BTI Wireless MBSC2100-040 mBSC-040 DAS System User Manual

Bravo Tech (Shenzhen) Co. Ltd. mBSC-040 DAS System

user manual

mBSC DAS SystemInstallation Manual Issue 3 mBSC DAS SYSTEM INSTALLATION AND OPERATIONS MANUAL
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage2                                                        COPYRIGHT This document serves as the System Installation Manual for the BTI mBSC Fiber Distributed Antenna System (DAS) system. BTI reserves the right to change the contents without prior notice. No part of this document may be reproduced or utilized. © 2009-2011, BTI, All Rights Reserved    REVISION HISTORY
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage3   ISSUE NO.  DESCRIPTION DATE 1 INITIAL DRAFT  OCT. 28, 2009 2  UPDATE THE SPECIFICATION  JAN. 18, 2010 3  UPDATE SPECIFICATION, INSTALLATION, AND ILLUSTRATIONS  MAY 31, 2011
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage4   TABLE OF CONTENTS 1 GENERAL INFORMATION ........................................................ 6 1.1  SAFETY PRECAUTIONS ....................................................................6 1.2  GLOSSARY AND ACRONYMS ...........................................................7 2 INTRODUCTION ........................................................................ 8 3  GENERAL DESCRIPTION ......................................................... 8 3.1  SYSTEM COMPONENTS DESCRIPTION ..........................................8 3.1.1  Host Unit ........................................................................................9 3.1.2  Network Management System......................................................9 3.1.3  Remote Unit .................................................................................10 3.2  USER INTERFACE ............................................................................13 3.2.1  Host Unit Interface ......................................................................13 3.2.2  NMS Interface ..............................................................................13 3.2.3  Remote Unit Interface  ................................................................15 3.3  SPECIFICATIONS .............................................................................17 3.3.1  Host Unit Specifications .............................................................17 3.3.2  NMS Specifications  ....................................................................17 3.3.3  Remote Unit Specification .........................................................18 4 INSTALLATION ........................................................................ 19 4.1  SYSTEM INSTALLATION OVERVIEW..............................................19 4.2  REMOTE UNIT INSTALLATION .......................................................20 4.2.1  Remote Unit Installation Overview.............................................20 4.2.2  Installation Hardware And Tools ................................................20 4.2.3  Unpacking And Inspection .........................................................22 4.2.4  Mechanical Installation ...............................................................23 4.2.4.1  Mechanical Safety Precautions......................................................................... 23 4.2.4.2  Install The Mounting Panel................................................................................ 24 4.2.4.3  Install The Remote Unit On The Mounting Panel ............................................. 25 4.2.4.4  Install The Shroud Cover .................................................................................. 25 4.2.5  Electrical Installation...................................................................27 4.2.5.1  Electrical Safety Precautions ............................................................................ 27 4.2.5.2  Grounding ......................................................................................................... 28 4.2.5.3  Route the Cables .............................................................................................. 28 4.2.5.4  Fiber Optic Cable Connection ........................................................................... 28 4.2.5.5  Antenna Cable Connection ............................................................................... 29 4.2.5.6  AC Power Cable Connection ............................................................................ 30 4.2.5.7  Slave Cable Connection ................................................................................... 31 4.2.6  Remote Unit Installation Review  ...............................................33
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage5   4.2.6.1  Mechanical Installation Review ......................................................................... 33 4.2.6.2  Electrical Installation Review............................................................................. 33 4.2.6.3  Field Status Test - Remote Unit LED Status Indicators..................................... 33 4.2.7  Troubleshooting ..........................................................................34 4.3  HOST UNIT INSTALLATION .............................................................35 4.3.1  Host Unit Installation Overview ..................................................35 4.3.2  Installation Hardware And Tools ................................................35 4.3.3  Unpacking And Inspection .........................................................36 4.3.4  Electrical Installation...................................................................37 4.3.4.1  Electrical Safety Precautions ............................................................................ 37 4.3.4.2  Grounding ......................................................................................................... 38 4.3.4.3  DC Power Cable Connection ............................................................................ 39 4.3.4.4  Install the BIU and FIU modules ....................................................................... 40 4.3.4.5 Alarm Installation ............................................................................................... 40 4.3.4.6  Connect the BIU/FIU Modules .......................................................................... 42 4.3.4.7  Optional Equipment Installation ........................................................................ 43 4.3.4.8  Connect POI to BIU........................................................................................... 44 4.3.4.9  Connect the Fiber Optic Cable.......................................................................... 44 4.3.5  Host Unit Installation Review  ....................................................44 4.3.5.1  Electrical Installation Review............................................................................. 44 4.3.6  Troubleshooting ..........................................................................46 4.4  NMS INSTALLATION.........................................................................47 4.4.1  Installation Overview...................................................................47 4.4.2  Installation Hardware and Tools.................................................47 4.4.3  Unpacking And Inspection .........................................................48 4.4.4  Verify Server software .................................................................48 4.4.5  Initial System Setup ....................................................................49 4.4.5.1  CD-ROM Install ................................................................................................. 49 4.4.5.2  Launch NMS ..................................................................................................... 51 4.4.6  Initial Start-up Configuration ......................................................52 4.4.6.1  Modify Default Accounts.................................................................................... 54 4.4.6.2  Set-up New User Accounts ............................................................................... 57 4.4.6.3  Configure Software Parameters........................................................................ 59 4.4.7  Firmware Update  ........................................................................60 4.4.8  Software Upgrade Installation ....................................................61 4.4.8.1  CD-ROM Install ................................................................................................. 61 4.4.9  NMS Upgrade Installation Review .............................................62 4.4.10  Troubleshooting ........................................................................64 5  mBSC DAS SYSTEM START-UP ............................................ 65 5.1  SYSTEM COMMUNICATION.............................................................65 5.1.1  Establishing a Host Unit communication ..................................65 5.2  INITIAL NETWORK CONFIGURATION ............................................68
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage6   5.2.1 Add a Site .....................................................................................70 5.2.2 Add a Host Unit............................................................................72 5.2.3  Configuring the Host Unit Hardware Card ................................74 5.2.4  Map the IP Address to the NMS Software..................................78 5.2.5 Add a Master Remote ..................................................................80 5.2.6 Add a Slave Remote ....................................................................81 5.2.7  Connect Host Unit to Server.......................................................82 5.3  MANAGING AND MONITORING ALARMS ......................................83 5.3.1 Alarm Manager.............................................................................83 5.3.2  Configuring Standard Alarm Defaults........................................84 5.3.3  System Activation Review  .........................................................89 5.3.4  Troubleshooting  .........................................................................90 6  CUSTOMER SERVICE CONTACT INFORMATION ................ 91
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage7    1 GENERAL INFORMATION   1.1 SAFETY PRECAUTIONS   Danger: Danger is used to indicate the presence of a hazard that will cause serious personal injury, death or substantial property damage if the hazard is not avoided.  Warning: Warning is used to indicate the presence of a hazard that may cause serious personal injury, possible death or substantial property damage if the hazard is not avoided.  Caution: Caution is used to indicate the presence of a hazard that will or may cause minor personal injury or substantial property damage if the hazard is not avoided.   1.  For general safety, only appropriately qualified personnel familiar with all recommended and regulatory safety practices and installation methods may be allowed to work on this system.  2.  All general and regional safety and installation regulations relating to high voltage installations, proper use of tools and recommended individual protective equipment must be obeyed.  3.  Operating instructions must be kept accessible and available for all users.  4.  The network provider is responsible for implementing protective measures to avoid the health hazards associated with radiation from the Unit antenna(s).  5.   For US and Canadian installations: FCC RF exposure compliance requires the following antenna installation and device operation configurations be satisfied: A separation distance of at least 4 meters must be maintained between the antenna of this device and all persons. RF exposure compliance may need to be addressed at the time of licensing, as required by the responsible FCC Bureau(s), including antenna co-location requirements of 1.1307(b)(3). §2.1091 Maximum permissible antenna gain is 16.15 dBi.  6.  Access should be restricted to appropriately qualified personnel.  7.  Operation of this Unit is restricted to the license holders of the respective frequency range.  8.  Use of this equipment is only for the purpose specified by the manufacturer. Modifications or the use of any spare parts which are not provided by or recommended by the manufacturer are prohibited as this may cause fires, electric shock or other injuries or damage.  9.  High temperatures due to power dissipation may occur, do not operate the equipment on or near combustible materials.  10.Ascertain that the mains supply is disconnected before opening the Unit as well as connecting or disconnecting the mains connector at the Remote Unit.  11.Observe ESD precautions. Use the available grounding system to connect ESD protection measures before commencing maintenance work.  12.This Unit complies with European standard EN60950.  13.Verify that all regulatory requirements have been met and that all system settings have been set according to the intended use. (Please see appropriate manufacturer product information materials.)  14.Grounding the antenna cables close to the antenna connectors of the Remote Unit for
