateur de l'appareil doit accepter tout brouillage radioélectrique subi, même si le brouillage est susceptible d'en compromettre le fonctionnement. 2.4.2 RSS-102 statement This device is designed and manufactured not to exceed the emission limits for exposure to radio frequency (RF) energy set by Industrial Canada and meets the requirements for radiation exposure limits set forth for an uncontrolled environment. In order to avoid the possibility of exceeding the Industrial Canada radio frequency exposure limits, human proximity to the equipment shall not be less than 0.2m
2 Regulatory Compliance Information    2-6 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)  Cet appareil est conçu et fabriqué pour ne pas dépasser les limites d'émission pour l'exposition à la fréquence radio (RF) de l'énergie fixé par l'Industrielle Canada et répond aux exigences en matière de limites d'exposition aux rayonnements définies pour un environnement non contrôlé.   Afin d'éviter la possibilité de dépasser les limites d'exposition aux fréquences radio industrielle du Canada, la proximité humaine pour l'appareil nedoit pas être inférieure à0.2m This product may contains IC 6369A-PRU01B02 or IC 6369A-PRU01B01 or 6369A-PRU02WLAN or their combination both or three transmitters  2.5 Japanese Regulatory Compliance  2.4.1VCCI The Product complies with VCCI Class B by Information Technology Equipment (ITE). The preceding translates as follows: This is a Class B product based on the standard of the Voluntary Control Council for Interference by Information Technology Equipment (VCCI).If this product is used Near a radio or television receiver in a domestic environment. It may cause radio Interference.Install and use the equipment according to the instruction manual.    2.6 CISPR 22 Compliance The Product complies with CISPR 22 for Class B by the ITE.  2.7 China RoHS hazardous substance table
  2 Regulatory Compliance Information  Issue    (02) Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. 2-7  This products described in this guide complies with “the Administration on the Control of Pollution Caused by Electronic Information Products” which is also called China RoHS 部件名称 产品中有害物质或元素的名称及含量 镉 铅 汞 六价铬 多溴联苯 多溴联苯醚 Alloy Parts 〇 ╳ 〇 〇 〇 〇 Metal Fittings 〇 〇 〇 〇 〇 〇 PCBA 〇 ╳ 〇 〇 〇 〇 Capacitor 〇 ╳ 〇 〇 〇 〇 Other electronics 〇 ╳ 〇 〇 〇 〇 Solder 〇 ╳ 〇 〇 〇 〇 Cable 〇 〇 〇 〇 〇 〇 Plastic and Polymer 〇 〇 〇 〇 〇 ╳ 〇:表示该有毒有害物质在该部件所有均质材料中的含量均在SJ/T11363-2006 标准规定的限量要求以下。 ╳:表示该有毒有害物质至少在该部件的某一均质材料中的含量超出SJ/T11363-2006 标准规定的限量要求。  2.8 India RoHS hazardous substance table This products described in this guide complies with the “e-waste (Management and Handling) Rules, 2011”of India which is also called India RoHS.  Part Descriptions Restricted Substances in Product Cd Pb Hg Cr(VI) PBBs PBDEs Alloy Parts 〇 ╳ 〇 〇 〇 〇 Metal Fittings 〇 〇 〇 〇 〇 〇 PCBA 〇 ╳ 〇 〇 〇 〇 Capacitor 〇 ╳ 〇 〇 〇 〇
2 Regulatory Compliance Information    2-8 Huawei Proprietary and Confidential                                     Copyright © Huawei Technologies Co., Ltd. Issue    (02)  Other electronics 〇 ╳ 〇 〇 〇 〇 Solder 〇 ╳ 〇 〇 〇 〇 Cable 〇 〇 〇 〇 〇 〇 Plastic and Polymer 〇 〇 〇 〇 〇 ╳ 〇: indicates that the content of the toxic and hazardous substance in all the Homogeneous Materials of the part is below the concentration limit requirement as described in the e-waste (Management and Handling) Rules, 2011. ╳: indicates that the content of the toxic and hazardous substance in at least one Homogeneous Material of the part exceeds the concentration limit requirement as described in S in the e-waste (Management and Handling) Rules, 2011.  2.9 Other Markets For relevant compliance information/documentation for markets not mentioned above, Please contact Huawei representative

Navigation menu