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage8    protection against atmospheric discharge is highly suggested, even though the Remote Unit is internally protected against over-voltage.  15.Class 1 – Laser Radiation warning:  Do not look into the beam, view it directly, or indirectly with or without optical instruments.   1.2 GLOSSARY AND ACRONYMS   The acronyms and abbreviations used in this manual are detailed in the following list.  Abbreviation Description AISG  Antenna Interface Standard Group BIU  Base station Interface Unit BTS Base Station CFR Crest Factor Reduction CL-OS  Closed-Loop Operating System DAS  Distributed Antenna System EDGE  Enhanced Data for GSM Evolution FIU  Fiber Interface Unit FIU-S  Fiber Interface Unit - Simulcast FIU-NS  Fiber Interface Unit - Non-Simulcast HPA High Power Amplifier HU Host Unit LMU Location Measurement Unit LNA Low Noise Amplifier mBSC  Multi-Band Multi-System Multi-Carriers MIMO Multi-input multi-output MTBF  Mean Time Between Failure NMS  Network Management System PA Power Amplifier PCU  Power Controller Unit PWM Pulse Width Modulation RCU Remote Control Unit RF Radio Frequency RU Remote Unit RX Receive Signal TDTD Time delay TX diversity TMA  Tower Mounted Amplifier TX Transmit Signal UMTS  Universal Mobile Telecom System VSWR  Vertical Standing Wave Radio
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage9   2 INTRODUCTION  This document provides the installation procedures for the BTI DAS system consisting of the DAS Host Unit, Remote Unit equipment and the Network Management System (NMS). It also provides for the initial configuration set-up, operation procedures and the software upgrade installation process for the Network Management System.  For Host Unit and Remote Unit installation, the reader should be familiar with the use of Distributed Antenna Systems, power system distribution for both AC and DC, all safety guidelines and regulations, and the required tools to accomplish the installation in a safe manner. NOTE: This equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to Part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference in a residential installation. This equipment generates, uses and can radiate radio frequency energy and, if not installed and used in accordance with the instructions, may cause harmful interference to radio communications. However, there is no guarantee that interference will not occur in a particular installation. If this equipment does cause harmful interference to radio or television reception, which can be determined by turning the equipment off and on, the user is encouraged to try to correct the interference by one or more of the following measures: -- Reorient or relocate the receiving antenna. -- Increase the separation between the equipment and receiver. -- Connect the equipment into an outlet on a circuit different from that to which the receiver is connected. -- Consult the dealer or an experienced radio/TV technician for help.  For  NMS  software  installation  and  configuration  as  well  as  firmware  update  and  software  upgrade installations, the reader should be familiar with server administration, software install, firmware update, and software upgrade procedures at the administrator level.                                3 GENERAL DESCRIPTION  Figure 3-1. BTI DAS System
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage10    The system consists of an Indoor HU (Host Unit) and an Outdoor RU (Remote Unit) and Network Management Software.  3.1 SYSTEM COMPONENTS DESCRIPTION  The  Host  Unit  is  designed  to  be  mounted  in  a  19”  rack  and  should  only  be  utilized  in  an  indoor environment (0C - 45C) or in a place were an indoor-type environment can be provided.  The NMS (Network Management System) runs on a centralized server that provides access to the entire network of hub sites and Remote nodes. The NMS is designed to configure, monitor, and manage all system functionality.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage11   The  Remote  Units  may  consist  of  combinations  of  700MHz,  850MHz,  1900MHz  and  2100MHz frequencies and are available in either a 20 Watt or 40 Watt output configuration. Each RU is designed to support a Single Frequency Band. For multi-frequency use, the system can be configured as multiple Master/Slave Remote Units. Each Master Unit can support a maximum of two slave RUs with a maximum of three RUs supported per fiber connection. The primary transport between the HU and the RU is fiber optic. The Fiber Optic also provides the RU alarms and configuration communication between the NMS and the Remote Unit. The downlink and uplink optical signals are duplexed so only one fiber is required.  3.1.1  Host Unit  The Host Unit provides a multiple slot assembly, consisting of 9 slots numbered from left to right: 1 through 9.  Slots 7 through 9 are used and specifically keyed for the Remote Control Unit (RCU) and two redundant Power Supply Units (PSU) only. The Host Unit also houses the Base Station Interface Units (BIU) and Fiber Interface Units (FIU), Figure 3-2. The BIU comes in Diversity (BIU-D) and Non-Diversity (BIU-ND) and the FIU comes in Simulcast (FIU-S) and Non-Simulcast (FIU-NS) modules. The HU allows multiple combinations of BIU and FIU modules with up to 3 band downlink and uplink RF signals per BIU from the BTS and converts them to analog over RF for fiber transport.  The Host Unit, through interface combinations, provides the following functions: • Converts the BTS RF signal to fiber signal. • Supplies connectivity between the BTS and the Remote Unit. • Manages and monitors the system alarms and configurations. • Supports 1 to 3 Sectors system configurations. • Supports a single sector with 1:1, 2:1, 3:1 and 4:1 Simulcast configuration. • Supplies fiber connectivity to the Remote Unit with in-band message signaling.                Figure 3-2. Host Unit Multiple-Slot Assembly   3.1.2  Network Management System  The  Network  Management  System  (NMS),  shown  in  Figure  3-3,  is  a  software-based  Network Management System tool that provides control and monitoring functions for the BTI mBSC DAS system. NMS is used to provision and configure a new system for operation, set the system operating parameters, get system alarms and status messages, and update the system firmware.  The Network Management System provides the following functions: • Manages SNMP v2 messaging to the Network Operating Center (NOC). • Provides  a  detailed  graphic  User  Interface  to  manage,  monitor  and  configure  multiple  DAS system. • Configure multiple DAS systems custom alarms. • Provides a firmware update interface.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage12      Figure 3-3. Network Management System Software Components Folder and Desktop Icon   3.1.3  Remote Unit  The Single-Band Master Remote Unit, shown in Figure 3-4a, b and c, consists of an optical module (O/E), a downlink power amplifier, an LNA, and duplexer. The Optical module converts the downlink optical signal from the FIU module in the HU and splits the RF signal into 3 RUs. It also converts the uplink RF signal to an optical signal and simultaneously sends it to the FIU module in the HU for distribution to the BIU modules. Each optical module can support 3 RUs in any combination of different bands.  The Single-Band Master Remote Unit provides the following functions: • Converts the forward optic signal to RF signal. • Boosts the forward RF signal from the HU to a higher power level (max output:40W). • Amplifies the uplink signal from the antenna to improve the system receive sensitivity. • Supplies in-band messaging between the HU and RU for RU Alarms and configuration.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage13                                Figure 3-4a. 40 Watt Fan Cooled Remote Unit
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage14                                Figure 3-4b. 20 Watt Convection Cooled Remote Unit                                Figure 3-4c. 20 Watt Fan Cooled Remote Unit
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage15   Module Name Port Name Description Remark TX1, TX2 Downlink interface ports to be connected to BIU output RF signal RX1, RX2 Uplink interface ports to be connected to BIU input RF signal Fiber 1, Fiber 2 Fiber optic interface ports to be connected to the RU Optical signal E9111, E9111-2 The RX coupling uplink signal for LMU (TDOA location only) RF signal E9111, E9111-2 The RX coupling uplink signal for LMU (TDOA Location only) RF signal FIU-S/FIU-NS E9111, E9111-2 The RX coupling uplink signal for LMU (TDOA Location only) RF signal TX1, TX2, TX3, TX4 Input signals from the BTS to provide the combined downlink signal to FIUs RF signal RX1, RX2, RX3, RX4 The combined uplink signal from FIUs RF signal TX1 and TX2 out Downlink RF interface to FIU RF signal BIU-ND/BIU-D RX1, RX2, RX3, andRX4 out Uplink RF interface from the FIU RF signal 3.2 USER INTERFACE  The user interface for each segment of the mBSC DAS System is designed to provide the most efficient interaction, installation and ease of use for the user.   3.2.1  Host Unit Interface  Each interface module of the Host Unit, shown in Figure 3-5, is described in Table 3-1 below.                 Figure 3-5. Host Unit Interface   Table 3-1. Host Unit User Interface                               3.2.2  NMS Interface  A simple login access, Figure 3-6, allows for quick access. A graphical user interface, Figure 3-7, provides real time user access to the configuration, performance monitoring, and alarm status. The system also uses SNMPv2.0 protocol to transmit automated traps to the operator's Network Operations
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage16   Center  for  remote  alarming  and  system  queries.  These  two  capabilities  provide  for  centralized configuration and alarm monitoring of the entire system.  Operational parameters, such as uplink and downlink, and gain can be set through the NMS server. Status information at each node is easily available. The customer can readily access power output, ALC status, VSWR, PA temperature, and other basic operating parameters, The BTI NMS simplifies the configuration of the network by providing accurate downlink power and uplink gain updates. This allows the system operator to maximize the efficient use of field personnel when diagnosing system performance issues.                        Figure 3-6. NMS Login Interface
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage17                                    Figure 3-7. NMS Command Console   Table 3-2. Default Parameter Values Menu Parameter Name Default Value System Parameter SNMP No User Manager Name: Manager; Password: 1; Level: Supervisor User User Name: User; Password: 1; Level: Observer  3.2.3  Remote Unit Interface  The interface of the Remote Unit consists of connectors and LEDs that are located on the bottom of the RU enclosure. The Master RU user interface points are indicated in Figure 3-8 and Table 3-3. The Slave RU user interface points are indicated in Figure 3-9 and Table 3-4.  Remote Units are classified as either MASTER or SLAVE. Master and Slave Units have exactly the same mechanical  dimensions.  Functionality  is  the  main  difference  as  the  MASTER  Remote Unit has the connection for the fiber optic cable. For supporting multiple bands, only the MASTER Remote Unit needs to have the fiber optic connection with the Host Unit. Other Remote Units are interfaced with SLAVE ports for receiving RF downlink signal and sending RF uplink signal with the Master Remote Unit.  • MASTER Remote Unit: • Has the Fiber Optic Cable connection with the Host Unit • Provides the RF downlink signal to the SLAVE Remote Unit through “TX_IN” or “TX_OUT” port. • Receives the RF uplink signal from the SLAVE Remote Unit “RF_IN” or “RF_OUT” port.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage18   Label Name Description ANT Interface port for Antenna Feed line OPERATE LED indicator for normal or critical fault status of the RU. Normal: Green ON, Critical fault: Red ON TX_Out  RX_In RF output port to provide the input signal to the Slave Remote Unit when Dual or Triple Band application is configured. RF input port to provide the output signal to the Master Remote Unit when Dual or Triple Band application is configured. FIBER Fiber Optic Cable interface port for combined downlink and uplink signal POWER Interface port for the AC 110/220V power cable DC_FAN Provides power to the fan VENT Port for the balance of pressure inside and outside of the enclosure Label Name Description ANT Interface port for Antenna Feed line OPERATE LED indicator for normal or critical fault status of the RU. Normal: Green ON, Critical fault: Red ON • SLAVE Remote Unit: • No Fiber Optic Cable connection with the Host Unit • Interfaces with the Master Unit for downlink and uplink signal • Unused ports (TX_OUT, RX_IN) are blocked with a cover.               Figure 3-8. User Interface of MASTER Remote Unit   Table -3-3. Master Remote Unit User Interface                                 Figure 3-9. User Interface of SLAVE Remote Unit   Table -3-4. Slave Remote Unit User Interface
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage19   Host Unit Specification  Description Notes System Support Multi-Frequency bands with Multi-Air Interface standards (GSM / EDGE / CDMA / WCDMA / AWS / LTE)  Max No. of Plug-in module •  3 fixed slots for two (PSU) and a single (RCU) •  6 module slots for BIU and FIU  PSU (Power Supply Unit) •  -48Vdc and optional AC 110/220 DC converter •  2 PSU are installed for redundancy  RCU (Remote Controller Unit)  Main process board for DAS system  BIU (Base station Interface Unit) •  Support multi-frequency bands DL and UL interface • Support RX Diversity •  QMA connector for RF Interface •  Support 4 downlink and uplink interface ports  FIU (Fiber Interface Unit) •  Support 2 Fiber ports per FIU •  Support Non-Simulcast or Simulcast   TX_Out (Slave 1) RX_In (Slave 2) POWER RF output port to provide the input signal to the Slave Remote Unit when Dual or Triple Band application is configured RF input port to provide the output signal to the Master Remote Unit when Dual or Triple Band application is configured. Interface port for the AC 110/220V power cable DC_FAN Provides power to fan VENT Port for the balance of pressure inside and outside of the enclosure  3.3 SPECIFICATIONS  3.3.1  Host Unit Specifications  The specifications for the Host Unit of the mBSC DAS system are listed in Table 3-5:  Table 3-5. Host Unit Specifications                       3.3.2  NMS Specifications  The specifications for the Network Management System (NMS) of the mBSC system are listed in Table 3- 6. Table 3-6. NMS Specifications NMS Specification  Specification  Notes Max No. of Nodes 1080 A combination of  BIU, FIU and Remote Units SNMP based management Yes  Real time alarm display Yes  Display various system level values Yes Voltages, RF power, etc. Remote firmware download Yes Firmware update interface for DAS components.  The NMS also requires a dedicated server to connect to the RCU. The Server specifications are  Table 3-7. Server Specifications  Server Specification  Notes Specification Processor One Quad-core Intel® Xeon® 3400 series processor
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage20   System Specification  Downlink Uplink Optic Wavelength 1310/1550nm Antenna Port 7/16 DIN female Optical connector E2000 Power Supply AC 110V / 220V ± 20% Current < 1A @ Full power, ~220V AC input < 2A @ Full power, ~110V AC input Weight varies per type Waterproof IP65  Server Specification  Notes Specification Operating System Microsoft® Windows® XP Professional  Memory 4GB (4 DIMM slots) DDR3  Storage Cabled Hard Drive Options: 2.5" SATA SSD, SAS (10K), nearline SAS (7.2K) Maximum Internal Storage: 250G  Power Single cabled power supply (250W)  Video Card Matrox G200eW w/ 8MB memory  Network Controller One dual-port Broadcom BCM 5716   3.3.3  Remote Unit  The specifications for the Remote Unit of the mBSC system are listed in Table 3-8.  Table 3-8. Remote Unit Specifications
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage21   4 INSTALLATION  4.1 SYSTEM INSTALLATION OVERVIEW  This section provides instructions for installing the mBSC DAS system in an efficient, productive and customer friendly order. Each component of the mBSC DAS system is covered in its own installation section  as follows:  4.2.REMOTE UNIT INSTALLATION The Remote Unit installation section provides instructions for the mechanical and electrical installation of the mBSC Remote Unit including: mounting the Remote Unit, connecting the fiber optics cables; Antenna feed line; and AC power cables.  The procedures in this section assume that the required Fiber Optic cables have been routed between the Host Unit and the Single-Band RU and that the required antenna has been installed.  4.3.HOST UNIT INSTALLATION The Host Unit installation section provides instructions for the electrical installation of the mBSC Host Unit including verifying the DC power cable connection, connecting the network cable, the alarm connectors, and other required connections and cables.  The procedures in this section assume that the Host Unit has been inspected, the Remote Unit(s) installation is complete and that a dedicated IP address for the Host Unit has been designated.  4.4.NMS INSTALLATION The Network Management System (NMS) installation section provides instructions for setting up the pre- installed software component of the mBSC NMS. The instructions will allow a qualified user to install the NMS software, set-up accounts, change passwords for security, and upgrade the system software and hardware.  The procedures in this section assume that the NMS server has been received, the Host Unit is installed, and that security software has been installed on the designated NMS computer(s).
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage22   4.2  REMOTE UNIT INSTALLATION   Danger: Wet conditions increase the potential for receiving an electrical shock when installing or using electrical power equipment. To avoid electrical shock, never install or use the electrical equipment in a wet location.  Danger: Do not look into the end of the fiber optic cables. Exposure to laser radiation may result. Do not assume that the laser power is turned off or that the fiber optic cable is disconnected at the other end.  Danger: Use extreme caution when working with high voltage AC power. Ensure all power is disconnected before working on power circuit.   Caution: Always make sure there is sufficient cable length to permit the routing of the fiber optic cables to prevent the cable damage. The optic cables may be damaged if bent or coiled too tightly.   4.2.1  Remote Unit Installation Overview  The installation of the Remote Unit, both single enclosure and multi-enclosure, consists of the following steps:  Table 4-1. Remote Unit Installation Overview Step Operation Type Operation Action 1 MECHANICAL INSTALL THE RU MOUNTING PANEL TO THE TOWER  2 MECHANICAL  VERIFY THAT THE SIDE MOUNTING BRACKETS ARE SECURELY ATTACHED TO THE REMOTE UNIT  3  MECHANICAL  INSTALL THE MASTER REMOTE UNIT ON THE MOUNTING PANEL  4 MECHANICAL  MOUNT THE SHROUD COVER OVER THE ENCLOSURE AND SECURE IT  5  INSTALLATION REVIEW  CONFIRM THE MECHANICAL INSTALLATION USING TABLE 4-4 MECHANICAL INSTALLATION CHECKLIST 6 ELECTRICAL  GROUND THE UNIT 7 ELECTRICAL  ROUTE THE CABLES TO BE CONNECTED 8 ELECTRICAL  CONNECT THE FIBER OPTIC CABLES 9 ELECTRICAL  CONNECT THE ANTENNA FEED LINE 10 ELECTRICAL  INSTALL THE AC POWER CABLE  11 ELECTRICAL  CONNECT ANY SLAVE REMOTE UNIT TO THE MASTER REMOTE UNIT  12  INSTALLATION REVIEW   13 FIELD STATUS TEST  CONFIRM THE ELECTRICAL INSTALLATION USING TABLE 4-5 ELECTRICAL INSTALLATION CHECKLIST  CHECK THE REMOTE UNIT LED STATUS INDICATORS USING TABLE 4-6  RU LED STATUS INDICATOR AND THE TROUBLESHOOTING GUIDE   4.2.2  Installation Hardware And Tools  The Remote Units are shipped with the standard mounting hardware required for a BTI pole-mount
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage23   Hardware and Fasteners Quantity Rec'd  1  MOUNTING PANEL (Configurable)  I-BEAM or U-BEAM/CHANNEL MOUNTING BRACKETS  2  SHROUD COVER 1  8  8  M5 SCREW M5 LOCK WASHER M5 FLAT WASHER 8  8  8  M6 SCREW  M6 LOCK WASHER  M6 FLAT WASHER 8  8  8  8  M8 SCREW M8 LOCK WASHER M8 FLAT WASHER M12 SCREW 4  M12 LOCK WASHER 4  4  1  2  1  M12 FLAT WASHER JUNCTION BOX RF CABLE (Designated Slave Unit) FIBER OPTIC COWL POWER CABLE (10 FEET) 1  FAN CONNECTOR (OPTIONAL) 1  installation. Table 4-2 lists the mounting hardware provided by the manufacturer for a BTI non-custom pole mount installation kit. Additional hardware may be needed, depending on the site requirements, and may be ordered through Customer Service (Section 6).  Table 4-2. Single-Band RU Mounting Hardware and Fasteners for a BTI non-custom pole mount installation kit                                            Table 4-3. Specified Hardware Torque     Type Screws Hex Nuts Spacers Spring/Lock Washers Spacers Flat Washers Thread M5 M8 M12 M5 M8 M12 M5 M8 M12 Specified Torques (lb. - ft.)  2  12  40  2  12  40  2  12  40  The following is a list of tools and any additional materials required for mounting every Single-Band Remote Unit configuration:  • DIN male connectors • Tool kit for attaching DIN connectors to coaxial cable • Tools for installing exterior AC circuit • Tools for securing M5 screw
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage24   • Wire cutters • Wire Stripper • Open End Wrench 1.25 inch/33mm (used for DIN connector) • Hex Wrench 5mm (M6 screw) • SAE Wrench 5/16 inch/8mm (the Slave Remote Unit connectors)  4.2.3  Unpacking And Inspection  This section provides the instruction for receiving the equipment shipment, verifying all parts have been received and checking that no damage has occurred during transportation. The Remote Unit includes the following items:  • Remote Unit(s) • Hardware and Fasteners described in Table 4-2, Section 4.2.2  Use the following procedure to unpack and inspect the Remote Unit and accessories:  1.   Open the shipping packet and carefully unpack the Remote Unit(s) and any accessories from the protective packing material.  2.   Verify receipt of hardware and fasteners using Table 4-2  3.   Check each Remote Unit and accessories for broken or missing parts. If there is any damage or missing parts, contact BTI (Section 6) for an RMA and to reorder parts, if any replacement parts are required.  NOTE: Check particularly for any damage to the power connection, the fins/fans, and the fiber optic cable connection on the Remote Unit Interface.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage25   4.2.4  Mechanical Installation  4.2.4.1 Mechanical Safety Precautions Please read the general Safety Precautions contained in Section 1.2 Safety Precautions   1.   Follow the procedures provided by the manufacturer when installing the Remote Unit. Do not install the Unit in a place or in a manner that does not meet the manufacturer's provided specifications.  2.   Use the mounting hardware supplied by the manufacturer. If non-standard mounting hardware is used, it must meet the requirements for mounting the Unit as specified by the manufacturer.  NOTE: It is important that specified load limits for the Unit are not exceeded as this may void the warranty.   3.   Safety measures for lifting heavy materials should be followed to prevent injury.  4.   High temperatures may occur due to power dissipation. Please follow the specifications for proper Remote Unit ventilation as indicated by the manufacturer.  5.   Check that the mains supply is disconnected, before connecting or disconnecting the main power connector at the Remote Unit.  6.   Do not block airflow ventilation outlets during installation or Remote Unit(s) may sustain critical damage.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage26   4.2.4.2 Install The Mounting Panel Use the following procedure to install the mounting panel on the pole:  1.   Take one M12 screw and insert it loosely in one of the two top holes in the panel. Place the mounting panel against the pole as shown in Figure 4-1.  2.   Place one of the two I-Beam or U-Beam brackets on the back side of the pole so that it aligns with the M12 screw.  3.   Hand tighten the screw to hold it in place  4.   Place the second M12 screw in the next hole at the top of the panel and loosely fasten the screw as well. Continue until all four screws are in place as shown in Figure 4-2.  5.   Use a wrench to securely fasten the screws through both panel and brackets until the panel is securely attached to the pole.                     Figure 4-1. Attach the Mounting Panel and Bracket to a Pole
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage27                           Figure 4-2. The Mounting Panel secured tightly to a Pole  4.2.4.3 Install The Remote Unit On The Mounting Panel  Use the following procedure to install the RU on the mounting Panel.  1.  Verify that the attached side mounting brackets, as shown in Figure 4-3 are secure.  2.  Grasp the Remote Unit at the top and bottom of the casing and carefully slide the top two hooks onto the mounting panel, Figure 4-4, followed by the lower hooks and allow the Unit to slide down into place.  3.  After hanging the enclosure on the mounting panel, use the M8 screws, lock and flat washers to secure the rear mounting bracket (top and bottom) so the RU does not move.                    Figure 4-3. The Side Mounting Bracket to the Mounting Panel
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage28      Figure 4-4. Secure Enclosure To the Side Mounting Bracket   4.2.4.4 Install The Shroud Cover The Remote Unit has a Shroud cover for thermal protection.  Use the following procedure to install the Shroud cover on the enclosure:  1.  Line up the slots at the top of the Shroud cover to the tabs at the top of the mounting panel as shown in Figure 4-5.  2.  Gently lower the slots over the tabs and slide the cover down. The cover will be at an angle, Figure 4- 6.  3.  Lay the cover flush against the mounting bracket, then carefully, place the M5 screw through the middle hole, aligning it to the hole on the bracket. Loosely fasten the screw. Working on the opposite side, again place an M5 screw through the middle hole and loosely fasten the screw.  4.  Loosely fasten the remaining M5 screws to all four corners of the cover and then tighten all the screws securely.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage29                       Figure 4-5. Install the Shroud Cover to the RU                               Figure 4-6. Secure Shroud Cover to the mounting panel
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage30    4.2.5  Electrical Installation  4.2.5.1 Electrical Safety Precautions Please read the general Safety Precautions presented in Section 1.2 Safety Precautions  1.   This Unit uses high voltages. Follow the instructions for installation provided in this manual to prevent serious accidents including loss of life, severe personal injury or extensive property damage.  2.   The Unit must be grounded before connecting any power supply. Grounding is a required precautionary measure. Grounding instructions are provided and should be followed for safety.  3.   The Unit is internally protected against over-voltage, but in areas with strong and frequent lightning strikes additional lightning protection is strongly recommended. Grounding the antenna cables close to the antenna connectors will help prevent damage from atmospheric discharge.  4.   Verify that there is a suitable circuit breaker and an over-current limiting device connected between the mains and the Remote Unit.  5.   Check that the mains supply is disconnected, before connecting or disconnecting the main power connector at the Remote Unit.  6.   An easily reached emergency disconnect device should be provided in the mains circuit if the power feeds to the Remote Unit(s) are not within close reach.  7.   The Remote Unit should be installed in close proximity to a power source with a circuit breaker to ensure safe installation and for ease of power connectivity.  8.   Electrical and electronic components can be destroyed by incorrectly wired connections.  9.   Cable connector materials must meet manufacturer specifications to avoid corrosion at the connectors.  10.  Check cable connections to ensure that water cannot penetrate the Unit.  11. Caution should be used when attaching the antenna. Hand tightening should be sufficient for connecting the antenna during installation. Manufacturer's recommendation for torque specification should be used during installtion. Use the appropriate tool to complete the Antenna installation, but do not use tools, such as pliers, as they may cause damage to the Remote Unit.  12. A voltage limiting device is strongly recommended for electrical networks that often produce spikes.  13. Compliance with the surge requirement of EN 61000-4-5 (fine protection) has been met by this Unit. Installing additional external surge protection, depending on the individual application, via local supply connection and/or coarse protection is recommended to avoid damage caused by electrical surges.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage31      4.2.5.2 Grounding  The  Unit  must  be  grounded.  Connect  an  earth-bonding  cable  to  the  provided  grounding connection. Do not connect any additional external devices to the grounding connection.                     Figure 4-7. Grounding Connection  1.  Uncover the RU interface by removing the Vandalism Protective Shield from the bottom of the Shroud Cover.  2.  Loosen the hex nut located on the grounding connection as shown in Figure 4-7.  3.  Connect the earth-bonding cable between the two lock and flat washers.  4.  Tighten the hex nut, making sure the cable is securely connected before moving to the next phase of the installation.   4.2.5.3 Route the Cables Prepare and route all cables according to standard field installation procedures. Care should be taken to prevent wear or field damage to cables during install. Particular attention should be paid to the Fiber Optics Cable as damage may occur if cable is tightly coiled or bent.  4.2.5.4 Fiber Optic Cable Connection One fiber optic cable must be routed from an external splice enclosure or fiber access terminal to the Master Remote Unit enclosure. The RU is equipped so only one cable is required per Master Remote Unit for the optic port. A hardened optical E2000 connector is used for the optic port.   Warning: Do not look into the end of the fiber optic cable. Do not look directly into the optical transmitter of any Unit or exposure to laser radiation may result. An optical power meter should be used to check the active fibers.   Use the following procedure to connect the fiber optic cable:  1.  Connect or splice the drop Fiber cable to the outside plant cable. Verify that there is sufficient cable length to reach from the splice enclosure or fiber access terminal (not provided) to the bottom of the Master Remote Unit
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage32   2.  Route the free end of the drop cable to the enclosure through the junction box as shown in Figure 4-8.  3.  Leave sufficient slack to allow the cable to be connected and disconnected from the enclosure fiber optic port without bending or crimping the fiber optic cable.  4.  Remove the cap from the interface port labeled "FIBER". Connect the fiber optic cable to the port on the bottom of the enclosure.                Figure 4-8. Junction Box   4.2.5.5 Antenna Cable Connection The antenna feed line(s) must be routed from the antenna to each Remote Unit. The cable must have the appropriate antenna connector termination to connect to the RU antenna port (ANT), shown in Figure 4- 9.                    Figure 4-9. Antenna port   Use the following procedure to install the antenna cable:  NOTE: When using multiple RU enclosures to support more than one RF band, each RU is supporting a different frequency. When routing the coaxial antenna cable, it is critical that the appropriate frequency band cable be connected to the same frequency type RU.   1.  Remove the dust cap from the DIN female connector located on the bottom of the enclosure. The port is labeled with “ANT”.  2.  Route the coaxial antenna cables from the antenna to the bottom of the enclosures.  3.  Cut the antenna cable to the required length and terminate with the appropriate connector.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage33   4.  Connect the antenna cable to the antenna port labeled with “ANT”, Figure 4-10.                   Figure 4-10. DIN Female Connector   4.2.5.6 AC Power Cable Connection   Danger: Use extreme caution when working with high voltage AC power. Ensure all power is disconnected before working on power circuit.   Warning: Verify that the Unit has been ground with an earth-bonding cable to the grounding connector.   Use the following procedure to install the AC Power cable:  1.  Route the power cable between the AC power port, located on the bottom of the enclosure and the nearest AC power junction box as shown Figure 4-11.                         Figure 4-11. Junction Box AC Power Cable Routing
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage34   2.  Secure the cable between the AC power port and the AC power junction box. Leave sufficient slack in the cable to allow it to be easily connected and disconnected from the AC power port.  3.  Install any AC power supply wires that may be required between the AC junction box and the AC circuit breaker box.  4.  At the AC circuit breaker box, connect the AC power supply load wire to the circuit breaker.  5.  Place the circuit breaker in the ON position and then test the connected end of the AC power cable for proper voltage levels and correct polarity.  6.  When testing is complete,   PLACE THE CIRCUIT BREAKER IN THE OFF POSITION.  Danger: To avoid serious personal injury and equipment damage, always turn the AC power off on the circuit breaker before connecting the any power cable to the AC power port.   7.  Connect the power cable connector to the AC power port labeled “POWER”.  8.  Tighten the coupling nut.   4.2.5.7 Slave Cable Connection When two RU or more enclosures are installed for supporting multi-band. One is designated the Master Remote Unit and each additional RU, up to two Units, are designated as slave Remote Units. The Master and slave Unit(s) is specified by the frequency band. The Master Unit will separate the bi-directional signal  related  to  the  frequency  and  provide  the  RF  input  signal  to  each  slave  Remote  Unit.  The connection between Master and Slave is interfaced with the RF cable provided with the Remote Units.  Use the following procedure to install the antenna cable:  1.   All designated slave RUs arrive with two RF cables.  2.   Connect one RF cable to the port labeled “TX_OUT” on the MASTER Remote Unit User Interface.  3.   Connect the other end of the RF cable to the port labeled “TX_IN” on the SLAVE Remote Unit User Interface as shown in Figure 4-12.  4.   Connect the second cable to the port labeled "RX_IN" on the MASTER RU.  5.   Connect the other end of the second RF cable to the port labeled "RX_OUT on the SLAVE RU.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage35                         Figure 4-12. RF cable connection between Master and Slave Remote Unit   1  Slave to Slave Connection: Connect an RF cable into the port labeled "TX_OUT" on the first SLAVE RU User interface.  2  Connect the other end of the RF cable to the port labeled "TX_IN" on the next SLAVE  RU Unit. Continue connecting all SLAVE RUs in this manner, as shown in Figure 4-13.  3  Connect an RF cable into the port labeled "RX_OUT" on the first SLAVE RU.  4  Connect the other end of the RF cable to the port labeled "RX_IN" on the next SLAVE RU. Continue connecting all SLAVE RUs in this manner.  5  Power may now be applied to all Master and Slave Units used in this configuration.                     Figure 4-13. RF cable connection between Slave to Slave Remote Units
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage36   LED Indicator Colors Cycles Test the LED Red and Green Blink 1 flash per second Master RU Fiber Alarm Red Fast Blink 2 times per second mRU and sRU Comm Fail Red and Green Blink 1 time per second PA/LNA shutdown or Other Red Fast Blink 2 times per second Normal Operation Green Blink 1 times per second 4.2.6  Remote Unit Installation Review  Use the following steps listed in Tables 4-3 and 4-4 to review the installation completion status  4.2.6.1 Mechanical Installation Review  Table 4-4. Remote Unit Mechanical Installation Check Lists Items Description  1  Confirm that the Unit is mounted firmly and is stable. 2  Verify that the Unit is affixed per manufacturer's specifications.  3  Check that all screws and nuts are secure, that spring washers sit flush upon the flat washers, and that there are no missing flat washers and spring washers.  4  Examine each part and cable for breakage or damage. 5  Make sure the Unit is clean and free of dust and other contaminants   4.2.6.2 Electrical Installation Review  Table 4-5. Remote Unit Electrical Installation Check List Items Description  1  Verify that the grounding cable is secure. 2  Make sure that all the cable sheathings are not damaged. 3  Confirm that the connection to the cables are stable and are not loose or damaged. Check that the cables are completely connected, but make sure there is enough slack, if 4  needed. Do not cross the cables and the cables should be bundled together in the same direction.  5  Check that the connected cables are not bent more than the manufacturer's specified maximum bending radius.   4.2.6.3 Field Status Test - Remote Unit LED Status Indicators Perform a visual review of the LED Status indicators on the installed Remote Unit. The Remote Unit (RU) status LED consists of a bi-colored LED of RED and GREEN. The high intensity LED is viewable from ground level under most circumstances when using the BTI RU shroud system.  Table 4-6. Remote Unit LED Status Indicators
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage37   4.2.7  Troubleshooting
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage38    4.3  HOST UNIT INSTALLATION   Danger: Wet conditions increase the potential for receiving an electrical shock when installing or using electrical power equipment. To avoid electrical shock, never install or use the electrical equipment in a wet location.  Warning: Verify that the Unit has been ground with an earth-bonding cable to the grounding connector.    4.3.1  Host Unit Installation Overview  The installation of the Host Unit consists of the following steps:  Table 4-6. Host Unit Installation Overview Step Operation Type Operation Action 1 ELECTRICAL VERIFY THAT THE UNIT IS GROUNDED  2 ELECTRICAL  CONFIRM THAT THE DC POWER CABLE IS INSTALLED AND SECURE  3 ELECTRICAL  INSTALL THE BIU AND FIU MODULES 4 ELECTRICAL  INSTALL THE ALARM CONNECTORS (Optional) 5 ELECTRICAL  CONNECT THE BIU AND FIU   6  ELECTRICAL CONFIRM THAT THE POI AND FAN (Opt. Equip.) ARE CONNECTED 7 ELECTRICAL CONNECT OPTIONAL EQUIPMENT TO THE BIU (if present) 8 ELECTRICAL CONNECT THE FIBER OPTIC CABLES 9  INSTALLATION REVIEW CONFIRM THE ELECTRICAL INSTALLATION, TABLE 4-10 HOST UNIT ELECTRICAL INSTALLATION CHECKLIST 10 TROUBLESHOOTING INSTALLATION TROUBLESHOOTING GUIDE  4.3.2  Installation Hardware And Tools  The Host Units may be shipped individually or shipped factory pre-installed in optional cabinets. Table 4-7 lists  the  cables  and  hardware  provided  by  the  manufacturer.  Additional  hardware  may  be  needed, depending on the site requirements, and may be ordered through Customer Service (Section 6).  Table 4-7. Host Unit Cables and Hardware Single Host Unit Hardware and Fasteners  Customer Install  Factory Install  Rec'd 1    1  CABINET (Optional) HU DC POWER CABLE ALARM CONNECTORS 8   3    4    FIU-S INTERFACE CABLE FIU-NS INTERFACE CABLE GROUNDING CABLES  1  POI GROUNDING CABLE (Optional)   1
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage39    Single Host Unit Hardware and Fasteners  Customer Install  Factory Install  Rec'd POI INTERFACE CABLE 4    The following is a list of tools and any additional materials required for the Host Unit installation:  • Small Phillips screwdriver • Wire cutters • Wire Harness (Required for Expanded Third Party Alarm)  4.3.3  Unpacking And Inspection  This section provides the instruction for receiving the equipment shipment, verifying all parts have been received and checking that no damage has occurred during transportation. The Host Unit includes the following items:  • Optional Cabinet with Host Unit installed as shown in Figure 4-14. • Hardware and Fasteners described in Table 4-7, Section 4.3.2                               Figure 4-14. Host Unit Cabinet   Use the following procedure to unpack and inspect the Host Unit and accessories:  1.   Open the shipping packet and carefully unpack the cabinet or individual Host Unit from the protective packing material.  2.   Verify receipt of hardware and fasteners using Table 4-7  3.   Check each optional cabinet for broken or missing parts. Check each Host Unit module for any damage, particularly the Fiber Optic Port. If there is any damage or missing parts, contact BTI (Section 6) for an RMA and to reorder parts, if any replacement parts are required.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage40   NOTE: Check particularly for any damage to the fiber optic connectors on the FIU module. Check the power connectors located at the back of the Host Unit and check the back plane connectors located inside the Host Unit for any damage.  .   4.3.4  Electrical Installation  4.3.4.1 Electrical Safety Precautions Please read the general Safety Precautions presented in Section 1.2 Safety Precautions  1.  Follow the instructions for installation provided in this manual to prevent serious accidents including loss of life, severe personal injury or extensive property damage.  2.   The Unit must be grounded before connecting any power supply. Grounding is a required precautionary measure. Grounding instructions are provided and should be followed for safety.  3.  Electrical and electronic components can be destroyed by incorrectly wired connections.  4.  Cable connector materials must meet manufacturer specifications to avoid corrosion at the connectors.  5.  Compliance with the surge requirement of EN 61000-4-5 (fine protection) has been met by this Unit. Installing additional external surge protection, depending on the individual application, via local supply connection and/or coarse protection is recommended to avoid damage caused by electrical surges.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage41   4.3.4.2 Grounding  The Unit must be grounded. The Host Unit is grounded during a factory installation in the optional cabinet with an earth-bonding cable connected to the provided grounding connection. Do not connect external devices to the grounding connection.  Please verify the Unit is securely grounded. If it is no longer securely grounded, please use the following procedure to ground the Unit:                      Figure 4-15. Host Unit Grounding Connection  1.  Find the screw at the bottom right corner of the Host Unit as shown in Figure 4-15.  2.  Loosen the screw located on the grounding connection.  3.  Connect the cabinet mounted earth-bonding cable between the two lock and flat washers as shown in Figure  4-16.  Ensure  the  grounding  surface  is  clean  and  free  of  paint,  insulating  material  or contaminants.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage42                                 Figure 4-16. Grounded Host Unit (shown with optional POI Unit, also grounded)  4.  Tighten the screw, making sure the cable is securely connected before moving to the next phase of the installation.   4.3.4.3 DC Power Cable Connection   Danger: Please use caution when working with DC power. Ensure all power is disconnected before working on power circuit.   Warning: Verify that the Unit has been ground with an earth-bonding cable to the grounding connector.   The DC power cable is connected during factory pre-installation.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage43                  Figure 4-17. Factory Installed DC Power Cable   1.  Confirm electrical polarity of the power cables to match the customer provided DC power system.  2.  Verify the DC power cable is attached securely, as shown Figure 4-17.  3.  If the DC power cable is not secure, turn off all associated DC power to the Host Unit, and secure the power cables as shown.   4.3.4.4 Install the BIU and FIU modules              Figure 4-18. BIU and FIU modules   1.  Remove the blank module covers for the chosen module slot locations.  2.  Slide the BIU and FIU modules in to each separate designated module slot, Figure 4-18.  3.  Secure the screws at the top and bottom of each module.   4.3.4.5 Alarm Installation The Alarm interface is an optional customer centered configuration.  The Alarm Input configuration gives the user the means to monitor third party alarms, such as battery or intrusion alarms.  The Alarm Output configuration provides the customer with the means to monitor major or minor alarms via Form C relay.  The alarm interface is located at the back of the Host Unit as shown in Figure 4-19.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage44                                   Figure 4-19. Alarm Interface  1.  With wire cutting tools, prepare the connecting wires.  2.  Loosen the screws in each connector.  3.  Use the Input Alarm configurations shown in Table 4-8 and the Output Alarm configurations in Table 4- 9 to determine the wire placement.  4.  Slide the bared wires into the slot under the screw and tighten securely.  5.  Plug all the alarm connectors into the Alarm Input interface as shown in Figure 4-20 and Figure 4-21.   Table 4-8. Input Alarm Configuration NMS Alarm Status Alarm No Alarm Expanded Alarm 1 (User Defined) IN1/GND IN1 Expanded Alarm 2 (User Defined) IN2/GND IN2 Expanded Alarm 3 (User Defined) IN3/GND IN3 Expanded Alarm 4 (User Defined) IN4/GND IN4
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage45      Figure 4-20. Input Alarm Installation (Alarm On)   Table 4-9. Output Alarm Configuration Alarm Type On Off Major COM1/NC1 COM1/NO1 Minor COM2/NC2 COM2/NO2     Figure 4-21. Output Alarm Installation (Alarm On)   4.3.4.6 Connect the BIU/FIU Modules Connect the BIU to the FIU-S with the provided interface cable using the following procedure:  1.  Connect one end of the interface cable to the BIU port labeled "Tx1 Out".  2.  Connect the other end of the cable to the FIU-S port labeled "Tx1".  3.  Connect a second interface cable to the BIU port labeled "Rx4".
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage45   4.  Connect the other end of the cable to the FIU port labeled "Rx1", Figure 4-22.                 Figure 4-22. Connect the BIU to the FIU   For a two BIU and FIU-NS configuration, use the additional provided interface cables and the following procedure:  5.  Connect the one end of the interface cable to the FIU-NS port labeled "Tx1".  6.  Connect the end of the second interface cable to the FIU-NS port labeled "Tx2".  1.  Connect one end of the interface cable to the BIU port labeled "Tx1 Out".  2.  Connect the end of the second interface cable to the port labeled "Tx1 Out" of the second BIU.  3.  Connect the end of the third interface cable to the FIU-NS port labeled "Rx1".  4.  Connect the other end of the fourth interface cable to the FIU-NS port labeled "Rx2"  5.  Connect the third interface cable to the BIU port labeled "Rx4".  6.  Connect the fourth interface cable to "Rx4" of the second BIU.   4.3.4.7 Optional Equipment Installation The POI and Fan, (if ordered) are factory installed. Please verify the POI and Fan are securely connected as shown in Figure 4-23.                     Figure 4-23 POI and FAN Installation
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage46    4.3.4.8 Connect POI to BIU The Point of Interface (POI) is an optional component. The POI is connected to the BIU using the following procedure:  1.  Connect one end of a POI interface cable into the BIU port labeled "Tx1 In".  2.  Connect the other end of the cable to the POI port labeled "Tx-L".  3.  Connect the one end of a POI interface cable into the BIU port labeled "Rx4 Out".  4.  Finally, connect the other end of the cable to the POI port labeled "Rx-L".                    Figure 4-24. POI to BIU Connection   4.3.4.9 Connect the Fiber Optic Cable The Fiber optic cable is connected to the FIU module by attaching the cable to the port labeled "Fiber-1" as shown in Figure 4-25.                   Figure 4-25. Fiber Optic Cable Connection to the FIU Module   4.3.5  Host Unit Installation Review  4.3.5.1 Electrical Installation Review
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage47   Table 4-10. Host Unit Electrical Installation Check List Items Description  1  Verify that the grounding cable is secure.  2  Confirm that the power cable connection is stable and is neither loose or damaged and that the electrical polarity is correct.  3  Verify that the fiber optic cable is securely connected. 4  Check that all installed cables are securely connected. 5  Confirm that the alarm connectors are securely connected.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage48   4.3.6  Troubleshooting
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage49    4.4 NMS INSTALLATION   Caution: Network security may be compromised when accessing external Internet connectivity. The use of established security software is recommended.   The NMS software is pre-installed on the Network Management Server and the NMS server arrives pre- installed in the optional Host Unit cabinet. This section provides instruction for installing the NMS software on a customer laptop or desktop and setting initial software parameters.          Figure 4-26. NMS Server   4.4.1  Installation Overview  The installation of the Network Management System consists of the following steps:  Table 4-11. NMS Installation Overview Step Operation Type Operation Action 1 SYSTEM SET-UP VERIFY SERVER SOFTWARE IS OPERATIONAL  2 SYSTEM SET-UP  INSTALL SYSTEM SOFTWARE ON TO CUSTOMER MONITORING EQUIPMENT  3 SYSTEM SET-UP  LAUNCH NMS SOFTWARE 4 CONFIGURE  CONFIGURE MANAGER ACCOUNT 5 CONFIGURE  SET-UP USER ACCOUNTS 6 CONFIGURE  SOFTWARE SYSTEM PARAMETERS 7 UPDATE/UPGRADE SOFTWARE/FIRMWARE UPGRADE INSTALL INITIAL SOFTWARE 8 INSTALLATION REVIEW UPGRADE 9 INSTALLATION REVIEW CONFIRM SOFTWARE SET-UP INSTALLATION, TABLE 4-13 NMS INITIAL SOFTWARE INSTALLATION CHECKLIST   CONFIRM FIRMWARE UPDATE AND SOFTWARE UPGRADE INSTALLATION, TABLE 4-14 NMS UPGRADE SOFTWARE INSTALLATION CHECKLIST 10 TROUBLESHOOTING INSTALLATION TROUBLESHOOTING GUIDE  4.4.2  Installation Hardware and Tools  The NMS server is shipped pre-installed in the optional Host Unit cabinet. Table 4-12 lists the accessories provided   by   the   manufacturer.  Additional  accessories   may  be   needed,  depending  on   the  site requirements, and may be ordered through Customer Service (Section 6).     Table 4-12. NMS Cables and Accessories     NMS ACCESSORY Quantity Received SOFTWARE CD-ROM 1
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage50    NMS ACCESSORY Quantity Received AC POWER CABLE 1   The following is a list of tools and any additional materials required for NMS software installation:  • Laptop, Desktop PC and/or Terminal • Crossover Cable • Hub and/or Router  4.4.3  Unpacking And Inspection  This section provides the instructions for receiving the equipment shipment and verifying that no damage has occurred during shipping. The NMS software is pre-installed on the server which is shipped with the following:  • Optional cabinet with NMS server and Host Unit installed as shown in Figure 4-27. • Installation cables and accessories as described in Table 4-12, Section 4.4.2. Use the following procedure to unpack and inspect the NMS server and accessories: 1.   Open the shipping packet and carefully unpack the cabinet from the protective packing material.  2.   Verify receipt of accessories using Table 4-12  3.   Check the server for visual damage. If there is any damage, contact BTI (Section 6) for further instructions including an RMA, if necessary.                                Figure 4-27. NMS Server  4.4.4  Verify Server software
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage51   1.  Connect the laptop, PC or terminal to the server through the hub using a crossover cable, Figure 4- 28. The monitoring device may also be plugged directly into the server with a crossover cable.                       Figure 4-28. Connecting the Monitoring Device to the Server   2.  Locate the NMS icon on the screen of the monitoring device, Figure 4-29.             Figure 4-29. Locate NMS Icon   4.4.5  Initial System Setup  4.4.5.1 CD-ROM Install The CD-ROM install is used to install NMS on to a Laptop or Desktop Computer. Use the following procedure to install the application on to the computer:  1.  Open the CD drive on the machine.  2.  Place the CD into the drive and close the drive.  3.  The CD will begin the install wizard, Figure 4-30.  4.  The wizard copies the files to the %ProgramFiles% folder. The default destination directory may be changed, if desired.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage52                         Figure 4-30. DAS Setup Wizard   4.4.5.2 Launch NMS 1.  After copying the files, the Wizard will ask to launch NMS, Figure 4-31.  2.  Select Yes.  3.  The Wizard simultaneously places a shortcut on to the desktop of the computer as shown in Figure 4-                         32. Double clicking on the NMS icon on the desktop also launches the NMS Login screen.  Figure 4-31. NMS Launch from Wizard Installation
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage53                  Figure 4-32. NMS Desktop Shortcut   NOTE: Occasionally, there are compatibility problems that cause a configuration conflict when setting up the NMS. Follow the steps shown in the Troubleshooting Guide. If this does not resolve the issue, contact Customer Service (Section 6).   4.  Verify that the Advance box is checked and then click in the password field, Figure 4-33.  5.  Enter the following default password: 1  6.  Click on OK. The NMS Command Console is then launched.                         Figure 4-33. NMS Login Screen   4.4.6  Initial Start-up Configuration  Once NMS is installed on the machine, the command console or main screen is used to navigate through various NMS menus to configure both the software system parameters and the DAS system parameters. This section covers the software system parameters needed to set-up an initial install.  Main access to the NMS software configuration is through the System(S) drop down on the Menu bar as shown in Figure 4-34. User accounts may also be accessed through the User Icon on the Command toolbar as shown in Figure 4-35. The software system configuration includes the ability to access the
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage54   following functions: • Access and manage User Accounts and passwords (Add/Modify/Delete) • Modify parameter defaults.                              Figure 4-34. System (S) Drop Down Menu
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage55                                    Figure 4-35. User Account Icon   4.4.6.1 Modify Default Accounts The NMS User Manager comes with two default entries shown in the User list. For security reasons, changing the default manager account and password is highly recommended. The default User account may also be modified by overwriting the default information. The following procedure details the steps necessary to change the default accounts:  1.  Using either the System(S), Figure 4-34 or the User icon, Figure 4-35, access the User Manager screen, Figure 4-36.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage56                                    Figure 4-36. User Manager Screen   2.  Select Manager in the User List, Figure 4-37 to see the default information.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage57                                    Figure 4-37. Manager Default Information  3.  Delete the default entries, Figure 4-38 and enter the new user name and password.  Note: There is a limit of 20 Alpha-Numeric characters for both User name and password entries. User names are selectable from the Login screen drop down menu, once entered into the system. Passwords are case sensitive.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage58                                       Figure 4-38. Edit Default Entries  4.  Click Modify to update the User and Password.  5.  Click Return to return to the NMS Command Console or continue to add or update User Accounts.   4.4.6.2 Set-up New User Accounts Adding a New User is easily managed through the User Manager screen. Access the User Manager screen, then use the following procedure to add Users of various levels:  1.  Currently, there are two levels available for User Accounts. Once the User Manager screen is up, select the User level, as shown in Figure 4-39.  • Supervisor: This level acts as an administrator for the Network System. This level can make edits and set custom features. • Observer: This level is a monitoring functionality only. This level is most commonly used for users who will monitor the system and review alarm logs. At the Observer level, a user may only: modify their user name and password and; view, save and print Alarm information.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage59                                    Figure 4-39. Select a User Level   2.  Enter a user name and password, Figure 4-40. Then click Add.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage60                                   Figure 4-40. Enter User name and Password    Note: There is a limit of 20 Alpha-Numeric characters for both User name and          password entries. User names are selectable from the Login screen drop down menu, once entered into the system. Passwords are case sensitive.   3.  Additional detailed information for managing User accounts, including deleting and modifying User accounts is contained in the NMS User Manual.   4.4.6.3 Configure Software Parameters The NMS system software parameter defaults allow the user to focus less on configuring the software system , Figure 4-41, and more on the critical functionality for the DAS system.  Detailed parameter information is available in the NMS User Manual.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage61                                          Figure 4-41. System Parameter Screen   4.4.7  Firmware Update  DAS components periodically require firmware updates. The following list of components may require periodic firmware updates: • BIU • FIU • PA • RCU • Remote Unit  A notification email is sent with the firmware update attached as a file to the email. The following procedures detail the firmware update process:  1.  Verify the email is genuine and the file attachment is safe for download. The sent file will be named in the following manner and have a file extension of .s:  DAS8345_[Component]_[Version].s  2.  Download the attached file to any chosen folder or the desktop. Note the folder name, if saved to a designated folder.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage62   3.  Log into the NMS System.  4.  Click on NetConfig  5.  Using the RemoteSoftwareDownload interface, Figure 4-42, Locate the file by clicking on the browse button.                                      Figure 4-42. Remote Software Download Screen   6.  Click Start Download. The firmware update may be paused if needed by clicking the Pause button.  7.  Once the download is complete, click Return.   4.4.8  Software Upgrade Installation  4.4.8.1 CD-ROM Install The CD-ROM Upgrade install is a quick and simple installation. Use the following procedure to install the application on to the computer:  1.  Check that no instance of NMS is running.  2.  Open the CD drive on the machine.  3.  Place the CD into the drive and close the drive.  4.  The CD will begin the install wizard and ask if the user would like to overwrite the older NMS version, Figure 4-43.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage63   5.  Select Yes.                         Figure 4-43. Replace NMS File  5.  An error dialog box will appear, Figure 4-44, if the older version of NMS is open and running.  6.  Close NMS and click Try Again.                               Figure 4-44. NMS Update Fail Error Box   4.4.9  NMS Upgrade Installation Review
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage64   Table 4-13. NMS Initial Installation Checklist Items Description  1  Verify that the CD is undamaged and the server software is installed. 2  Confirm that the version number once the set-up Wizard launches NMS. 3  Verify that the shortcut launches the NMS Login. 4  Check that the default Manager Account and password have been updated. 5  Confirm that new User accounts and passwords have been added.   Table 4-14. NMS Firmware Update and Software Upgrade Checklist Items Description  1  Verify that the email and attachment. are genuine.  2  Confirm that the firmware update is downloaded to the appropriate folder on the computer.  3  Verify that firmware update was complete from the RemoteSoftwareDownload interface. 4  Confirm that no instance of NMS is running before beginning Upgrade installation. 5  Check the version number to verify upgrade once the set-up Wizard has launched NMS.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage65   4.4.10  Troubleshooting
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage66   5 mBSC DAS SYSTEM START-UP  When the system component installations are complete, the system must be configured. Please refer to the applicable System Operation and User Manual for detailed system configurations, operations, and troubleshooting/test procedures  5.1 SYSTEM COMMUNICATION  Once   the   components   have   been   installed,   the   system   should   be   activated   by   establishing communication through the Host Unit and configuring the system to the network through the NMS.  5.1.1  Establishing a Host Unit communication  The Host Unit hardware default IP address must be updated with the customer's network IP address. This is  accomplished  by  first  establishing  a  communication  link,  setting  up  the  initial  base  system  and configuring the IP Address parameter. Use the following procedure to establish communication with the Host Unit :  1.  Connect the NMS installed Laptop ethernet port to the RCU front ethernet port with a cross or null modem cable.  2.  From the Laptop, click the Start Button, then Settings and Network Connections, Figure 5-1.                   Figure 5-1. Open Network Connections   3.  Select the LAN Icon and click on File then Properties, Figure 5-2.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage67                           Figure 5-2. LAN Properties   4.  Click on Internet Version Protocol (TCP/IPv4) and then click on Properties, Figure 5-3.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage68                                         Figure 5-3. Select Internet Protocol Version 4  5.  Click on the second option, Use the Following IP Address:,  Figure 5-4, and manually enter the IP Address: 128.0.2.30. The Subnet mask will automatically default to 255.255.0.0.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage69                                   6.  Click OK. Figure 5-4. Manually Enter the IP Address  5.2 INITIAL NETWORK CONFIGURATION  This section details the initial functions necessary for a basic system activation through the NMS. Access to the DAS system configuration is through the Network(N)  menu bar drop-down or the Net Config Command bar button, Figure 5-5. The DAS Network(N)  drop-down includes the ability to access the following functions: • Add/Modify/Delete Sites • Add/Modify/Delete the Host Unit(s) • Add/Modify/Delete the Remote Unit(s)
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage70                                     Figure 5-5. Accessing the Network Configuration screen   The NMS software provides an example configuration as shown in Figures 5-5 and 5-6. The example may be deleted or the example information may be overwritten with customer specific information and then saved by clicking the Modify  button. For the purposes of this installation manual, the example has been deleted to provide the most accurate details.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage71                                       Figure 5-6. BTI Example System Configuration   5.2.1  Add a Site  The highest level of system configuration is defined by adding a Site Caption and a Site Code. The alpha- numeric text fields accept any user-defined descriptive name (30 alpha-numeric character limit) and site code (1 through 9999 numeric limit). The following steps are used to add the Site Caption and Site code:  1.  Access  the  Network  Config  screen,  Figure  5-5,  via  the  NetConfig  Command  bar  button  or  the Network(N) menu drop-down.  2.  Click on the Site button in the Select Information field, Figure 5-7.  3.  Enter the Site name and the Site code. The example, BTI_Example_Cypress_Site is shown in Figure 5-8.  4.  Click Add to save the Site Caption and Site Code.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage72                                 Figure 5-7. Add a Site
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage73                                      Figure 5-8 Adding a Site   5.2.2  Add a Host Unit  Once the Site Caption and Site Code have been configured, the Host Unit should be added to the system. The alpha-numeric text fields accept any user-defined descriptive HU Caption (20 alpha-numeric character limit) and HU No. (1 through 9999 numeric limit). The following steps provide the Host Unit configuration:  1.  Click on Equipment to bring up the new information section for the DAS System equipment.  2.  Click on HU in the Select Equipment section. Verify that the Site Caption and Site Code are correct for the Host Unit being added.  3.  Add the customer designated Host Unit Caption and Host Unit No. as shown in Figure 5-9.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage74                                      Figure 5-9. Adding a Host Unit  4.  Verify that all changes have been correctly entered and click Add, Figure 5-10.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage75                                      Figure 5-10. Configured Host Unit   5.2.3  Configuring the Host Unit Hardware Card  Once the Host Unit has been added to the system, the IP address for the Host Unit must be changed from the default to the designated network IP address in the Host Unit Hardware Card. Configuring the IP Address is done from the Main Command Screen. The following procedures outline the steps necessary to change the Host Unit IP Address:  1.  From the Main Command Screen, Select the added HU.  2.  Select the RCU Module, Figure 5-11.  3.  Select Config.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage76                                     Figure 5-11. Select the HU   4.  Click on Parameter List. Then click Select All.  5.  Click on Read, Figure 5-12.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage77                                     Figure 5-12. View the Current Values   6.  Confirm Select All is unchecked. Click on Site IP Address in the Parameter List.  7.  Click Edit.  8.  Enter the new IP Address in the Edit Value Column, Figure 5-13.  9.  Click Set, Figure 5-14.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage78                                    Figure 5-13. Enter the New IP Address
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage79                                    Figure 5-14. IP Address Update Setting   5.2.4  Map the IP Address to the NMS Software  1.  Click the Netconfig button.  2.  Select the Host Unit. Figure 5-15.  3.  Change the IP Address(HU) from the default value to the designated network IP address. This will map the IP Address in the NMS System to the HU hardware card.  4.  Then Click Modify. Click Return  5.  Restart NMS to set the new parameters.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage80                                       Figure 5-15. Modify IP Address(HU)   From the Main Command Screen:  1.  Select the updated Host Unit.  2.  Click on Parameter List. Then click Select All.  3.  Click on Read, Figure 5-16.  4.  Confirm that the HU Hardware Card IP Address matches.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage81                                    Figure 5-16. Confirm IP Address Update Accepted.   5.2.5  Add a Master Remote  Once the Site Caption, Site Code, and Host Unit have been configured, the Master Remote Unit should be added to the system. The alpha-numeric text fields accept any user-defined descriptive RU Caption (20 alpha-numeric character limit) and RU No. (1 through 9999 numeric limit). The following steps provide the Remote Unit configuration:  1.  Click on the new HU in the System Net section.  2.  Click on Equipment to bring up the new information section for the DAS System equipment.  3.  Click on RU in the Select Equipment section.  4.  Select the Slot No. for the Master Remote Unit. (This is generally Slot 2).  5.  Select the Fiber value.  6.  Select the Type of Remote Unit.  7.  NMS creates a default name based on the chosen slot, fiber and type values selected as shown in Figure 5-17. Modify the Remote Unit Caption with a customer designated name, if desired.  8.  Verify that the Site Caption, Site Code and HU No. are correct for the Remote Unit being added  9.  Click Add.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage82                                       Figure 5-17 Adding Master Remote Unit   5.2.6  Add a Slave Remote  To complete the system activation, Slave Remote Units should be added to the system. The alpha- numeric text fields accept any user-defined descriptive RU Caption (20 alpha-numeric character limit) and RU No. (1 through 9999 numeric limit). The following steps provide the Remote Unit configuration:  7.  Click on the new HU in the System Net section.  8.  Click on Equipment to bring up the new information section for the DAS System equipment.  9.  Click on RU in the Select Equipment section.  10.Select the Slot No. for the Slave Remote Unit. (This should match the Master RU configuration).  11.Select the Fiber value.  12.Select the Type of Remote Unit.  13.NMS creates a default name based on the chosen slot, fiber and type values selected as shown in Figure 5-18. Modify the Remote Unit Caption with a customer designated name, if desired.  14.Verify that the Site Caption, Site Code and HU No. are correct for the Remote Unit being added.  15.Click Add.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage83                                      Figure 5-18. Adding a Slave Remote Unit     Table 5-2. Slots, Fiber and Type Values     Name Configuration Value Slot Represents the slots on the HU from Left to Right that can be assigned to various equipment. Slots 1-6 are reserved for the FIU and BIU. Designating a slot number maps the RU to an FIU. Fiber Maps the RU to the Fiber connection on the Host Unit to the associated FIU. Type Defines the frequency used and must match the RU type installed. There are currently four different types of Remote Units. 700 MHz, 850 MHz, 1900 MHz, and 2100 MHz.   5.2.7  Connect Host Unit to Server  With  the  IP  address  updated,  the  Host  Unit  must  be  connected  the  server,  Figure  5-19,  for communication information to function. The Host Unit is connected from the Network port on the back interface through the hub to the server as shown in Figure 5-20 or may be directly connected from the back interface port to the server. The Host Unit may also be connected to the server from the RCU network port on the front interface, either directly or through the hub to the server. Only one network port connection may be used at a time.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage84                       Figure 19. Connect Host Unit to Server   Only one port may be connected to the server at a time, as both front interface and back interface network ports are the same port.                    Figure 5-20. HU Back Interface Network Connection   5.3 MANAGING AND MONITORING ALARMS  5.3.1  Alarm Manager  The  NMS  is  also  the  means  for  managing  and  monitoring  the  DAS  systems  through  the  Alarm Manager(A) menu or the Alarm Icon on the Menu bar. The managing and monitoring of the DAS system is more completely detailed in the BTI NMS User Manual.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage85                                     Figure 5-21. Alarm Manager   5.3.2  Configuring Standard Alarm Defaults  Configuring NMS is easily accomplished through the Custom Alarm tab, Figure 5-21. Select the alarm type and click the Select button for the appropriate category. Table 5-3 provides a recommended list of alarms by category that may be selected to create a custom alarm configuration.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage86                                          Figure 5-22. Configuring Custom Alarm Levels   Figure 5-23 shows an active alarm.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage87   Alarm Indicator Description Category Component Downlink OverPower Transmit Power exceeds rated output Critical PA Downlink VSWR Antenna system VSWR exceeds preset level Critical PA Downlink OverVoltage PA Power supply over voltage Critical PA Downlink DeviceFail Downlink system critical failure Critical PA Downlink LoopFail Downlink MCPA IM cancellation not functioning Critical Fiber Module PA Downlink MCPA is operating at an unsafe Critical Fiber Module PA                                        Figure 5-23. Active Alarm Screen   The Table5-3  provides alarm indicator descriptions for the mBSC DAS system. Alarm types for the Host Unit and Remote Unit monitored by the NMS are included as well as optional components such as the POI. The recommended category for the alarm indicator is included in column 3 of the table along with the affected component. Critical alarms indicate system failures that disable the uplink or downlink operation. Other categories, such as Major, may indicate impaired performance, but not the catastrophic system failure or a specific RU node failure.  Table 5-3. Host Unit Alarm Indicators
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage88    Alarm Indicator Description Category Component OverTemperature temperature   Fiber Light Rx RU fiber RX failure Critical Remote Unit Fiber Light Tx RU fiber TX failure Critical Remote Unit mRU and sRU1(LTE) comm Master to Slave communications failed Critical Remote Unit mRU and sRU2(AWS) comm Master to Slave communications failed Critical Remote Unit mRU and sRU2(Cell) comm Master to Slave communications failed Critical Remote Unit mRU and sRU2(PCS) comm Master to Slave communications failed Critical Remote Unit RU Fan1 RU Fan failure Major Remote Unit RU Fan2 RU Fan failure Major Remote Unit LNA RU Receive LNA failure Critical Remote Unit RU/PA communication RU Internal PA to CPU comm failure Major Remote Unit  Uplink Pilot Power  Uplink Pilot Power Failure  Minor  Remote Unit  RCU No Communication  NMS to RCU comm failure  Major  Host Unit  FIU No Communication  FIU to RCU comm failure  Major  Host Unit  BIU No Communication  BIU to RCU comm failure  Major  Host Unit  Fiber1 Light RX  FIU Fiber1 port RX light fail  Critical  Host Unit FIU  Fiber1 Light TX  FIU Fiber1 port TX light fail  Critical  Host Unit FIU  Fiber2 Light RX  FIU Fiber2 port RX light fail  Critical  Host Unit FIU  Fiber2 Light TX  FIU Fiber2 port TX light fail  Critical  Host Unit FIU  RCU +5V  Host Unit RCU power supply alarm  Major  Host Unit RCU  RCU +9V  Host Unit RCU power supply alarm  Major  Host Unit RCU  POI Fan1  POI Fan1 failure  Major  Host Unit POI  POI Fan2  POI Fan2 failure  Major  Host Unit POI  Expanded Alarm Input 1  Expansion  User Defined  Third Party Component  Expanded Alarm Input 2  Expansion  User Defined  Third Party Component  Expanded Alarm Input 3  Expansion  User Defined  Third Party Component
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage89    Alarm Indicator Description Category Component  Expanded Alarm Input 4  Expansion  User Defined  Third Party Component   5.3.3  System Activation Review    Items Description Table 5-4. System Start-up Review  1  Verify that the Host Unit communication was established. 2  Confirm that at least one Site has been added. 3  Verify that the Host Unit Hardware card IP address has been configured. 4  Check that the Remote Unit is communicating with the Host Unit 5  Confirm that the Host Unit is connected to the Server.
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage90   5.3.4  Troubleshooting
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage91   6   CUSTOMER SERVICE CONTACT INFORMATION    USA                BTI 6185 Phyllis Dr. Unit D. Cypress, CA 90630, USA Tel: +1 714-230-8333 Fax: +1 714-230-8341 E-mail: Customer Service: CustomerService@bravotechinc.com Sales: sales@bravotechinc.com     China
mBSC DAS SystemInstallation Manual Issue 3©2009‐2011,BTIPage92    This device complies with part 15 of the FCC Rules. Operation is subject to the  following two conditions:      (1) This device may not cause harmful interference, and      (2) this device must accept any interference received, including interference that may  cause undesired operation    Changes or modifications not expressly approved by the party responsible for  compliance could void the user's authority to operate the equipment.  NOTE: This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to Part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference in a residential installation. This  equipment generates, uses and can radiate radio frequency energy and, if not installed  and used in accordance with the instructions, may cause harmful interference to radio  communications. However, there is no guarantee that interference will not occur in a  particular installation. If this equipment does cause harmful interference to radio or  television reception, which can be determined by turning the equipment off and on, the  user is encouraged to try to correct the interference by one or more of the following  measures:    -- Reorient or relocate the receiving antenna.      -- Increase the separation between the equipment and receiver.       -- Connect the equipment into an outlet on a circuit different from that to which the  receiver is connected.      -- Consult the dealer or an experienced radio/TV technician for help.  FCC Radiation Exposure Statement    This equipment complies with FCC radiation exposure limits set forth for an  uncontrolled environment. This equipment should be installed and operated with  minimum distance 400cm between the radiator & your body.                   BTI  (Shenzhen) Co., Ltd. No.8 Building, Zone #3, Tangtou Industrial Park, Shiyan, Baoan District, Shenzhen, Guangdong P.R.China 518102 Tel: +86 755-2951-2233 Fax: +86 755-2951-2299 E-mail:  chinasales@bravotechinc.com